8757 W HOLLYWOOD BLVD 90069
Certificate Information: 8757 W HOLLYWOOD BLVD 90069
- Application / Permit
- 16010-20003-01394
- Plan Check / Job No.
- B20VN15717
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT FOR 16010-20000-01394 TO RE-DESIGN & ADD PATIO COVER AT ROOF (N) 2-STORY SFD W/ 2-BASEMENT LEVELS & ATTACHED GARAGE CREATING A 3-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- Issued on 6/24/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/7/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/12/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/15/2021 | APPLICANT |
| Applicant returned to address corrections | 3/9/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/11/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 4/8/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/7/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/1/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/1/2021 | NILOOFAR MEHRAIN |
| Issued | 6/24/2021 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/17/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 2/17/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 2/17/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 2/17/2021 | THOMAS LANG |
| Street Frontage | Cleared | 2/17/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 4/12/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 4/14/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 4/28/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | CECILIO NAVARRO |
| Excavation more than 5-ft deep | Cleared | 5/7/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/7/2021 | NILOOFAR MEHRAIN |
| BHO/Hillside ordinance | Cleared | 5/14/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 5/14/2021 | CECILIO NAVARRO |
| Haul Route | Cleared | 6/1/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Koulos Peter Construction; Lic. No.: 456943-B | 292 POMONA AVENUE LONG BEACH, CA 90803 |
| Engineer | Tran,, John Dinh; Lic. No.: C62653 | 11251 GARDENAIRE GARDEN GROVE, CA 92841 |
| Engineer | Tsai, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Fishburn, Scott David; Lic. No.: EG2114 | 1545 VICTORY BLVD. GLENDALE, CA 91201 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Piling/Pier/Caisson | 6/28/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 6/29/2021 | Approved | RONALD KIDWELL |
| Footing/Foundation/Slab | 7/12/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/19/2021 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Reinf. Concrete | 7/19/2021 | Partial Approval | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 7/20/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 7/21/2021 | Conditional Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 8/24/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/24/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Shotcrete | 8/25/2021 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/31/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Shotcrete | 9/1/2021 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 10/12/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 10/12/2021 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 10/13/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/13/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/15/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/26/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 11/2/2021 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 11/2/2021 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 11/3/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 11/3/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 11/12/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 11/16/2021 | Conditional Approval | ROBERT VORHIS |
| Deputy Shotcrete | 11/19/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Shotcrete | 11/23/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/30/2021 | No Access for Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 1/4/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 1/13/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 1/18/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 1/21/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 1/28/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 2/1/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 2/2/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/4/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 2/7/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/11/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 2/14/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 2/16/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/18/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/2/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/4/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/7/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/9/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 6/17/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 7/1/2022 | Conditional Approval | RAUL BARAJAS |