244 N LADERA DR 90210

Certificate Information: 244 N LADERA DR 90210

Application / Permit
16010-20000-05465
Plan Check / Job No.
B16VN16782
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/14/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2016 APPLICANT
Green Plans Picked Up 1/10/2017 APPLICANT
Assigned to Plan Check Engineer 1/12/2017 NILOOFAR MEHRAIN
Corrections Issued 1/17/2017 NILOOFAR MEHRAIN
Quality Review Completed 1/19/2017 GUANG MIN TUNG
Building Plans Picked Up 1/20/2017 APPLICANT
Applicant returned to address corrections 6/22/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/14/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/16/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/23/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/24/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/6/2018 NILOOFAR MEHRAIN
Plan Check Approved 2/13/2018 NILOOFAR MEHRAIN
Issued 2/14/2018 LADBS
CofO in Progress 9/27/2022 CHRISTOPHER WILSON
CofO in Progress 9/27/2022 CHRISTOPHER WILSON
Permit Finaled 10/14/2022 DANIEL ORRANTE
CofO Issued 11/14/2022 DANIEL ORRANTE
Permit Finaled 11/14/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading in hillside Cleared 2/1/2017 EDBER MACEDO
Green Code Cleared 9/28/2017 MICHAEL AYERS
Address approval Cleared 1/23/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/23/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/23/2018 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/23/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/23/2018 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 1/23/2018 ROBERT DUFF
Permit Cleared 1/23/2018 ADRIAN SANCHEZ
Sewer availability Cleared 1/23/2018 ADRIAN SANCHEZ
GPI Written Notices Cleared 2/6/2018 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 2/6/2018 NILOOFAR MEHRAIN
Excavation more than 5-ft deep Cleared 2/8/2018 CALOSHA APPROVED
Low Impact Development Cleared 2/12/2018 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/12/2018 MICHAEL CASTILLO

Contact Information

Architect Studio, Mig Architecture; Lic. No.: C30880 6363 WILSHIRE BLVD   #636    LOS ANGELES, CA 90048
Contractor Hilgendorf Corp; Lic. No.: 772712-B 2300 S GRANVILLE      LOS ANGELES, CA 90064
Engineer Baad, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Fischer, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/29/2018 Partial Approval JOEL LAUNCHBAUGH
Excavation/Setback/Form/Re-Bar 8/2/2018 Partial Approval JOEL LAUNCHBAUGH
Footing/Foundation/Slab 8/2/2018 Partial Approval JOEL LAUNCHBAUGH
Floor/Roof Diaphrgm/Shear Wall 10/4/2018 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 10/4/2018 Partial Approval CHRISTOPHER WILSON
Green Building Rough 10/4/2018 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 10/4/2018 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/4/2018 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/11/2018 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/11/2018 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/5/2018 Partial Approval CHRISTOPHER WILSON
Green Building Rough 11/5/2018 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 11/5/2018 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 11/5/2018 Partial Inspection CHRISTOPHER WILSON
Deputy Shotcrete 11/6/2018 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/16/2018 Partial Approval MATT KELLERMAN
Green Building Rough 11/16/2018 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 11/16/2018 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 11/16/2018 Not Ready for Inspection MATT KELLERMAN
Deputy Reinf. Concrete 11/20/2018 Approved MATT KELLERMAN
Deputy Shotcrete 11/21/2018 Partial Approval MATT KELLERMAN
Green Building Rough 11/27/2018 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 11/27/2018 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 11/27/2018 Not Ready for Inspection MATT KELLERMAN
Deputy Reinf. Concrete 11/28/2018 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 12/5/2018 Partial Approval CARLOS MATAMOROS
Green Building Rough 12/5/2018 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 12/5/2018 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 12/14/2018 Partial Approval MATT KELLERMAN
Green Building Rough 12/14/2018 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 12/14/2018 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 12/14/2018 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 12/27/2018 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 12/27/2018 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 12/27/2018 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 12/31/2018 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 12/31/2018 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 12/31/2018 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 1/9/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 1/9/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 1/9/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/9/2019 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/11/2019 Conditional Approval CHRISTOPHER WILSON
Sewer 1/11/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/24/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 1/24/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/30/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 1/30/2019 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 1/31/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/31/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Shotcrete 2/4/2019 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 2/8/2019 Partial Approval MATT KELLERMAN
PLUMBING-Rough 2/8/2019 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 2/14/2019 Partial Approval CARLOS MATAMOROS
Green Building Rough 2/20/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/4/2019 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 3/4/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 3/15/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 3/15/2019 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 3/15/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 3/15/2019 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 3/19/2019 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/1/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/3/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/10/2019 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/18/2019 Partial Approval MICHAEL TEMPLE
Green Building Rough 4/18/2019 Not Ready for Inspection MICHAEL TEMPLE
Reinforced Concrete Frame 4/18/2019 Partial Approval MICHAEL TEMPLE
Verify Sprinkler Sign Off 4/18/2019 Not Ready for Inspection MICHAEL TEMPLE
Green Building Rough 4/24/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 4/24/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/24/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 5/7/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/8/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/9/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/10/2019 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 5/10/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/10/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/10/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 5/13/2019 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 5/20/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 5/20/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/20/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 6/20/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 6/20/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/20/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 7/17/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/1/2019 Conditional Approval DANNY TOLENTINO
Green Building Rough 8/15/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 8/15/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 8/15/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 9/5/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 9/5/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 9/5/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/5/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 9/12/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 9/12/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/12/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 9/18/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 9/18/2019 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 9/18/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 10/9/2019 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 10/9/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 10/9/2019 Partial Approval MATT KELLERMAN
Green Building Rough 10/15/2019 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 10/15/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 10/15/2019 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 10/21/2019 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 10/21/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 10/21/2019 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 10/28/2019 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 10/28/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 10/28/2019 Not Ready for Inspection MATT KELLERMAN
Deputy Steel/Welding 11/4/2019 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 11/25/2019 Approved MATT KELLERMAN
Green Building Rough 11/25/2019 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 11/25/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 11/25/2019 Not Ready for Inspection MATT KELLERMAN
Deputy Steel/Welding 12/6/2019 Partial Approval MATT KELLERMAN
Green Building Rough 12/6/2019 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 12/6/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 12/6/2019 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 12/13/2019 Partial Approval MATT KELLERMAN
Green Building Rough 12/17/2019 Partial Approval MATT KELLERMAN
Pre-Inspection 12/17/2019 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 12/17/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 12/17/2019 Not Ready for Inspection MATT KELLERMAN
Green Building Rough 12/24/2019 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 12/24/2019 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 12/24/2019 Not Ready for Inspection MATT KELLERMAN
Footing/Foundation/Slab 1/8/2020 Conditional Approval MATT KELLERMAN
Green Building Rough 1/8/2020 Conditional Approval MATT KELLERMAN
Deputy Steel/Welding 1/14/2020 Corrections Issued MATT KELLERMAN
Deputy Steel/Welding 1/15/2020 Approved MATT KELLERMAN
Green Building Rough 1/15/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 1/15/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 1/15/2020 Not Ready for Inspection MATT KELLERMAN
Deputy Steel/Welding 1/16/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 1/17/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/21/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 1/22/2020 Partial Approval MATT KELLERMAN
Green Building Rough 1/22/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 1/22/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 1/22/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/23/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/24/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/29/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 2/3/2020 Conditional Approval MATT KELLERMAN
Deputy Steel/Welding 2/5/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 2/19/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 2/20/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 2/21/2020 Approved MATT KELLERMAN
Footing/Foundation/Slab 2/21/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 2/24/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 2/26/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 2/26/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 2/27/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 2/28/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 3/4/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 3/5/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 3/6/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 3/9/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 3/10/2020 Approved MATT KELLERMAN
Deputy Reinf. Concrete 3/11/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 3/11/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 3/12/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 3/13/2020 Conditional Approval MATT KELLERMAN
Deputy Steel/Welding 3/18/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 3/19/2020 Conditional Approval MATT KELLERMAN
Deputy Steel/Welding 3/20/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 3/24/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 3/25/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 3/26/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 3/27/2020 Conditional Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 3/27/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 4/23/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 4/24/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 4/27/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 4/28/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 4/29/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 4/30/2020 Conditional Approval MATT KELLERMAN
Deputy Steel/Welding 5/1/2020 Approved MATT KELLERMAN
Special/Order Compliance 5/2/2020 Partial Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 5/8/2020 Conditional Approval MATT KELLERMAN
Rough-Elec/Plmb/HVAC 5/8/2020 Partial Approval MATT KELLERMAN
Sewer 5/13/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Not Ready for Inspection MATT KELLERMAN
Light Gage Steel Frame 5/22/2020 Not Ready for Inspection MATT KELLERMAN
Light Gage Steel Frame 6/3/2020 Partial Inspection CHRISTOPHER WILSON
Light Gage Steel Frame 6/15/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval CHRISTOPHER WILSON
Light Gage Steel Frame 7/10/2020 Corrections Issued CHRISTOPHER WILSON
Light Gage Steel Frame 7/14/2020 Partial Inspection CHRISTOPHER WILSON
Light Gage Steel Frame 7/15/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 7/20/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 7/22/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Partial Approval MATT KELLERMAN
Light Gage Steel Frame 8/19/2020 Approved MATT KELLERMAN
PLUMBING-Rough 8/21/2020 Partial Approval MATT KELLERMAN
PLUMBING-Rough 8/25/2020 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 8/26/2020 Partial Approval MATT KELLERMAN
Underground Mechanical 8/26/2020 Partial Approval MATT KELLERMAN
Green Building Rough 8/27/2020 Approved MATT KELLERMAN
Structural Steel Frame 8/27/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 8/27/2020 Not Ready for Inspection MATT KELLERMAN
Footing/Foundation/Slab 9/1/2020 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 9/4/2020 Conditional Approval MATT KELLERMAN
Reinforced Concrete Frame 9/11/2020 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 9/11/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 9/16/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 9/17/2020 Conditional Approval MATT KELLERMAN
Verify Sprinkler Sign Off 9/18/2020 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 9/25/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/20/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 10/21/2020 Partial Approval MATT KELLERMAN
PLUMBING-Rough 10/29/2020 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/30/2020 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/30/2020 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 12/10/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/16/2020 Partial Approval MATT KELLERMAN
HVAC-Rough 12/21/2020 Partial Approval MATT KELLERMAN
PLUMBING-Rough 12/21/2020 Partial Approval MATT KELLERMAN
PLUMBING-Rough 12/23/2020 Partial Approval MATT KELLERMAN
PLUMBING-Rough 12/28/2020 Partial Approval MATT KELLERMAN
Insulation 1/14/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 1/19/2021 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 1/27/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 1/27/2021 Corrections Issued CHRISTOPHER WILSON
Insulation 2/1/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/1/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/1/2021 Partial Approval CHRISTOPHER WILSON
Shower Pan 2/2/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/8/2021 Partial Approval CHRISTOPHER WILSON
Shower Pan 2/8/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 2/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 3/3/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 3/8/2021 Not Ready for Inspection MATT KELLERMAN
Drywall Nailing 3/10/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 3/11/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 3/22/2021 Partial Approval CHRISTOPHER WILSON
Insulation 3/22/2021 Partial Approval CHRISTOPHER WILSON
Insulation 3/25/2021 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 3/26/2021 Approved MATT KELLERMAN
Insulation 3/26/2021 Approved MATT KELLERMAN
Drywall Nailing 4/6/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 4/7/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 4/15/2021 Conditional Approval MATT KELLERMAN
Grounding or Bonding 4/20/2021 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 4/27/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/5/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/20/2021 Partial Approval CHRISTOPHER WILSON
Shower Pan 5/20/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/26/2021 Partial Approval CHRISTOPHER WILSON
Shower Pan 5/26/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 6/17/2021 Partial Approval MATT KELLERMAN
Light Gage Steel Frame 6/22/2021 Approved MATT KELLERMAN
Structural Steel Frame 6/22/2021 Partial Approval MATT KELLERMAN
Verify Sprinkler Sign Off 6/22/2021 No Access for Inspection MATT KELLERMAN
PLUMBING-Rough 7/1/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 7/13/2021 Approved MATT KELLERMAN
Reinforced Concrete Frame 7/13/2021 Not Ready for Inspection MATT KELLERMAN
Shower Pan 7/13/2021 Approved MATT KELLERMAN
Verify Sprinkler Sign Off 7/13/2021 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 7/20/2021 Not Ready for Inspection MATT KELLERMAN
Verify Sprinkler Sign Off 7/20/2021 Not Ready for Inspection MATT KELLERMAN
Deputy Steel/Welding 7/28/2021 Conditional Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 7/28/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 7/28/2021 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 7/28/2021 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 7/30/2021 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 8/3/2021 Partial Approval CHRISTOPHER WILSON
Gas Test 8/5/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 8/16/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 8/23/2021 Partial Approval MATT KELLERMAN
Masonry Wall/Backfill 8/25/2021 Partial Approval MATT KELLERMAN
Reinforced Masonry Frame 8/25/2021 Partial Approval MATT KELLERMAN
Rough-Elec/Plmb/HVAC 8/27/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 8/31/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Partial Approval MATT KELLERMAN
Rough-Elec/Plmb/HVAC 9/3/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 9/3/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 9/7/2021 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 9/17/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 9/17/2021 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 9/30/2021 Partial Approval MATT KELLERMAN
Insulation 10/6/2021 Approved CHRISTOPHER WILSON
Drywall Nailing 10/12/2021 Partial Approval DANIEL ORRANTE
ELECTRICAL-Rough 11/3/2021 Partial Approval MATT KELLERMAN
Service/Power Release 11/3/2021 Approved MATT KELLERMAN
Interior/Exterior Lathing 12/15/2021 Partial Approval BRENDAN LOONEY
Special/Order Compliance 12/22/2021 Partial Inspection CLAYTON GRAHAM
Underground Mechanical 12/22/2021 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/23/2021 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/23/2021 Approved CHRISTOPHER WILSON
Green Building Rough 12/23/2021 Approved CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 12/23/2021 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 12/23/2021 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 1/11/2022 Approved CHRISTOPHER WILSON
Reinforced Concrete Frame 1/19/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/1/2022 Partial Approval JOHN KIDWELL
PLUMBING-Final 6/1/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 6/6/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/6/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 6/13/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 6/13/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 6/15/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Final 6/20/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 6/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 6/29/2022 Approved CHRISTOPHER WILSON
HVAC-Final 7/14/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 7/26/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 8/15/2022 Approved CHRISTOPHER WILSON
Final 8/19/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Final 8/19/2022 Approved CHRISTOPHER WILSON
Reinforced Concrete Frame 8/19/2022 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 8/19/2022 Approved CHRISTOPHER WILSON
Structural Steel Frame 8/19/2022 Approved CHRISTOPHER WILSON
Final 9/9/2022 Not Ready for Inspection CHRISTOPHER WILSON
Final 9/26/2022 OK to Issue CofO CHRISTOPHER WILSON