913 N BEVERLY GLEN BLVD 90077

Certificate Information: 913 N BEVERLY GLEN BLVD 90077

Application / Permit
16010-20000-05727
Plan Check / Job No.
B16VN17466
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 STORY SFD W/ HABITABLE BASEMENT & ATT. GARAGE. <sprinklers req'd throughout>
Permit Issued
Issued on 3/7/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2016 APPLICANT
Assigned to Plan Check Engineer 1/26/2017 ABDUL CHEGENI
Green Plans Picked Up 1/31/2017 APPLICANT
Corrections Issued 2/23/2017 ABDUL CHEGENI
Quality Review Completed 3/1/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/8/2017 APPLICANT
Applicant returned to address corrections 3/22/2017 ABDUL CHEGENI
Applicant returned to address corrections 9/1/2017 ABDUL CHEGENI
Applicant returned to address corrections 3/5/2018 ABDUL CHEGENI
Plan Check Approved 3/7/2018 ABDUL CHEGENI
Issued 3/7/2018 LADBS
CofO in Progress 3/3/2025 CHRISTOPHER WILSON
Permit Finaled 3/17/2025 RICHARD STEINBACH
CofO Issued 3/17/2025 RICHARD STEINBACH
Permit Finaled 3/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/18/2017 HOWARD COOPER
BHO/Hillside ordinance Cleared 7/18/2017 CHRISTINE REUSCH
BHO/Hillside ordinance Cleared 7/18/2017 CHRISTINE REUSCH
BHO/Hillside ordinance Cleared 7/18/2017 CHRISTINE REUSCH
Hydrant and Access approval Cleared 7/18/2017 JOHN DALLAS
Permit Cleared 7/18/2017 CHRISTINE REUSCH
Roof/Waste drainage to street Cleared 7/18/2017 CHRISTINE REUSCH
Low Impact Development Cleared 7/25/2017 MATTHEW JIMENEZ
Green Code Cleared 8/9/2017 MICKEY YAMASHITA
GPI Written Notices Cleared 9/1/2017 ABDUL CHEGENI
Grading Pre-Inspection Cleared 9/1/2017 ABDUL CHEGENI
Eng Process Fee Ord 176,300 Cleared 1/3/2018 KENNETH PHAM
Excavation more than 5-ft deep Cleared 1/3/2018 CALOSHA APPROVED
Sewer availability Cleared 1/3/2018 KENNETH PHAM
ZA Case Cleared 1/3/2018 HERMINIGILDO AGUSTIN
Miscellaneous Cleared 3/5/2018 ABDUL CHEGENI
Work Adjacent to Public Way Cleared 3/7/2018 HOK CHI CHIU

Contact Information

Architect Himes, John A; Lic. No.: C25478 17155 LISETTE STREET      GRANADA HILLS, CA 91344
Contractor Owner-Builder       ,
Engineer Adams, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304
Engineer Cai, Luo B; Lic. No.: C80352 5244 HUCKLEBERRY OAK STREET      SIMI VALLEY, CA 93063
Engineer Tsao, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311
Engineer Yenjai, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010
Geologist Tsao, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/20/2018 Partial Inspection JOEL LAUNCHBAUGH
Deputy Grading 7/17/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/7/2019 Not Ready for Inspection CARLOS MATAMOROS
Special/Order Compliance 11/8/2019 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 2/27/2020 Partial Approval ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 3/24/2020 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 4/3/2020 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 5/21/2020 Corrections Issued ANTHONY MCDOWALL
Deputy Reinf. Concrete 11/23/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/24/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 12/28/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 3/26/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Drilled-In Anchors 7/20/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/28/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/22/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/28/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/4/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 3/21/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Wood Construction 3/30/2022 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/14/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 7/15/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 8/10/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 8/23/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 8/23/2022 Approved CHRISTOPHER WILSON
Deputy Wood Construction 9/2/2022 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 9/7/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 9/12/2022 Approved CHRISTOPHER WILSON
Green Building Rough 9/12/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 9/12/2022 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/12/2022 Approved CHRISTOPHER WILSON
Insulation 9/14/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 9/21/2022 Approved CHRISTOPHER WILSON
Gas Test 1/25/2023 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 1/25/2023 Partial Approval CHRISTOPHER WILSON
Gas Test 1/27/2023 Approved CHRISTOPHER WILSON
Underground Mechanical 1/27/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 3/13/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 3/16/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 3/28/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 3/29/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Final 3/31/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sewer 4/7/2023 Approved CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/5/2023 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/9/2023 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Final 10/12/2023 Approved CHRISTOPHER WILSON
Service/Power Release 10/12/2023 Approved CHRISTOPHER WILSON
Final 6/4/2024 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/4/2024 Approved CHRISTOPHER WILSON
Green Building Final 6/4/2024 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Masonry Frame 6/4/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 6/4/2024 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 6/4/2024 Approved CHRISTOPHER WILSON
HVAC-Final 6/7/2024 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Not Ready CHRISTOPHER WILSON
Final 8/2/2024 Corrections Issued CHRISTOPHER WILSON
Green Building Final 8/2/2024 Approved CHRISTOPHER WILSON
HVAC-Final 8/2/2024 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 8/2/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 2/27/2025 OK to Issue CofO CHRISTOPHER WILSON
HVAC-Final 2/27/2025 Approved CHRISTOPHER WILSON
Smoke Detectors 2/27/2025 Approved CHRISTOPHER WILSON