6500 N SEPULVEDA BLVD 91411

Certificate Information: 6500 N SEPULVEDA BLVD 91411

Application / Permit
16010-20000-05719
Plan Check / Job No.
B16VN17444
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 6-STORY 160-UNIT TYPE III-A APT W/ TYPE 1-A BASEMENT PARKING PER DIR-2016-4380-DB-SPR (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/23/2017
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2016 APPLICANT
Assigned to Plan Check Engineer 1/23/2017 NILOOFAR MEHRAIN
Disabled Access Plans Picked Up 2/1/2017 APPLICANT
Green Plans Picked Up 2/1/2017 APPLICANT
Corrections Issued 2/9/2017 NILOOFAR MEHRAIN
Quality Review Completed 2/10/2017 GUANG MIN TUNG
Building Plans Picked Up 2/10/2017 APPLICANT
Applicant returned to address corrections 3/20/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/5/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/17/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/16/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/7/2017 NILOOFAR MEHRAIN
Plan Check Approved 8/23/2017 NILOOFAR MEHRAIN
Issued 8/23/2017 LADBS
CofO in Progress 8/18/2020 JOHN KITCKO
No Progress 8/28/2020 RICKEY JACKSON
TCO Issued (Expire Date: 02-24-2021) 8/28/2020 RICKEY JACKSON
CofO in Progress 9/11/2020 RICKEY JACKSON
Permit Finaled 9/11/2020 RICKEY JACKSON
CofO Issued 9/11/2020 RICKEY JACKSON
Permit Finaled 9/11/2020 RICKEY JACKSON

Permit Application Clearance Information

Low Impact Development Cleared 1/18/2017 AYMAN JABBOURI
Address approval Cleared 3/22/2017 HOWARD COOPER
Hydrant and Access approval Cleared 3/30/2017 JOHN DALLAS
Miscellaneous Cleared 3/30/2017 EDBER MACEDO
Stormwater Pollution Mitigatn Cleared 3/30/2017 RYAN HUDSON
ZA Case Cleared 3/30/2017 EDBER MACEDO
ZA Case Cleared 4/19/2017 JOHN DACEY
ZA Case Cleared 4/19/2017 JOHN DACEY
ZA Case Cleared 4/19/2017 JOHN DACEY
ZA Case Cleared 4/19/2017 JOHN DACEY
Eng Process Fee Ord 176,300 Cleared 5/10/2017 KENNETH PHAM
Permit Cleared 5/10/2017 KENNETH PHAM
Sewer availability Cleared 5/10/2017 KENNETH PHAM
Bicycle Parking Cleared 5/15/2017 ERIK MUNOZ
Frnt yard landscape/Water mgmt Cleared 5/15/2017 DENNIS CHEW
Opn space landscape/Water mgmt Cleared 5/15/2017 DENNIS CHEW
Roof/Waste drainage to street Cleared 5/15/2017 ERIK MUNOZ
ZI Cleared 5/15/2017 DENNIS CHEW
Highway dedication Cleared 6/7/2017 IRENE CHIA
Work Adjacent to Public Way Cleared 6/7/2017 YESENIA DIAZ
DAS Clearance Cleared 6/29/2017 NORLITO MEDRANO
Green Code Cleared 7/5/2017 MICHAEL AYERS
Fire Marshall Fire Life Safety Cleared 7/17/2017 MENOA AGHAJANI
Housing rent stabilization Cleared 8/1/2017 CHARLES GARCIA
DCP conditions approval Cleared 8/4/2017 NICHOLAS KAWAZOE
Housing density bonus Cleared 8/4/2017 NICHOLAS KAWAZOE
Miscellaneous Cleared 8/9/2017 RICK TORRES
Building over 3-story or 36-ft Cleared 8/23/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 8/23/2017 CALOSHA APPROVED

Contact Information

Architect Ghafoori-Tabrizi, Kamran; Lic. No.: C20369 21731 AMBAR DRIVE      WOODLAND HILLS, CA 91364
Contractor Imt Residential; Lic. No.: 766199-B 15303 VENTURA BLVD   STE. 200    SHERMAN OAKS, CA 91403
Engineer Dejban, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Hill, Edward Foster; Lic. No.: GE2126 GEOTECH 439 WESTERN AVE      GLENDALE, CA 91201

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/5/2018 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 1/5/2018 Partial Approval JEFFREY DURAN
Deputy Shotcrete 1/17/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/18/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/18/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/19/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/22/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/22/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/23/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/23/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/24/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/24/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/24/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 1/25/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/30/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/30/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/2/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/2/2018 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 2/2/2018 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 2/2/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/7/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/8/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 2/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 2/13/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 2/13/2018 Partial Approval JEFFREY DURAN
Green Building Rough 2/13/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 2/13/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 2/13/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 2/15/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/21/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/21/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/22/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/27/2018 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 3/1/2018 Partial Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/2/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/12/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 3/19/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 3/19/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 3/19/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 4/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/10/2018 Approved JEFFREY DURAN
Green Building Rough 4/10/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 4/10/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 4/10/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 4/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/30/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/1/2018 Approved JEFFREY DURAN
Reinforced Concrete Frame 5/1/2018 Partial Approval JEFFREY DURAN
Reinforced Masonry Frame 5/1/2018 Partial Approval JEFFREY DURAN
Special/Order Compliance 5/1/2018 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 5/2/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/3/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/4/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 5/4/2018 Approved JEFFREY DURAN
Green Building Rough 5/4/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 5/4/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 5/4/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 5/7/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/7/2018 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 5/7/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/8/2018 Approved JEFFREY DURAN
Reinforced Concrete Frame 5/8/2018 Partial Approval JEFFREY DURAN
Reinforced Masonry Frame 5/8/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/9/2018 Approved JEFFREY DURAN
Deputy Shotcrete 5/9/2018 Approved JEFFREY DURAN
Deputy Shotcrete 5/10/2018 Approved JEFFREY DURAN
Green Building Rough 5/10/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 5/10/2018 Partial Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 5/10/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 5/11/2018 Conditional Approval DANNY RODRIGUEZ
Deputy Shotcrete 5/11/2018 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/11/2018 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/14/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 5/14/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 5/14/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 5/15/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/16/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 5/17/2018 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/17/2018 Approved DANNY RODRIGUEZ
Deputy Shotcrete 5/17/2018 Approved DANNY RODRIGUEZ
Green Building Rough 5/17/2018 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 5/17/2018 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/18/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 5/21/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/21/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/22/2018 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 5/22/2018 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/23/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/23/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/24/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 5/25/2018 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 5/30/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/31/2018 Approved DANNY RODRIGUEZ
Green Building Rough 5/31/2018 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 5/31/2018 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/31/2018 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/4/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/4/2018 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 6/8/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/22/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/28/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 6/28/2018 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 7/2/2018 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 7/2/2018 Conditional Approval CAMERON CHABAN
Green Building Rough 7/2/2018 Not Ready for Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 7/2/2018 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Concrete 7/3/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/6/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 7/6/2018 Approved JEFFREY DURAN
Green Building Rough 7/6/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 7/6/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/9/2018 Approved JEFFREY DURAN
Reinforced Concrete Frame 7/9/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 7/9/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 7/10/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/11/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/12/2018 Approved JEFFREY DURAN
Green Building Rough 7/12/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 7/12/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 7/12/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 7/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/19/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 7/19/2018 Partial Approval JEFFREY DURAN
Green Building Rough 7/19/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 7/19/2018 Corrections Issued JEFFREY DURAN
Verify Sprinkler Sign Off 7/19/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Shotcrete 7/25/2018 Conditional Approval CAMERON CHABAN
Green Building Rough 7/25/2018 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 7/25/2018 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 7/25/2018 Not Ready for Inspection CAMERON CHABAN
Deputy Shotcrete 7/26/2018 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/27/2018 Conditional Approval JAMES STEPHENS
Green Building Rough 7/30/2018 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 7/30/2018 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 7/30/2018 Not Ready for Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 7/31/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/3/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 8/13/2018 Partial Inspection JEFFREY DURAN
Green Building Rough 8/13/2018 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 8/14/2018 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/28/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/28/2018 Approved JEFFREY DURAN
Drywall Nailing 8/28/2018 Partial Approval JEFFREY DURAN
Green Building Rough 8/28/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 8/28/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 8/28/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 8/29/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 8/30/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 8/30/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 9/4/2018 Partial Approval JEFFREY DURAN
Green Building Rough 9/4/2018 Not Ready for Inspection JEFFREY DURAN
Light Gage Steel Frame 9/4/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/6/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 9/6/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 9/6/2018 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 9/6/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 9/7/2018 Approved JEFFREY DURAN
Drywall Nailing 9/7/2018 Partial Approval JEFFREY DURAN
Reinforced Concrete Frame 9/7/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/10/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 9/20/2018 Partial Approval JEFFREY DURAN
Green Building Rough 9/20/2018 Not Ready for Inspection JEFFREY DURAN
Light Gage Steel Frame 9/20/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/21/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/9/2018 Approved JEFFREY DURAN
Drywall Nailing 10/9/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/9/2018 Partial Approval JEFFREY DURAN
Green Building Rough 10/9/2018 Not Ready for Inspection JEFFREY DURAN
Light Gage Steel Frame 10/9/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 10/31/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 11/5/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 11/6/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2018 Partial Approval JEFFREY DURAN
Green Building Rough 11/6/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 11/15/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 11/28/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/28/2018 Partial Approval JEFFREY DURAN
Green Building Rough 11/28/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 12/17/2018 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 1/9/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/9/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2019 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 2/8/2019 Partial Approval JOHN KITCKO
Drywall Nailing 2/11/2019 Partial Approval JEFFREY DURAN
Green Building Rough 2/11/2019 Not Ready for Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2019 Partial Approval JEFFREY DURAN
Green Building Rough 3/13/2019 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 3/13/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 3/13/2019 Partial Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/15/2019 Partial Approval JEFFREY DURAN
Green Building Rough 3/19/2019 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 3/19/2019 Not Ready for Inspection DANIEL VARNUM
Wood Frame 3/19/2019 Partial Approval DANIEL VARNUM
Insulation 3/20/2019 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 3/22/2019 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2019 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 3/28/2019 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2019 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2019 Conditional Approval CAMERON CHABAN
Insulation 4/5/2019 Conditional Approval CAMERON CHABAN
Drywall Nailing 4/9/2019 Partial Approval JEFFREY DURAN
Green Building Rough 4/9/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 4/9/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 4/12/2019 Conditional Approval JEFFREY DURAN
Insulation 4/25/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 4/30/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 4/30/2019 Not Ready for Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 5/1/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 5/2/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 5/2/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 5/3/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 5/7/2019 Partial Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2019 Partial Approval JEFFREY DURAN
Green Building Rough 5/7/2019 Partial Approval JEFFREY DURAN
Insulation 5/22/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 5/22/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 5/29/2019 Partial Approval JEFFREY DURAN
Green Building Rough 5/29/2019 Not Ready for Inspection JEFFREY DURAN
Interior/Exterior Lathing 5/29/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 5/31/2019 Partial Approval JEFFREY DURAN
Green Building Rough 5/31/2019 Partial Inspection JEFFREY DURAN
Insulation 5/31/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 6/10/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 6/14/2019 Partial Approval JEFFREY DURAN
Green Building Rough 6/14/2019 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 6/14/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 6/21/2019 Partial Approval ROBERT DAVIS
Insulation 6/21/2019 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 6/21/2019 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 7/15/2019 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 7/18/2019 Partial Approval DANNY RODRIGUEZ
Insulation 7/23/2019 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/1/2019 Partial Approval JEFFREY DURAN
Wood Frame 8/2/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 8/12/2019 Partial Approval JEFFREY DURAN
Insulation 8/12/2019 Partial Approval JEFFREY DURAN
Insulation 8/14/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 8/21/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 8/22/2019 Partial Approval JEFFREY DURAN
Green Building Rough 8/22/2019 Partial Approval JEFFREY DURAN
Insulation 8/22/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 8/27/2019 Not Ready for Inspection ROBERT COLE
Green Building Rough 8/27/2019 Not Ready for Inspection ROBERT COLE
Insulation 8/27/2019 Partial Approval ROBERT COLE
Drywall Nailing 8/29/2019 Partial Approval JEFFREY DURAN
Green Building Rough 8/29/2019 Partial Approval JEFFREY DURAN
Insulation 9/5/2019 Partial Approval DANIEL VARNUM
Drywall Nailing 9/12/2019 Partial Approval JEFFREY DURAN
Green Building Rough 9/12/2019 Partial Inspection JEFFREY DURAN
Insulation 9/12/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 9/23/2019 Partial Approval JEFFREY DURAN
Green Building Rough 9/23/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/3/2019 Partial Approval ROBERT COLE
Insulation 10/3/2019 Partial Approval ROBERT COLE
Insulation 10/15/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/22/2019 Partial Approval JEFFREY DURAN
Green Building Rough 10/22/2019 Not Ready for Inspection JEFFREY DURAN
Insulation 10/25/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 10/30/2019 Partial Approval JEFFREY DURAN
Insulation 10/30/2019 Partial Approval JEFFREY DURAN
Insulation 11/1/2019 Partial Approval JAMES STEPHENS
Insulation 11/8/2019 Partial Approval JEFFREY DURAN
Insulation 11/14/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 11/19/2019 Partial Approval JAMES STEPHENS
Green Building Rough 11/19/2019 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 11/27/2019 Partial Approval FRED WOHLFARTH
Green Building Rough 11/27/2019 Not Ready for Inspection FRED WOHLFARTH
Insulation 12/3/2019 Partial Approval JEFFREY DURAN
Insulation 12/6/2019 Partial Inspection JEFFREY DURAN
Drywall Nailing 12/13/2019 Partial Approval JEFFREY DURAN
Green Building Rough 12/13/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 12/23/2019 Partial Approval JEFFREY DURAN
Green Building Rough 12/23/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 12/23/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 1/17/2020 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 1/17/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 1/24/2020 Partial Approval JEFFREY DURAN
Green Building Rough 1/24/2020 Partial Inspection JEFFREY DURAN
Drywall Nailing 1/28/2020 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 2/5/2020 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 3/3/2020 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 3/20/2020 Partial Inspection JEFFREY DURAN
Light Gage Steel Frame 4/6/2020 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 4/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/16/2020 Partial Approval JOHN KITCKO
Green Building Rough 4/16/2020 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 7/13/2020 Approved JOHN KITCKO
Final 7/13/2020 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 7/13/2020 Approved JOHN KITCKO
Green Building Final 7/13/2020 Approved JOHN KITCKO
Green Building Rough 7/13/2020 Approved JOHN KITCKO
Reinforced Concrete Frame 7/13/2020 Approved JOHN KITCKO
Reinforced Masonry Frame 7/13/2020 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Approved JOHN KITCKO
SUSMP-Std. Urban Storm Water 7/13/2020 Approved JOHN KITCKO
Smoke Detectors 7/13/2020 Approved JOHN KITCKO
Verify Sprinkler Sign Off 7/13/2020 Approved JOHN KITCKO
Wood Frame 7/13/2020 Approved JOHN KITCKO
Final 8/18/2020 OK to Issue CofO JOHN KITCKO