Green Building Rough
|
8/5/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
8/5/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
8/5/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
8/13/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
8/13/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
8/13/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/22/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
8/22/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/26/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
8/26/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
9/18/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
9/18/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
9/18/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
9/25/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
9/25/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
9/25/2019
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
9/30/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
9/30/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
9/30/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
10/4/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/4/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/4/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
10/9/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/9/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/9/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
10/15/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/15/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/15/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
10/18/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/18/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/18/2019
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
10/23/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/23/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/23/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
10/29/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/29/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/29/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
10/31/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/31/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/31/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
11/5/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
11/5/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
11/5/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
11/7/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
11/7/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
11/7/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
11/12/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
11/12/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
11/12/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
11/15/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
11/15/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
11/15/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
11/26/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
11/26/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
11/26/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
12/2/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/2/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/2/2019
|
Corrections Issued
|
JOHN KITCKO
|
|
Green Building Rough
|
12/4/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/4/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/4/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
12/12/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/12/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/12/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/16/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
12/17/2019
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
12/20/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/20/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/20/2019
|
Corrections Issued
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
12/31/2019
|
Corrections Issued
|
JOHN KITCKO
|
|
T-Bar Ceiling
|
12/31/2019
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
1/2/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
1/3/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
1/7/2020
|
Conditional Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
1/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
1/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
1/9/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
1/13/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
1/13/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
1/13/2020
|
Corrections Issued
|
JOHN KITCKO
|
|
Green Building Rough
|
1/15/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
1/15/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
1/15/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
1/21/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
1/21/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
1/23/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
1/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
1/23/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
1/27/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
1/27/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
1/27/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
1/28/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
1/29/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
1/29/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
1/29/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
1/29/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
1/31/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
1/31/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
2/3/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/4/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
2/4/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
2/4/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/7/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
2/7/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/14/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
2/14/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/20/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
2/20/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
2/26/2020
|
No Access for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/27/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
2/27/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/12/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/12/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/12/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/16/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/16/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/16/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/19/2020
|
Approved
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
3/19/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/19/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/19/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/25/2020
|
Approved
|
JOHN KITCKO
|
|
Wood Frame
|
3/25/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
3/26/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/27/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
4/1/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
4/7/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
4/10/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
4/13/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
4/13/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
4/14/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
4/14/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
4/15/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
4/17/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
4/22/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
4/28/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
4/28/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
5/4/2020
|
Corrections Issued
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/5/2020
|
Partial Approval
|
JOHN KITCKO
|
|
T-Bar Ceiling
|
5/7/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/13/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/25/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Final
|
8/25/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Footing/Foundation/Slab
|
8/25/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Green Building Final
|
8/25/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Reinforced Concrete Frame
|
8/25/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Reinforced Masonry Frame
|
8/25/2020
|
Approved
|
HAMID PISHEHVAR
|
|
SGSOV-Seismic Gas S/O Valve
|
8/25/2020
|
SGSOV Approved
|
HAMID PISHEHVAR
|
|
Smoke Detectors
|
8/25/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Wood Frame
|
8/25/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Final
|
8/27/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
8/27/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Final
|
9/9/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
9/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
9/10/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
9/14/2020
|
Corrections Issued
|
JOHN KITCKO
|
|
Green Building Final
|
9/14/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Final
|
9/16/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
9/16/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
9/22/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
9/22/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
9/23/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
9/24/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
9/28/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
9/28/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
10/2/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Green Building Final
|
10/2/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Special/Order Compliance
|
10/6/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
10/7/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
10/7/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Final
|
10/9/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
10/9/2020
|
Conditional Approval
|
JOHN KITCKO
|
|
Special/Order Compliance
|
10/13/2020
|
No Access for Inspection
|
JOHN KITCKO
|
|
Final
|
10/14/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
10/14/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Final
|
10/16/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
10/16/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Rec and Parks Fee Memo
|
3/17/2021
|
Partial Inspection
|
JOHN KITCKO
|
|
Final
|
5/19/2021
|
OK to Issue CofO
|
JEFFREY DURAN
|
|
Green Building Final
|
5/19/2021
|
Approved
|
JEFFREY DURAN
|