1111 N ECHO PARK AVE 1-11 90026

Certificate Information: 1111 N ECHO PARK AVE 1-11 90026

Application / Permit
16010-20000-06449
Plan Check / Job No.
B16VN18289
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
APARTMENT HOUSE OVER FIRST FLOOR GARAGE.
Permit Issued
Issued on 12/28/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2016 APPLICANT
Disabled Access Plans Picked Up 1/23/2017 APPLICANT
Green Plans Picked Up 1/23/2017 APPLICANT
Assigned to Plan Check Engineer 1/26/2017 RUDOLF KINAR MELIKOFF
Corrections Issued 1/30/2017 RUDOLF KINAR MELIKOFF
Quality Review Completed 2/2/2017 TIEN JEN WANG
Building Plans Picked Up 2/10/2017 APPLICANT
Applicant returned to address corrections 8/31/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 10/29/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 11/19/2018 RUDOLF KINAR MELIKOFF
Plan Check Approved 12/28/2018 RUDOLF KINAR MELIKOFF
Issued 12/28/2018 LADBS
CofO in Progress 3/16/2022 RAFAEL ESPINOZA
Permit Finaled 3/30/2022 ERNESTO CORRAL
CofO Issued 3/30/2022 ERNESTO CORRAL
Permit Finaled 3/30/2022 ERNESTO CORRAL

Permit Application Clearance Information

Permit Cleared 6/28/2018 EDUARDO PEDROZA
Address approval Cleared 6/29/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 6/29/2018 NAZILA NOORIFAR
Highway dedication Cleared 6/29/2018 NAZILA NOORIFAR
Sewer availability Cleared 6/29/2018 NAZILA NOORIFAR
Green Code Cleared 7/5/2018 ROLLIN GETTLE III
Hydrant and Access approval Cleared 7/5/2018 GILBERT URREA
Frnt yard landscape/Water mgmt Cleared 7/11/2018 RINA LARA
Opn space landscape/Water mgmt Cleared 7/11/2018 RINA LARA
Grading Pre-Inspection Cleared 7/25/2018 JOHN YAKUBYAN
Low Impact Development Cleared 10/5/2018 MATTHEW JIMENEZ
DAS Clearance Cleared 10/17/2018 HAYATO TSUCHIYA
DAS Clearance Cleared 10/17/2018 NORLITO MEDRANO
DAS Clearance Cleared 10/17/2018 RUDOLF KINAR MELIKOFF
Fire Marshall Fire Life Safety Cleared 11/2/2018 OSCAR SALGADO JR
Driveway location Cleared 12/11/2018 MOHAMMAD HASAN
Internal circulation Cleared 12/11/2018 MOHAMMAD HASAN
Roof/Waste drainage to street Cleared 12/21/2018 JEANETTE VONG
Supp. Use District POD/CDO/TDO Cleared 12/21/2018 NORA DRESSER
ZI Cleared 12/21/2018 NORA DRESSER

Contact Information

Architect Jazayeri, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/7/2019 Approved ERNESTO CORRAL
Footing/Foundation/Slab 5/7/2019 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 5/9/2019 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 5/21/2019 Partial Inspection ERNESTO CORRAL
Masonry Wall/Backfill 5/22/2019 Partial Inspection ERNESTO CORRAL
Green Building Rough 5/30/2019 Approved ERNESTO CORRAL
Masonry Wall/Backfill 5/30/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 5/30/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 5/30/2019 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/31/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/12/2019 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 6/26/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 6/26/2019 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 8/23/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 8/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/26/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 9/20/2019 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Partial Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 11/22/2019 Approved ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 2/3/2020 Approved EDWIN GREGORYONA
Deputy Wood Construction 2/25/2020 Conditional Approval ERNESTO CORRAL
Wood Frame 2/25/2020 Partial Inspection ERNESTO CORRAL
Interior/Exterior Lathing 2/26/2020 Partial Inspection ERNESTO CORRAL
Pre-Inspection 2/26/2020 Approved ERNESTO CORRAL
Verify Sprinkler Sign Off 2/27/2020 Not Ready for Inspection ERNESTO CORRAL
Wood Frame 2/27/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 3/3/2020 Conditional Approval ERNESTO CORRAL
Insulation 3/18/2020 Partial Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 3/18/2020 Conditional Approval LESLIE TRUJILLO
Wood Frame 3/18/2020 Partial Inspection LESLIE TRUJILLO
Insulation 3/20/2020 Partial Approval DAVID BURKHEAD
Drywall Nailing 3/31/2020 Partial Inspection ERNESTO CORRAL
Drywall Nailing 4/2/2020 Partial Inspection ERNESTO CORRAL
Interior/Exterior Lathing 4/3/2020 Partial Inspection ERNESTO CORRAL
Interior/Exterior Lathing 4/10/2020 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 4/16/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/16/2020 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 4/27/2020 Approved RAFAEL ESPINOZA
Special/Order Compliance 5/8/2020 Approved RAFAEL ESPINOZA
Drywall Nailing 9/4/2020 Approved NICK DANERI
Final 9/4/2020 Not Ready for Inspection NICK DANERI
Green Building Final 9/4/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/4/2020 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 9/4/2020 SGSOV Not Ready NICK DANERI
Smoke Detectors 9/4/2020 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 9/4/2020 Not Ready for Inspection NICK DANERI
Wood Frame 9/4/2020 Not Ready for Inspection NICK DANERI
Final 6/10/2021 Corrections Issued RAFAEL ESPINOZA
Green Building Final 6/10/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/10/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 6/10/2021 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/10/2021 Approved RAFAEL ESPINOZA
Wood Frame 6/10/2021 Not Ready for Inspection RAFAEL ESPINOZA
Final 6/23/2021 Corrections Issued RAFAEL ESPINOZA
Green Building Final 6/23/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/23/2021 Approved RAFAEL ESPINOZA
Wood Frame 6/23/2021 Approved RAFAEL ESPINOZA
Final 6/25/2021 Corrections Issued RAFAEL ESPINOZA
Green Building Final 6/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
Final 7/13/2021 Partial Inspection RAFAEL ESPINOZA
Green Building Final 7/13/2021 Approved RAFAEL ESPINOZA
Final 7/28/2021 Not Ready for Inspection JONATHAN QUACH
Final 8/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Final 9/13/2021 Partial Inspection RAFAEL ESPINOZA
Final 1/26/2022 Conditional Approval RAFAEL ESPINOZA