Footing/Foundation/Slab
|
2/14/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Underground Mechanical
|
4/5/2018
|
Approved
|
BRUCE ROZAK
|
|
Underground Mechanical
|
4/6/2018
|
Partial Approval
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
4/11/2018
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
4/11/2018
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
4/17/2018
|
Approved
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
4/17/2018
|
Approved
|
JOHN KIDWELL
|
|
Sewer
|
4/26/2018
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Sewer
|
4/27/2018
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Sewer
|
5/3/2018
|
Approved
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/25/2018
|
Partial Inspection
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/1/2018
|
Partial Approval
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/4/2018
|
Partial Approval
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/13/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/15/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/25/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/27/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/1/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/17/2018
|
Partial Approval
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/20/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/1/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2018
|
Partial Approval
|
JOHN KIDWELL
|
|
PLUMBING-Rough
|
11/15/2018
|
Partial Approval
|
DONALD SUNSERI
|
|
Pre-Inspection
|
11/15/2018
|
Approved
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2018
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/7/2018
|
Partial Approval
|
BRUCE ROZAK
|
|
HVAC-Rough
|
1/23/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Deputy Wood Construction
|
2/15/2019
|
Approved
|
JOHN KIDWELL
|
|
Wood Frame
|
2/15/2019
|
Partial Approval
|
JOHN KIDWELL
|
|
Deputy Wood Construction
|
3/11/2019
|
Approved
|
DONALD SUNSERI
|
|
Interior/Exterior Lathing
|
3/11/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
ELECTRICAL-Rough
|
3/13/2019
|
Partial Inspection
|
DONALD SUNSERI
|
|
HVAC-Rough
|
3/13/2019
|
Partial Inspection
|
DONALD SUNSERI
|
|
PLUMBING-Rough
|
3/15/2019
|
Approved
|
BRUCE ROZAK
|
|
ELECTRICAL-Rough
|
3/19/2019
|
Approved
|
DONALD SUNSERI
|
|
BUILDING-Rough-Frame
|
3/29/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Green Building Rough
|
3/29/2019
|
Approved
|
DONALD SUNSERI
|
|
HVAC-Rough
|
3/29/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
MERV13>=Rough
|
3/29/2019
|
Partial Inspection
|
DONALD SUNSERI
|
|
Verify Sprinkler Sign Off
|
3/29/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
BUILDING-Rough-Frame
|
4/3/2019
|
Approved
|
BRUCE ROZAK
|
|
HVAC-Rough
|
4/3/2019
|
Approved
|
BRUCE ROZAK
|
|
Verify Sprinkler Sign Off
|
4/3/2019
|
Approved
|
BRUCE ROZAK
|
|
Insulation
|
4/8/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Interior/Exterior Lathing
|
4/12/2019
|
Approved
|
DONALD SUNSERI
|
|
Drywall Nailing
|
4/19/2019
|
Approved
|
BRUCE ROZAK
|
|
Interior/Exterior Lathing
|
4/24/2019
|
Approved
|
BRUCE ROZAK
|
|
Special/Order Compliance
|
11/6/2019
|
Partial Approval
|
JOSEPH SAGEN
|
|
Special/Order Compliance
|
11/21/2019
|
Partial Approval
|
JOSEPH SAGEN
|
|
ELECTRICAL-Final
|
11/25/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
ELECTRICAL-Final
|
1/2/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Service/Power Release
|
1/2/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Gas Test
|
3/10/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
PLUMBING-Final
|
3/10/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
ELECTRICAL-Final
|
3/24/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Gas Test
|
3/24/2020
|
Approved
|
JOSEPH SAGEN
|
|
PLUMBING-Final
|
3/24/2020
|
Approved
|
JOSEPH SAGEN
|
|
ELECTRICAL-Final
|
5/11/2020
|
Approved
|
JOSEPH SAGEN
|
|
Special/Order Compliance
|
5/22/2020
|
Approved
|
JOSEPH SAGEN
|
|
SGSOV-Seismic Gas S/O Valve
|
6/30/2020
|
SGSOV Approved
|
JOSEPH SAGEN
|
|
Service/Power Release
|
8/17/2020
|
Approved
|
JOSEPH SAGEN
|
|
Final
|
9/15/2020
|
Corrections Issued
|
DONALD SUNSERI
|
|
Green Building Final
|
9/15/2020
|
Approved
|
DONALD SUNSERI
|
|
Smoke Detectors
|
9/15/2020
|
Approved
|
DONALD SUNSERI
|
|
Final
|
9/21/2020
|
OK to Issue CofO
|
JOSEPH SAGEN
|
|
HVAC-Final
|
9/21/2020
|
Approved
|
JOSEPH SAGEN
|