Special/Order Compliance
|
5/29/2018
|
Partial Inspection
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
2/1/2019
|
Corrections Issued
|
JEFFREY DURAN
|
|
Pre-Inspection
|
2/1/2019
|
Approved
|
JEFFREY DURAN
|
|
Wood Frame
|
2/12/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Footing/Foundation/Slab
|
2/20/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
6/5/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Footing/Foundation/Slab
|
6/6/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
6/7/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
6/14/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
6/17/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
6/17/2019
|
Partial Approval
|
MILLARD ARDOIN
|
|
Deputy Reinf. Concrete
|
6/19/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Deputy Shotcrete
|
6/21/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Deputy Shotcrete
|
6/24/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
6/25/2019
|
Approved
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/25/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
6/26/2019
|
Approved
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/26/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
6/27/2019
|
Approved
|
JEFFREY DURAN
|
|
Green Building Rough
|
6/27/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Reinforced Concrete Frame
|
6/27/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Verify Sprinkler Sign Off
|
6/27/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
6/28/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
6/28/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/19/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/23/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Excavation/Setback/Form/Re-Bar
|
7/26/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/6/2019
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Deputy Shotcrete
|
8/8/2019
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
8/8/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
8/13/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
8/14/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
8/15/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
8/15/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
8/16/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
8/20/2019
|
Approved
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
8/20/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
8/23/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
9/6/2019
|
Corrections Issued
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
9/9/2019
|
Conditional Approval
|
JAMES STEPHENS
|
|
Excavation/Setback/Form/Re-Bar
|
9/10/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
9/19/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
9/20/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
9/25/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
9/26/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
9/27/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/4/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/8/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/21/2019
|
Partial Inspection
|
JEFFREY DURAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/22/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
10/23/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Wood Frame
|
11/12/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
11/14/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
11/19/2019
|
Conditional Approval
|
RICKEY JACKSON
|
|
Wood Frame
|
11/21/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
11/27/2019
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
11/27/2019
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Wood Frame
|
11/27/2019
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Insulation
|
12/4/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Insulation
|
12/9/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
12/12/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Wood Frame
|
12/13/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
12/17/2019
|
Conditional Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
12/17/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Green Building Rough
|
12/17/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
12/19/2019
|
Approved
|
JEFFREY DURAN
|
|
Drywall Nailing
|
12/19/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
12/19/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/26/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
12/26/2019
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Insulation
|
12/27/2019
|
Partial Approval
|
JEFFREY DURAN
|
|
Special/Order Compliance
|
12/27/2019
|
Corrections Issued
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
1/13/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
1/21/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
1/23/2020
|
Conditional Approval
|
JAMES STEPHENS
|
|
Drywall Nailing
|
1/24/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
1/24/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Wood Frame
|
1/24/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
2/5/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
2/5/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
2/7/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
2/11/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/14/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Masonry Wall/Backfill
|
2/14/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Deputy Wood Construction
|
2/19/2020
|
Approved
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/19/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Masonry Wall/Backfill
|
2/19/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Drywall Nailing
|
2/20/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/20/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
2/20/2020
|
Partial Inspection
|
JEFFREY DURAN
|
|
Insulation
|
2/25/2020
|
Not Ready for Inspection
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
3/6/2020
|
Approved
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Wood Construction
|
3/25/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2020
|
Conditional Approval
|
CAMERON CHABAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
3/31/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Insulation
|
4/1/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Special/Order Compliance
|
4/1/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
4/10/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Insulation
|
4/14/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Wood Construction
|
4/17/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/21/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/23/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Insulation
|
4/23/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/24/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
4/24/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/27/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
4/30/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
4/30/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
5/4/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
5/4/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Wood Construction
|
5/5/2020
|
Conditional Approval
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/5/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
5/5/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
5/6/2020
|
Partial Inspection
|
DANIEL VARNUM
|
|
Green Building Rough
|
5/6/2020
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Wood Frame
|
5/8/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Wood Construction
|
5/12/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Drywall Nailing
|
5/12/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
5/12/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
5/13/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/13/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
5/19/2020
|
Partial Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2020
|
Partial Approval
|
ROBERT COLE
|
|
Green Building Rough
|
5/19/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Wood Frame
|
5/19/2020
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Wood Construction
|
5/20/2020
|
Approved
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/20/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Insulation
|
5/20/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/21/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
5/21/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Special/Order Compliance
|
5/21/2020
|
Corrections Issued
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/22/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
5/22/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
5/26/2020
|
Partial Approval
|
ROBERT COLE
|
|
Wood Frame
|
5/26/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
5/28/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Wood Construction
|
6/3/2020
|
Conditional Approval
|
JEFFREY FULTON
|
|
Drywall Nailing
|
6/4/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/4/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Wood Construction
|
6/10/2020
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/10/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
6/12/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
6/16/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/16/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
6/16/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
6/22/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
6/24/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
6/24/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
6/29/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/29/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
7/13/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
7/15/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
7/20/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
7/20/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
7/20/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
7/23/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
7/23/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Interior/Exterior Lathing
|
7/28/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
7/30/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
7/30/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
8/4/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
8/4/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
8/6/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
8/6/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/6/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/7/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
8/12/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
8/12/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
8/17/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
8/17/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/18/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
8/26/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/26/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
8/27/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
8/31/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Wood Frame
|
9/1/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
9/3/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
9/3/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/4/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
9/8/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/8/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/9/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
9/9/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
9/9/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/10/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
9/16/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
9/17/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
9/17/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/24/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
9/24/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/28/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
9/28/2020
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
9/28/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
9/29/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Interior/Exterior Lathing
|
9/29/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
9/30/2020
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Green Building Rough
|
9/30/2020
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
10/2/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
10/8/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
10/8/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
10/8/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
10/9/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
10/13/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
10/13/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
10/14/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
10/16/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
10/20/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
10/20/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
10/21/2020
|
No Access for Inspection
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
10/22/2020
|
Partial Inspection
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
10/22/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Insulation
|
10/22/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Light Gage Steel Frame
|
10/23/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
10/28/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
10/28/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
10/28/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
10/30/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
10/30/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
11/4/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
11/4/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
11/5/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
11/10/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
11/10/2020
|
Partial Inspection
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
11/17/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
11/17/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
12/1/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
12/1/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Interior/Exterior Lathing
|
12/1/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Interior/Exterior Lathing
|
12/3/2020
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
12/4/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
12/4/2020
|
Approved
|
JEFFREY FULTON
|
|
Insulation
|
12/8/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
12/8/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
12/16/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Insulation
|
12/17/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Insulation
|
12/18/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
12/22/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
12/23/2020
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
1/6/2021
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
1/7/2021
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
1/7/2021
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
1/8/2021
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
1/12/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Interior/Exterior Lathing
|
1/12/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
1/15/2021
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
1/15/2021
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
1/22/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Drywall Nailing
|
1/22/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Masonry Wall/Backfill
|
1/22/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Insulation
|
1/27/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Masonry Wall/Backfill
|
1/27/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Light Gage Steel Frame
|
2/12/2021
|
Partial Inspection
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
2/17/2021
|
Partial Inspection
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
2/18/2021
|
Partial Inspection
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
2/19/2021
|
Partial Inspection
|
CAMERON CHABAN
|
|
Deputy Reinf. Masonry
|
3/12/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Masonry Wall/Backfill
|
3/12/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Masonry Wall/Backfill
|
3/19/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Special/Order Compliance
|
4/6/2021
|
Partial Approval
|
CAMERON CHABAN
|
|
Light Gage Steel Frame
|
4/20/2021
|
Partial Approval
|
CAMERON CHABAN
|
|
Pre-Inspection
|
4/28/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Insulation
|
5/3/2021
|
Partial Approval
|
CAMERON CHABAN
|
|
Pre-Inspection
|
5/14/2021
|
Partial Approval
|
CAMERON CHABAN
|
|
Pre-Inspection
|
5/19/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Final
|
6/24/2021
|
Partial Inspection
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
6/24/2021
|
Approved
|
CAMERON CHABAN
|
|
Green Building Final
|
6/24/2021
|
Partial Inspection
|
CAMERON CHABAN
|
|
Reinforced Concrete Frame
|
6/24/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Reinforced Masonry Frame
|
6/24/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
SGSOV-Seismic Gas S/O Valve
|
6/24/2021
|
SGSOV Not Ready
|
CAMERON CHABAN
|
|
Smoke Detectors
|
6/24/2021
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
6/24/2021
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Smoke Detectors
|
7/15/2021
|
Not Ready for Inspection
|
JEFF BYTHEWAY
|
|
Special/Order Compliance
|
10/13/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Verify Sprinkler Sign Off
|
10/13/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Final
|
1/28/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Green Building Final
|
1/28/2022
|
Approved
|
CAMERON CHABAN
|
|
Reinforced Concrete Frame
|
1/28/2022
|
Approved
|
CAMERON CHABAN
|
|
Reinforced Masonry Frame
|
1/28/2022
|
Approved
|
CAMERON CHABAN
|
|
SGSOV-Seismic Gas S/O Valve
|
1/28/2022
|
SGSOV Approved
|
CAMERON CHABAN
|
|
Smoke Detectors
|
1/28/2022
|
Approved
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
1/28/2022
|
Approved
|
CAMERON CHABAN
|
|
Final
|
6/7/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Final
|
7/14/2022
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Final
|
8/5/2022
|
OK to Issue CofO
|
CAMERON CHABAN
|