6815 N CANOGA AVE 91303

Certificate Information: 6815 N CANOGA AVE 91303

Application / Permit
16010-20000-06384
Plan Check / Job No.
B16VN18209
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED MIX-USE 6 STORY 154 UNIT APARTMENT OVER 2 LEVEL BASEMENT BELOW.
Permit Issued
Issued on 8/10/2022
Issuing Office
Valley
Current Status
Issued on 8/10/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/29/2016 APPLICANT
Disabled Access Plans Picked Up 2/13/2017 APPLICANT
Green Plans Picked Up 2/13/2017 APPLICANT
Assigned to Plan Check Engineer 2/23/2017 KAMRAN GHOTBI RAVANDI
Corrections Issued 3/6/2017 KAMRAN GHOTBI RAVANDI
Quality Review Completed 3/10/2017 TIEN JEN WANG
Applicant returned to address corrections 5/22/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/25/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/8/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/17/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/23/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/6/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/27/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/6/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/15/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/26/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/26/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/3/2022 SERGIO SILVA
Plan Check Approved 6/9/2022 SERGIO SILVA
Building Plans Picked Up 6/15/2022 APPLICANT
Issued 8/10/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/27/2017 JOSEPH RHYU
Low Impact Development Cleared 6/6/2018 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 9/26/2018 MICHAEL CASTILLO
Highway dedication Cleared 9/26/2018 MICHAEL CASTILLO
Green Code Cleared 10/10/2018 MICHAEL AYERS
Hydrant and Access approval Cleared 10/24/2018 JOHN DALLAS
Fire Marshall Fire Life Safety Cleared 12/12/2018 OSCAR SALGADO JR
Metro Rail approval Cleared 1/8/2019 KAMRAN GHOTBI RAVANDI
Sewer availability Cleared 1/14/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 1/16/2019 MARKOS PEREZ-BRAN
Driveway location Cleared 1/30/2019 KEN AITCHISON
Internal circulation Cleared 1/30/2019 KEN AITCHISON
DAS Clearance Cleared 9/9/2019 NORLITO MEDRANO
CPC Cleared 2/6/2020 SARAH GOLDMAN
Miscellaneous Cleared 2/6/2020 SARAH GOLDMAN
Specific Plan Cleared 2/6/2020 SARAH GOLDMAN
ZA Case Cleared 2/6/2020 SARAH GOLDMAN
ZA Case Cleared 2/6/2020 SARAH GOLDMAN
"Q" conditions Cleared 3/11/2020 SARAH GOLDMAN
Site Plan review Cleared 3/11/2020 SARAH GOLDMAN
ZI Cleared 3/11/2020 SARAH GOLDMAN
Permit Cleared 3/19/2020 GABRIEL ROBLES
Building over 3-story or 36-ft Cleared 5/2/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/5/2022 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 5/19/2022 LEE GUILBEAUX
Encroachment in public way Cleared 5/20/2022 LEE GUILBEAUX

Contact Information

Architect Stockton, Kenneth; Lic. No.: C19870 26500 W AGOURA RD. PMB # 844      CALABASAS, CA 91302
Contractor Associated Construction Llc; Lic. No.: 1070625-B 6245 WILSHIRE BLVD UNIT 710      LOS ANGELES, CA 90048
Engineer Choi, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 9/20/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/22/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/26/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/28/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/29/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/31/2023 Conditional Approval CAMERON CHABAN
Pre-Inspection 2/1/2023 Partial Inspection CAMERON CHABAN
Drywall Nailing 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Final 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Final 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Masonry Frame 3/4/2024 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 3/4/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 5/2/2024 Approved ROBERT DAVIS
Deputy Shotcrete 5/2/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 5/2/2024 Approved ROBERT DAVIS
Deputy Reinf. Concrete 5/3/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 5/3/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 5/6/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 5/7/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 5/7/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 5/8/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/9/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 5/9/2024 Partial Approval ROBERT DAVIS
Special/Order Compliance 5/9/2024 Partial Inspection BRIAN KELLY
Deputy Reinf. Concrete 5/10/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 5/10/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 5/13/2024 Approved ROBERT DAVIS
Deputy Shotcrete 5/13/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 5/16/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/21/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 5/23/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/12/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/14/2024 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 6/20/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/28/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/28/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/1/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/12/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/15/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/15/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/16/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/26/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/29/2024 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 7/30/2024 Approved ROBERT DAVIS
Deputy Reinf. Concrete 7/30/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/30/2024 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 7/30/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 8/6/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/6/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 8/7/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/7/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 8/8/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/8/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 8/9/2024 Approved ROBERT DAVIS
Deputy Shotcrete 8/16/2024 Conditional Approval GREGORY POMISH
Deputy Shotcrete 8/19/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 8/20/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 8/22/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/22/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 8/23/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/23/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 8/26/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 8/27/2024 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 8/28/2024 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 8/29/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/29/2024 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/30/2024 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/3/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 9/4/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/4/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 9/5/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 9/5/2024 Partial Approval ROBERT DAVIS
Special/Order Compliance 9/5/2024 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Verify Sprinkler Sign Off 9/5/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 9/6/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/6/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 9/9/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/9/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 9/10/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/10/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 9/11/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/11/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 9/12/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 10/11/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 10/15/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 10/25/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/5/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 11/5/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/5/2024 Partial Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/6/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 11/7/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/7/2024 Not Ready for Inspection ROBERT DAVIS
Deputy Drilled-In Anchors 11/14/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 11/22/2024 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 11/26/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 11/27/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 12/2/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 12/13/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/13/2024 Partial Inspection ROBERT DAVIS
Deputy Shotcrete 12/16/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/17/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 12/18/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 12/19/2024 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/19/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 12/20/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 12/23/2024 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 1/2/2025 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 1/6/2025 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 1/10/2025 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/13/2025 Partial Approval ROBERT DAVIS
Deputy Shotcrete 1/14/2025 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 1/15/2025 Conditional Approval ROBERT DAVIS
Deputy Shotcrete 1/16/2025 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 1/24/2025 Approved ROBERT DAVIS
Structural Steel Frame 1/24/2025 Partial Approval ROBERT DAVIS
Deputy Steel/Welding 1/27/2025 Approved ROBERT DAVIS
Special/Order Compliance 1/27/2025 Partial Inspection ROBERT DAVIS
Deputy Drilled-In Anchors 1/30/2025 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 2/12/2025 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 2/25/2025 Conditional Approval ROBERT DAVIS
Special/Order Compliance 2/27/2025 Partial Inspection ROBERT DAVIS
Deputy Reinf. Concrete 3/6/2025 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/7/2025 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 3/7/2025 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 3/8/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 3/10/2025 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/11/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/12/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/13/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/14/2025 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 3/17/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/18/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/19/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/20/2025 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 3/24/2025 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 3/28/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/28/2025 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 3/29/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 4/1/2025 Conditional Approval ROBERT DAVIS
Drywall Nailing 4/24/2025 Partial Approval GREGORY POMISH
Green Building Rough 4/24/2025 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 5/2/2025 Conditional Approval ROBERT DAVIS
Special/Order Compliance 5/5/2025 Partial Inspection ROBERT DAVIS
Footing/Foundation/Slab 5/6/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/7/2025 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 5/14/2025 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 5/21/2025 Approved ROBERT DAVIS
Footing/Foundation/Slab 5/21/2025 Partial Approval ROBERT DAVIS
Deputy Wood Construction 6/4/2025 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/6/2025 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/10/2025 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 6/20/2025 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 6/23/2025 Partial Approval ROBERT DAVIS
Deputy Wood Construction 6/24/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 No Access for Inspection ROBERT DAVIS
Green Building Rough 6/27/2025 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 6/27/2025 Not Ready for Inspection ROBERT DAVIS
Wood Frame 6/27/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/3/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Not Ready for Inspection ROBERT DAVIS
Deputy Wood Construction 7/15/2025 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Partial Approval ROBERT DAVIS
Deputy Wood Construction 7/29/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval ROBERT DAVIS
Deputy Wood Construction 8/13/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 8/29/2025 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 9/2/2025 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 9/3/2025 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 9/5/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 9/8/2025 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 9/8/2025 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 9/10/2025 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Partial Approval ROBERT DAVIS
Deputy Wood Construction 9/16/2025 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 9/17/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/18/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 9/19/2025 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 9/24/2025 Partial Approval ROBERT DAVIS
Deputy Wood Construction 9/25/2025 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/6/2025 Conditional Approval ROBERT DAVIS
Green Building Rough 10/10/2025 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 10/10/2025 Partial Approval ROBERT DAVIS
Wood Frame 10/10/2025 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 10/17/2025 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 11/3/2025 Conditional Approval GREGORY POMISH
Green Building Rough 11/4/2025 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 11/4/2025 Partial Inspection GREGORY POMISH
Wood Frame 11/4/2025 Partial Inspection GREGORY POMISH
Deputy Wood Construction 11/10/2025 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 11/12/2025 Conditional Approval GREGORY POMISH
Green Building Rough 11/13/2025 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 11/13/2025 Partial Inspection GREGORY POMISH
Wood Frame 11/13/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 11/20/2025 Conditional Approval GREGORY POMISH
Green Building Rough 11/26/2025 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 11/26/2025 Partial Inspection GREGORY POMISH
Wood Frame 11/26/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 12/4/2025 Conditional Approval GREGORY POMISH
Green Building Rough 12/4/2025 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 12/4/2025 Partial Inspection GREGORY POMISH
Wood Frame 12/4/2025 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 1/5/2026 Approved ROBERT DAVIS
Deputy Drilled-In Anchors 1/7/2026 Partial Approval ROBERT DAVIS
Green Building Rough 1/8/2026 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 1/8/2026 Not Ready for Inspection ROBERT DAVIS
Wood Frame 1/8/2026 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 1/9/2026 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 1/13/2026 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 1/15/2026 Approved ROBERT DAVIS
Green Building Rough 1/21/2026 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 1/21/2026 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 1/21/2026 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 1/26/2026 Conditional Approval ROBERT DAVIS
Special/Order Compliance 2/19/2026 Partial Inspection ROBERT DAVIS
Deputy Drilled-In Anchors 3/3/2026 Conditional Approval ROBERT DAVIS
Green Building Rough 3/5/2026 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 3/5/2026 Partial Inspection GREGORY POMISH
Wood Frame 3/5/2026 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 3/13/2026 Conditional Approval ROBERT DAVIS
Green Building Rough 3/17/2026 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 3/17/2026 Not Ready for Inspection ROBERT DAVIS
Wood Frame 3/17/2026 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/27/2026 Conditional Approval ROBERT DAVIS