746 N SWARTHMORE AVE 90272
Certificate Information: 746 N SWARTHMORE AVE 90272
- Application / Permit
- 16010-20000-05929
- Plan Check / Job No.
- B16VN17756
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 1/8/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2017 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 2/7/2017 | APPLICANT |
| Corrections Issued | 2/15/2017 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/16/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/17/2017 | APPLICANT |
| Applicant returned to address corrections | 4/14/2017 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/26/2017 | NILOOFAR MEHRAIN |
| Issued | 1/8/2018 | LADBS |
| CofO in Progress | 11/9/2021 | ANDREW NAVE |
| CofO Issued | 11/16/2021 | DANIEL ORRANTE |
| Permit Finaled | 11/16/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/5/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/5/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Permit | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Watercourse | Cleared | 4/5/2017 | LEE GUILBEAUX |
| Excavation more than 5-ft deep | Cleared | 4/14/2017 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/14/2017 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 4/14/2017 | NILOOFAR MEHRAIN |
| Hydrant and Access approval | Cleared | 8/22/2017 | JOHN DALLAS |
| Coastal Zone | Cleared | 8/23/2017 | RICK TORRES |
| ZI | Cleared | 8/23/2017 | RICK TORRES |
| Green Code | Cleared | 8/28/2017 | MICHAEL AYERS |
| Low Impact Development | Cleared | 8/28/2017 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 8/29/2017 | NAOMI DIEP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Kruger, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 7/18/2018 | Approved | JOHN LUMB |
| FLOOD-Elevation Certificate | 7/18/2018 | Approved | JOHN LUMB |
| Footing/Foundation/Slab | 7/18/2018 | Partial Approval | JOHN LUMB |
| Deputy Reinf. Concrete | 7/23/2018 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 7/30/2018 | Partial Approval | JOHN LUMB |
| Footing/Foundation/Slab | 7/30/2018 | Partial Approval | JOHN LUMB |
| Sewer | 7/30/2018 | Partial Approval | JOHN LUMB |
| Deputy Reinf. Concrete | 8/6/2018 | Conditional Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 8/14/2018 | Conditional Approval | RICHARD STEINBACH |
| Reinforced Concrete Frame | 8/14/2018 | Conditional Approval | RICHARD STEINBACH |
| Deputy Shotcrete | 8/15/2018 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 8/28/2018 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/4/2018 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2018 | Partial Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2018 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2018 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 2/8/2019 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 2/28/2019 | Approved | RICHARD STEINBACH |
| Deputy Wood Construction | 3/19/2019 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| HVAC-Rough | 4/1/2019 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 4/12/2019 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 4/19/2019 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 4/22/2019 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2019 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2019 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 4/29/2019 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/6/2019 | Corrections Issued | ANDREW NAVE |
| Green Building Rough | 5/6/2019 | Not Ready for Inspection | ANDREW NAVE |
| Verify Sprinkler Sign Off | 5/6/2019 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/9/2019 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/10/2019 | Approved | ANDREW NAVE |
| Green Building Rough | 5/10/2019 | Approved | ANDREW NAVE |
| HVAC-Rough | 5/10/2019 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 5/10/2019 | Partial Approval | ANDREW NAVE |
| Insulation | 5/21/2019 | Partial Approval | ANDREW NAVE |
| Shower Pan | 5/24/2019 | Approved | ANDREW NAVE |
| Insulation | 5/31/2019 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 5/31/2019 | Approved | ANDREW NAVE |
| Drywall Nailing | 7/1/2019 | Partial Approval | ANDREW NAVE |
| Drywall Nailing | 7/5/2019 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 7/19/2019 | Approved | ANDREW NAVE |
| Sewer | 9/17/2019 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 9/17/2019 | Partial Approval | DAVID FEILER |
| Sewer | 10/1/2019 | Partial Inspection | DANNY TOLENTINO |
| Sewer | 10/8/2019 | Partial Inspection | ANDREW NAVE |
| Sewer | 10/25/2019 | Conditional Approval | DAVID FEILER |
| Pre-Inspection | 2/16/2021 | Approved | ANDREW NAVE |
| Special/Order Compliance | 2/22/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 2/26/2021 | Partial Approval | ANDREW NAVE |
| Drywall Nailing | 3/3/2021 | Approved | ANDREW NAVE |
| Service/Power Release | 4/8/2021 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Final | 4/12/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 6/29/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 6/29/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 6/29/2021 | Corrections Issued | ANDREW NAVE |
| Service/Power Release | 6/29/2021 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Final | 7/6/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 7/8/2021 | Approved | ANDREW NAVE |
| HVAC-Final | 7/8/2021 | Approved | ANDREW NAVE |
| PLUMBING-Final | 7/8/2021 | Approved | ANDREW NAVE |
| Final | 11/3/2021 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 11/3/2021 | Approved | ANDREW NAVE |
| Green Building Final | 11/3/2021 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Approved | ANDREW NAVE |
| Service/Power Release | 11/3/2021 | Approved | ANDREW NAVE |
| Smoke Detectors | 11/3/2021 | Approved | ANDREW NAVE |
| Final | 11/8/2021 | OK to Issue CofO | ANDREW NAVE |