750 N SWARTHMORE AVE 90272
Certificate Information: 750 N SWARTHMORE AVE 90272
- Application / Permit
- 16010-20000-05935
- Plan Check / Job No.
- B16VN17775
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD OVER BASEMENT AND ATTACHED GARAGE.
- Permit Issued
- Issued on 2/9/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/4/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2017 | RODNEY SAMIIAN |
| Corrections Issued | 2/6/2017 | RODNEY SAMIIAN |
| Quality Review Completed | 2/6/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/7/2017 | APPLICANT |
| Green Plans Picked Up | 2/7/2017 | APPLICANT |
| Applicant returned to address corrections | 11/2/2017 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 11/17/2017 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 12/6/2017 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 12/27/2017 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 1/17/2018 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 1/29/2018 | RODNEY SAMIIAN |
| Plan Check Approved | 2/7/2018 | RODNEY SAMIIAN |
| Issued | 2/9/2018 | LADBS |
| CofO in Progress | 8/3/2020 | ANDREW NAVE |
| Permit Finaled | 8/4/2020 | VINCENT COTTON |
| CofO Issued | 8/4/2020 | VINCENT COTTON |
| Permit Finaled | 8/4/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Coastal Zone | Cleared | 3/28/2017 | RICK TORRES |
| ZI | Cleared | 3/28/2017 | RICK TORRES |
| Address approval | Cleared | 4/5/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/5/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/5/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Flood clearance | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Permit | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Watercourse | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Green Code | Cleared | 9/26/2017 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 11/16/2017 | GILBERT URREA |
| Low Impact Development | Cleared | 11/27/2017 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/27/2017 | STEVE MELGAR |
| Excavation more than 5-ft deep | Cleared | 12/6/2017 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markarian, Mardiros; Lic. No.: C53434 | 3814 VANALDEN AVE TARZANA, CA 91356 |
| Engineer | Smith, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Geologist | Kruger, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2018 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 6/6/2018 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 6/7/2018 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 6/8/2018 | Conditional Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 6/19/2018 | Conditional Approval | RICHARD STEINBACH |
| Deputy Shotcrete | 6/20/2018 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 7/6/2018 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 7/6/2018 | Partial Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 7/11/2018 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/11/2018 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 7/17/2018 | Conditional Approval | RICHARD STEINBACH |
| Deputy Drilled-In Anchors | 7/19/2018 | Conditional Approval | RICHARD STEINBACH |
| Wood Frame | 8/8/2018 | Partial Approval | VINCENT SCIPIONI |
| Deputy Steel/Welding | 8/21/2018 | Conditional Approval | RICHARD STEINBACH |
| Wood Frame | 8/28/2018 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2018 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 11/14/2018 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 11/14/2018 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 11/20/2018 | Approved | RICHARD STEINBACH |
| Deputy Wood Construction | 11/27/2018 | Conditional Approval | RICHARD STEINBACH |
| Wood Frame | 12/24/2018 | Partial Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 1/4/2019 | Conditional Approval | RICHARD STEINBACH |
| Wood Frame | 1/28/2019 | Corrections Issued | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 2/5/2019 | Approved | RICHARD STEINBACH |
| Green Building Rough | 2/5/2019 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 2/5/2019 | Partial Approval | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 2/5/2019 | Approved | RICHARD STEINBACH |
| Insulation | 4/1/2019 | Approved | ANDREW NAVE |
| Drywall Nailing | 4/18/2019 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 4/23/2019 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 5/14/2019 | Partial Approval | ANDREW NAVE |
| Shower Pan | 5/17/2019 | Approved | ANDREW NAVE |
| Drywall Nailing | 6/13/2019 | Approved | ANDREW NAVE |
| Special/Order Compliance | 7/11/2019 | Approved | ANDREW NAVE |
| Pre-Inspection | 9/27/2019 | Approved | ANDREW NAVE |
| Sewer | 12/17/2019 | Approved | ANDREW NAVE |
| Underground Mechanical | 12/17/2019 | Partial Approval | ANDREW NAVE |
| Service/Power Release | 1/28/2020 | Not Ready for Inspection | ANDREW NAVE |
| Rough-Elec/Plmb/HVAC | 1/31/2020 | Partial Approval | DANNY TOLENTINO |
| HVAC-Final | 2/12/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 3/18/2020 | Corrections Issued | ANDREW NAVE |
| Gas Test | 3/18/2020 | Approved | ANDREW NAVE |
| PLUMBING-Final | 3/18/2020 | Not Ready for Inspection | ANDREW NAVE |
| Service/Power Release | 3/18/2020 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Final | 3/20/2020 | Approved | ANDREW NAVE |
| PLUMBING-Final | 3/20/2020 | Corrections Issued | ANDREW NAVE |
| Service/Power Release | 6/16/2020 | Approved | ROBERT SHELLY |
| ELECTRICAL-Final | 6/25/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 6/29/2020 | Approved | ANDREW NAVE |
| PLUMBING-Final | 6/30/2020 | Approved | ANDREW NAVE |
| Final | 7/9/2020 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Final | 7/9/2020 | Not Ready for Inspection | ANDREW NAVE |
| Reinforced Concrete Frame | 7/9/2020 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 7/9/2020 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 7/9/2020 | Approved | ANDREW NAVE |
| Verify Rec and Parks Fee Memo | 7/9/2020 | Not Ready for Inspection | ANDREW NAVE |
| Final | 7/20/2020 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 7/20/2020 | Approved | ANDREW NAVE |
| Final | 7/29/2020 | Conditional Approval | ANDREW NAVE |