644 3/4 N COMMONWEALTH AVE 90004
Certificate Information: 644 3/4 N COMMONWEALTH AVE 90004
- Application / Permit
- 16010-20000-06306
- Plan Check / Job No.
- B16VN18151
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- "Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-73859. A certificate of occupancy (temporary or final ) shall not be issued until after the final map has been recorded." NEW 3- STORY 22'-7" X 34' SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ROOF DECK; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGH OUT
- Permit Issued
- Issued on 6/1/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/27/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2017 | SELLA BENYAMIN |
| Corrections Issued | 1/25/2017 | SELLA BENYAMIN |
| Quality Review Completed | 1/25/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/6/2017 | APPLICANT |
| Green Plans Picked Up | 2/6/2017 | APPLICANT |
| Plan Check Approved | 1/30/2018 | SELLA BENYAMIN |
| Issued | 6/1/2018 | LADBS |
| CofO in Progress | 8/19/2020 | SCOTT FINNILA |
| Permit Finaled | 8/27/2020 | DEROLD HAUFF |
| CofO Issued | 8/27/2020 | DEROLD HAUFF |
| Permit Finaled | 8/27/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/21/2017 | ROBERT DUFF |
| Address approval | Cleared | 9/20/2017 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2017 | STEVE MELGAR |
| Permit | Cleared | 9/20/2017 | STEVE MELGAR |
| Sewer availability | Cleared | 9/20/2017 | STEVE MELGAR |
| Frnt yard landscape/Water mgmt | Cleared | 10/31/2017 | NOAH MCCOY |
| Miscellaneous | Cleared | 10/31/2017 | NOAH MCCOY |
| Tract Map conditions | Cleared | 10/31/2017 | NOAH MCCOY |
| Low Impact Development | Cleared | 12/1/2017 | MARTIN FRAGOSO |
| Highway dedication | Cleared | 12/4/2017 | LINDA MARGARET |
| Miscellaneous | Cleared | 12/4/2017 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 12/4/2017 | LINDA MARGARET |
| Green Code | Cleared | 12/11/2017 | MICKEY YAMASHITA |
Contact Information
| Contractor | Cambridge Homes; Lic. No.: 736218-B | 41197 GOLDEN GATE CIR STE 201 MURRIETA, CA 92562 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/28/2018 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 11/1/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/5/2018 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 11/9/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/19/2018 | Corrections Issued | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 11/21/2018 | Approved | SCOTT FINNILA |
| Final | 11/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/21/2018 | Approved | SCOTT FINNILA |
| Green Building Final | 11/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Green Building Rough | 11/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2018 | SGSOV Not Ready | SCOTT FINNILA |
| Service/Power Release | 11/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Smoke Detectors | 11/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 11/21/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 12/11/2018 | Approved | MICHAEL FAUNCE |
| Drywall Nailing | 12/13/2018 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 12/13/2018 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2018 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 1/22/2019 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 1/22/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 2/27/2019 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 2/27/2019 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 2/27/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2019 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 8/12/2019 | Partial Approval | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 8/12/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 9/18/2019 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/1/2019 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/1/2019 | Approved | SCOTT FINNILA |
| Green Building Rough | 11/1/2019 | Approved | SCOTT FINNILA |
| HVAC-Rough | 11/1/2019 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 11/1/2019 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 11/1/2019 | Approved | SCOTT FINNILA |
| Insulation | 11/7/2019 | Approved | MICHAEL FAUNCE |
| Drywall Nailing | 11/20/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 11/21/2019 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 11/21/2019 | Partial Approval | SCOTT FINNILA |
| Gas Test | 2/10/2020 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/24/2020 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 3/10/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Final | 6/29/2020 | Partial Approval | SCOTT FINNILA |
| Gas Test | 6/29/2020 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 7/7/2020 | Approved | SCOTT FINNILA |
| HVAC-Final | 7/7/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 7/7/2020 | Approved | SCOTT FINNILA |
| Service/Power Release | 7/7/2020 | Corrections Issued | SCOTT FINNILA |
| Final | 7/29/2020 | Partial Inspection | SCOTT FINNILA |
| Green Building Final | 7/29/2020 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2020 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 7/29/2020 | Partial Inspection | SCOTT FINNILA |
| Smoke Detectors | 7/29/2020 | Approved | SCOTT FINNILA |
| Service/Power Release | 8/3/2020 | Approved | SCOTT FINNILA |
| Final | 8/19/2020 | OK to Issue CofO | SCOTT FINNILA |