20627 W OAKGLEN LANE 91306

Certificate Information: 20627 W OAKGLEN LANE 91306

Application / Permit
16010-20000-06005
Plan Check / Job No.
B16VN17821
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(VTT 73177-SL) PROPOSE THREE STORY SFD WITH ATTACHED GARAGE _ PLAN 3
Permit Issued
Issued on 6/28/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2016 APPLICANT
Green Plans Picked Up 1/18/2017 APPLICANT
Assigned to Plan Check Engineer 1/19/2017 DAWN MC NULTY
Corrections Issued 2/1/2017 DAWN MC NULTY
Quality Review Completed 2/1/2017 GUANG MIN TUNG
Building Plans Picked Up 2/2/2017 APPLICANT
Applicant returned to address corrections 3/16/2017 DAWN MC NULTY
Applicant returned to address corrections 4/18/2017 DAWN MC NULTY
Applicant returned to address corrections 6/15/2017 DAWN MC NULTY
Applicant returned to address corrections 11/13/2017 DAWN MC NULTY
Applicant returned to address corrections 12/5/2017 DAWN MC NULTY
Applicant returned to address corrections 6/4/2018 DAWN MC NULTY
Applicant returned to address corrections 6/6/2018 DAWN MC NULTY
Applicant returned to address corrections 6/12/2018 DAWN MC NULTY
Plan Check Approved 6/18/2018 DAWN MC NULTY
Issued 6/28/2019 LADBS
CofO in Progress 8/27/2020 SEAN WIRCH
CofO Issued 9/2/2020 DONALD SUNSERI
Permit Finaled 9/2/2020 DONALD SUNSERI

Permit Application Clearance Information

Sewer availability Cleared 2/9/2017 ROCHELLE DUNGCA
Driveway location Cleared 3/16/2017 KEN AITCHISON
Internal circulation Cleared 3/16/2017 KEN AITCHISON
Low Impact Development Cleared 6/12/2018 SAM NAVID
Green Code Cleared 5/1/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 5/23/2019 GEORGE SUCHAND
"Q" conditions Cleared 6/27/2019 ANNA VAN
"T" removal Cleared 6/27/2019 ANNA VAN
CPC Cleared 6/27/2019 ANNA VAN
Frnt yard landscape/Water mgmt Cleared 6/27/2019 ANNA VAN
Miscellaneous Cleared 6/27/2019 ANNA VAN
Site Plan review Cleared 6/27/2019 ANNA VAN
Tract Map conditions Cleared 6/27/2019 ANNA VAN
Tract Map conditions Cleared 6/27/2019 ANNA VAN
Tract Map conditions Cleared 6/27/2019 ANNA VAN
ZA Case Cleared 6/27/2019 ANNA VAN
ZA Case Cleared 6/27/2019 ANNA VAN
ZA Case Cleared 6/27/2019 ANNA VAN
Address approval Cleared 6/28/2019 JULIUS GARCIA
Eng Process Fee Ord 176,300 Cleared 6/28/2019 APEKSHYA BAJRACHARYA
Highway dedication Cleared 6/28/2019 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 6/28/2019 APEKSHYA BAJRACHARYA
Permit Cleared 6/28/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 6/28/2019 APEKSHYA BAJRACHARYA

Contact Information

Architect Texter, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Meritage Homes Of California Inc; Lic. No.: 755679-B 1671 EAST MONTE VISTA AVE #214      VACAVILLE, CA 95688
Engineer Kim, Kevin Chae; Lic. No.: C53821 2349 N CAMPUS AVENUE      UPLAND, CA 91784
Engineer Lothrop, Shawn Duane; Lic. No.: S5627 29970 TECHNOLOGY DRIVE SUITE 212      MURRIETA, CA 92563

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/2/2019 Approved BRUCE ROZAK
Sewer 12/17/2019 Approved BRUCE ROZAK
Underground Mechanical 12/17/2019 Approved BRUCE ROZAK
Footing/Foundation/Slab 1/17/2020 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 2/10/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 2/18/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/24/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/28/2020 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/25/2020 Approved SEAN WIRCH
Deputy Wood Construction 4/9/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Not Ready for Inspection JOSEPH SAGEN
Wood Frame 4/9/2020 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 4/13/2020 Approved SEAN WIRCH
PLUMBING-Rough 4/13/2020 Approved SEAN WIRCH
ELECTRICAL-Rough 4/14/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 4/20/2020 Approved SEAN WIRCH
Green Building Rough 4/20/2020 Not Ready for Inspection SEAN WIRCH
Verify Sprinkler Sign Off 4/20/2020 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 4/28/2020 Approved SEAN WIRCH
Green Building Rough 4/28/2020 Approved SEAN WIRCH
HVAC-Rough 4/28/2020 Approved SEAN WIRCH
Verify Sprinkler Sign Off 4/28/2020 Approved SEAN WIRCH
Interior/Exterior Lathing 5/6/2020 Not Ready for Inspection SEAN WIRCH
Interior/Exterior Lathing 5/7/2020 Approved SEAN WIRCH
Drywall Nailing 5/11/2020 Approved SEAN WIRCH
Drywall Nailing 5/12/2020 Approved SEAN WIRCH
Gas Test 6/11/2020 Approved SEAN WIRCH
Service/Power Release 6/23/2020 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 7/15/2020 SGSOV Approved JOSEPH SAGEN
ELECTRICAL-Final 7/28/2020 Approved SEAN WIRCH
PLUMBING-Final 7/29/2020 Approved SEAN WIRCH
HVAC-Final 7/30/2020 Approved SEAN WIRCH
Smoke Detectors 7/30/2020 Approved SEAN WIRCH
Final 8/10/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 8/10/2020 Approved JOSEPH SAGEN
Final 8/27/2020 OK to Issue CofO SEAN WIRCH