3148 N FLOYE DR 90046

Certificate Information: 3148 N FLOYE DR 90046

Application / Permit
16010-20000-06422
Plan Check / Job No.
B16VN18249
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW IRR SHAPED 2-STORY SFD OVER BASEMENT 2- CAR GARAGE & REC RM W/ MECH RM. ROOF DECK OVER FIRST FLR LIVING ROOM AREA. SEE COMMENTS.
Permit Issued
Issued on 11/27/2018
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2016 APPLICANT
Green Plans Picked Up 2/10/2017 APPLICANT
Assigned to Plan Check Engineer 2/23/2017 HAYATO TSUCHIYA
Corrections Issued 3/23/2017 HAYATO TSUCHIYA
Quality Review Completed 3/29/2017 ABDUL CHEGENI
Building Plans Picked Up 4/6/2017 APPLICANT
Applicant returned to address corrections 11/22/2017 HAYATO TSUCHIYA
Applicant returned to address corrections 12/21/2017 HAYATO TSUCHIYA
Applicant returned to address corrections 4/19/2018 HAYATO TSUCHIYA
Applicant returned to address corrections 11/15/2018 HAYATO TSUCHIYA
Plan Check Approved 11/16/2018 HAYATO TSUCHIYA
Plan Check Approved 11/20/2018 HAYATO TSUCHIYA
Issued 11/27/2018 LADBS
CofO in Progress 8/31/2022 BRIAN SULLIVAN
Permit Finaled 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/23/2017 HAYATO TSUCHIYA
BHO/Hillside ordinance Cleared 12/21/2017 EDUARDO PEDROZA
BHO/Hillside ordinance Cleared 12/21/2017 EDUARDO PEDROZA
Eng Process Fee Ord 176,300 Cleared 12/21/2017 EDUARDO PEDROZA
Permit Cleared 12/21/2017 EDUARDO PEDROZA
Sewer availability Cleared 12/21/2017 EDUARDO PEDROZA
Work Adjacent to Public Way Cleared 12/21/2017 EDUARDO PEDROZA
Hydrant and Access approval Cleared 2/21/2018 JOHN DALLAS
Green Code Cleared 2/23/2018 ROLLIN GETTLE III
BHO/Hillside ordinance Cleared 2/26/2018 MICHAEL CASTILLO
Highway dedication Cleared 2/26/2018 MICHAEL CASTILLO
GPI Written Notices Cleared 5/1/2018 HAYATO TSUCHIYA
Low Impact Development Cleared 5/17/2018 RYAN HUDSON
Metro Rail approval Cleared 5/23/2018 HAYATO TSUCHIYA
Miscellaneous Cleared 6/8/2018 RINA LARA
Specific Plan Cleared 6/8/2018 RINA LARA
Disturb/Remove Protected Trees Cleared 11/14/2018 LUIS TORRES
Encroachment in public way Cleared 11/14/2018 KARAN PATEL
Roof/Waste drainage to street Cleared 11/15/2018 RUDY TERRIQUEZ.

Contact Information

Contractor Owner-Builder       ,
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2019 Partial Inspection RAUL BARAJAS
Protected Tree Letter 10/4/2019 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/7/2019 No Access for Inspection RAUL BARAJAS
Footing/Foundation/Slab 10/8/2019 Partial Approval BRIAN SULLIVAN
Protected Tree Letter 10/8/2019 Partial Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 11/19/2019 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 12/5/2019 Partial Approval RAUL BARAJAS
Protected Tree Letter 12/5/2019 Not Ready for Inspection RAUL BARAJAS
Reinforced Masonry Frame 12/5/2019 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/10/2020 Partial Approval BRIAN SULLIVAN
Underground Mechanical 1/22/2020 No Access for Inspection RAUL BARAJAS
Footing/Foundation/Slab 1/24/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 1/24/2020 Partial Approval BRIAN SULLIVAN
Protected Tree Letter 1/24/2020 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 1/27/2020 Approved RAUL BARAJAS
Piling/Pier/Caisson 3/20/2020 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 4/8/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 4/14/2020 Conditional Approval RAUL BARAJAS
Underground Mechanical 4/24/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/8/2020 Approved RAUL BARAJAS
Underground Mechanical 5/22/2020 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/3/2020 No Access for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/8/2020 Approved RAUL BARAJAS
Deputy Steel/Welding 6/22/2020 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/29/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Partial Inspection RAUL BARAJAS
Grounding or Bonding 9/10/2020 Not Ready for Inspection RAUL BARAJAS
Pool Piping 9/10/2020 Not Ready for Inspection RAUL BARAJAS
Pre-Gunite 9/10/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 9/16/2020 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Corrections Issued RAUL BARAJAS
Pre-Inspection 11/4/2020 Partial Inspection RAUL BARAJAS
Underground Mechanical 12/3/2020 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/14/2020 Not Ready for Inspection RAUL BARAJAS
Grounding or Bonding 12/14/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 12/14/2020 Partial Approval RAUL BARAJAS
Pre-Inspection 4/30/2021 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 5/21/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 5/21/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 5/21/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 5/21/2021 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 5/21/2021 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 6/17/2021 Partial Inspection RAUL BARAJAS
Pre-Inspection 6/30/2021 Not Ready for Inspection JOSEPH MCGARRY
Special/Order Compliance 6/30/2021 Partial Approval JOSEPH MCGARRY
Pre-Inspection 7/2/2021 Not Ready for Inspection RICHARD STEINBACH
Pre-Inspection 7/14/2021 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 7/16/2021 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 7/16/2021 Not Ready for Inspection RAUL BARAJAS
Wood Frame 7/16/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 7/22/2021 Partial Inspection RAUL BARAJAS
Pre-Inspection 7/22/2021 Partial Approval RAUL BARAJAS
Wood Frame 7/22/2021 Not Ready for Inspection RAUL BARAJAS
Gas Test 8/27/2021 Approved RAUL BARAJAS
PLUMBING-Rough 8/27/2021 Approved RAUL BARAJAS
Service/Power Release 8/27/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 9/3/2021 Approved RAUL BARAJAS
Gas Test 10/6/2021 Approved RAUL BARAJAS
Gas Test 10/7/2021 Approved RAUL BARAJAS
HVAC-Rough 10/8/2021 No Access for Inspection RAUL BARAJAS
HVAC-Rough 10/12/2021 Corrections Issued RAUL BARAJAS
Masonry Wall/Backfill 10/21/2021 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 11/8/2021 Not Ready for Inspection RAUL BARAJAS
Shower Pan 11/8/2021 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 11/10/2021 Not Ready for Inspection MASHEL JONGERT
Shower Pan 11/10/2021 Approved MASHEL JONGERT
Interior/Exterior Lathing 11/16/2021 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 11/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Insulation 11/23/2021 Not Ready for Inspection RAUL BARAJAS
Insulation 12/1/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 1/11/2022 Approved RAUL BARAJAS
Drywall Nailing 1/11/2022 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 1/11/2022 Approved RAUL BARAJAS
Green Building Rough 1/11/2022 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 1/11/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 2/9/2022 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 3/3/2022 Approved RAUL BARAJAS
Pre-Inspection 6/13/2022 Not Ready for Inspection BRIAN SULLIVAN
Pre-Inspection 6/15/2022 Partial Inspection RAUL BARAJAS
Gas Test 6/30/2022 Approved BRIAN SULLIVAN
Service/Power Release 6/30/2022 Approved BRIAN SULLIVAN
Final 7/21/2022 Partial Inspection RAUL BARAJAS
Green Building Final 7/21/2022 Not Ready for Inspection RAUL BARAJAS
Pre-Inspection 7/21/2022 Partial Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 7/21/2022 Approved RAUL BARAJAS
Pre-Inspection 8/10/2022 No Access for Inspection RAUL BARAJAS
Pre-Inspection 8/11/2022 Partial Inspection RAUL BARAJAS
ELECTRICAL-Final 8/29/2022 Approved BRIAN SULLIVAN
Final 8/29/2022 OK to Issue CofO BRIAN SULLIVAN
Green Building Final 8/29/2022 Approved BRIAN SULLIVAN
HVAC-Final 8/29/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 8/29/2022 Approved BRIAN SULLIVAN