8029 W WILLOW GLEN ROAD 90046
Certificate Information: 8029 W WILLOW GLEN ROAD 90046
- Application / Permit
- 16010-20000-06453
- Plan Check / Job No.
- B16VN18298
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 6/13/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2017 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 1/30/2017 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 2/3/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/6/2017 | APPLICANT |
| Green Plans Picked Up | 2/6/2017 | APPLICANT |
| Applicant returned to address corrections | 3/8/2017 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/13/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/20/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 3/23/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/11/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/29/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/8/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 6/13/2018 | KAMRAN GHOTBI RAVANDI |
| Issued | 6/13/2018 | LADBS |
| Permit Expired-Status Void | 2/7/2020 | RAUL BARAJAS |
| Re-Activate Permit | 2/20/2020 | RAUL BARAJAS |
| CofO in Progress | 2/4/2022 | RAUL BARAJAS |
| Permit Finaled | 2/4/2022 | RONALD MYRICK |
| CofO Issued | 2/4/2022 | RONALD MYRICK |
| Permit Finaled | 2/4/2022 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/14/2017 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2017 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 3/14/2017 | ROBERT DUFF |
| Low Impact Development | Cleared | 5/9/2017 | MARTIN FRAGOSO |
| Permit | Cleared | 2/1/2018 | KAYLA PEJI |
| Miscellaneous | Cleared | 2/7/2018 | STEVEN WECHSLER |
| Roof/Waste drainage to street | Cleared | 3/5/2018 | JOHN LIN |
| Miscellaneous | Cleared | 3/14/2018 | STEVEN WECHSLER |
| Sewer availability | Cleared | 3/15/2018 | JOSEPH RHYU |
| Miscellaneous | Cleared | 3/21/2018 | STEVEN WECHSLER |
| Green Code | Cleared | 5/9/2018 | PARISA ZAHABI |
| Excavation more than 5-ft deep | Cleared | 5/11/2018 | CALOSHA APPROVED |
| BHO/Hillside ordinance | Cleared | 6/13/2018 | CHRISTOPHER LAW |
| BHO/Hillside ordinance | Cleared | 6/13/2018 | CHRISTOPHER LAW |
Contact Information
| Contractor | Jb Home Builders Co; Lic. No.: 619281-B | 6745 DARBY AVENUE RESEDA, CA 91335 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Hill, Thomas George; Lic. No.: EG1100 | 3210 VAL VERDE LONG BEACH, CA 90808 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/17/2018 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 10/3/2018 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/4/2018 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/5/2018 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 11/7/2018 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/7/2018 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/26/2018 | Partial Approval | RAUL BARAJAS |
| Deputy Shotcrete | 11/30/2018 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/7/2018 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 12/7/2018 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/31/2019 | Partial Approval | RAUL BARAJAS |
| Special/Order Compliance | 1/31/2019 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/6/2019 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/19/2019 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 2/28/2019 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/1/2019 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 3/1/2019 | Partial Approval | RAUL BARAJAS |
| Special/Order Compliance | 3/26/2019 | Partial Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2019 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/3/2019 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2019 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/6/2019 | Partial Inspection | RAUL BARAJAS |
| HVAC-Rough | 6/6/2019 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 6/6/2019 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/10/2019 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 6/10/2019 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 6/10/2019 | Approved | RAUL BARAJAS |
| Shower Pan | 6/17/2019 | Approved | RAUL BARAJAS |
| Drywall Nailing | 6/21/2019 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/21/2019 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/26/2019 | Approved | RAUL BARAJAS |
| HVAC-Rough | 6/26/2019 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/26/2019 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 6/26/2019 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 7/31/2019 | Partial Inspection | RAUL BARAJAS |
| Sewer | 12/5/2019 | Approved | RAUL BARAJAS |
| HVAC-Final | 1/16/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 1/16/2020 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 2/6/2020 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 3/20/2020 | Approved | RAUL BARAJAS |
| Service/Power Release | 3/20/2020 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 12/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 12/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 12/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 12/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 12/23/2021 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/20/2022 | Approved | RAUL BARAJAS |
| Final | 1/20/2022 | OK to Issue CofO | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/20/2022 | Approved | RAUL BARAJAS |
| Green Building Final | 1/20/2022 | Approved | RAUL BARAJAS |
| Reinforced Concrete Frame | 1/20/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 1/20/2022 | Approved | RAUL BARAJAS |