244 N LADERA DR 90210

Certificate Information: 244 N LADERA DR 90210

Application / Permit
16010-20000-05466
Plan Check / Job No.
B16VN16782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
(N) 2-STORY TYPE I-B ACCESSORY LIVING QUARTERS W/ MECHANICAL & POOL EQUIPMENT ROOMS (NFPA-13D FIRE SPRINKLER THROUGHOUT)
Permit Issued
Issued on 2/14/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2016 APPLICANT
Green Plans Picked Up 1/10/2017 APPLICANT
Assigned to Plan Check Engineer 1/12/2017 NILOOFAR MEHRAIN
Corrections Issued 1/17/2017 NILOOFAR MEHRAIN
Quality Review Completed 1/19/2017 GUANG MIN TUNG
Building Plans Picked Up 1/20/2017 APPLICANT
Applicant returned to address corrections 6/22/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/14/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/16/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/23/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/24/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/6/2018 NILOOFAR MEHRAIN
Plan Check Approved 2/13/2018 NILOOFAR MEHRAIN
Issued 2/14/2018 LADBS
CofO in Progress 9/27/2022 CHRISTOPHER WILSON
CofO in Progress 9/27/2022 CHRISTOPHER WILSON
Permit Finaled 10/14/2022 DANIEL ORRANTE
CofO Issued 10/14/2022 DANIEL ORRANTE
Permit Finaled 10/14/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading in hillside Cleared 2/1/2017 EDBER MACEDO
Green Code Cleared 9/28/2017 MICHAEL AYERS
BHO/Hillside ordinance Cleared 1/23/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/23/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/23/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/23/2018 ADRIAN SANCHEZ
GPI Written Notices Cleared 1/23/2018 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 1/23/2018 NILOOFAR MEHRAIN
Hydrant and Access approval Cleared 1/23/2018 ROBERT DUFF
Permit Cleared 1/23/2018 ADRIAN SANCHEZ
Sewer availability Cleared 1/23/2018 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 2/8/2018 CALOSHA APPROVED
Low Impact Development Cleared 2/12/2018 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/12/2018 MICHAEL CASTILLO

Contact Information

Architect Studio, Mig Architecture; Lic. No.: C30880 6363 WILSHIRE BLVD   #636    LOS ANGELES, CA 90048
Contractor Hilgendorf Corp; Lic. No.: 772712-B 2300 S GRANVILLE      LOS ANGELES, CA 90064
Engineer Baad, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Fischer, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/15/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/18/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 3/9/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 3/9/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 3/9/2020 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 4/17/2020 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 4/17/2020 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/17/2020 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 8/20/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 8/20/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 8/20/2020 Not Ready for Inspection MATT KELLERMAN
Pool Piping 9/4/2020 Conditional Approval MATT KELLERMAN
Footing/Foundation/Slab 10/5/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/9/2020 Conditional Approval MATT KELLERMAN
Green Building Rough 11/19/2020 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 11/19/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 11/19/2020 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 12/15/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 12/15/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 12/15/2020 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 1/26/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 1/26/2021 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/26/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 7/2/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 7/2/2021 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 7/2/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 7/12/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 7/12/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 7/12/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Partial Approval CHRISTOPHER WILSON
Green Building Rough 8/16/2021 Not Ready for Inspection MATT KELLERMAN
Structural Steel Frame 8/16/2021 Not Ready for Inspection MATT KELLERMAN
Verify Sprinkler Sign Off 8/16/2021 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 8/20/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 8/20/2021 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 8/20/2021 Not Ready for Inspection MATT KELLERMAN
Structural Steel Frame 8/23/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 10/13/2021 Approved CHRISTOPHER WILSON
Special/Order Compliance 10/15/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/3/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 11/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 11/23/2021 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 11/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 11/23/2021 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 11/24/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/24/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 11/24/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 12/2/2021 Partial Approval CHRISTOPHER WILSON
Insulation 12/7/2021 Approved CHRISTOPHER WILSON
Drywall Nailing 12/16/2021 Approved RYAN SALAZAR
Green Building Rough 12/16/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/7/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 1/19/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 6/20/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 8/9/2022 Corrections Issued CHRISTOPHER WILSON
Final 8/9/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 8/10/2022 Approved CHRISTOPHER WILSON
HVAC-Final 8/12/2022 Approved CHRISTOPHER WILSON
Final 8/19/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 8/19/2022 Approved CHRISTOPHER WILSON
Green Building Final 8/19/2022 Approved CHRISTOPHER WILSON
Reinforced Concrete Frame 8/19/2022 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Approved CHRISTOPHER WILSON
Service/Power Release 8/19/2022 Approved CHRISTOPHER WILSON
Smoke Detectors 8/19/2022 Approved CHRISTOPHER WILSON
Structural Steel Frame 8/19/2022 Approved CHRISTOPHER WILSON
Final 9/9/2022 Not Ready for Inspection CHRISTOPHER WILSON
Final 9/26/2022 OK to Issue CofO CHRISTOPHER WILSON