8827 N VAN NUYS BLVD 91402

Certificate Information: 8827 N VAN NUYS BLVD 91402

Application / Permit
16010-20000-05103
Plan Check / Job No.
B16VN15345
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) APARTMENT BUILDING WITH ON GRADE PARKING
Permit Issued
Issued on 11/9/2017
Issuing Office
Valley
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2016 APPLICANT
Assigned to Plan Check Engineer 11/22/2016 KAMRAN GHOTBI RAVANDI
Corrections Issued 11/28/2016 KAMRAN GHOTBI RAVANDI
Quality Review Completed 11/30/2016 TIEN JEN WANG
Building Plans Picked Up 12/5/2016 APPLICANT
Disabled Access Plans Picked Up 12/5/2016 APPLICANT
Green Plans Picked Up 12/5/2016 APPLICANT
Applicant returned to address corrections 4/12/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 4/18/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 4/27/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/16/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/23/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/6/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/14/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/18/2017 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/29/2017 KAMRAN GHOTBI RAVANDI
Issued 11/9/2017 LADBS
CofO in Progress 2/21/2023 DANNY RODRIGUEZ
Permit Finaled 3/15/2023 RICKEY JACKSON
CofO Issued 3/15/2023 RICKEY JACKSON
Permit Finaled 3/15/2023 RICKEY JACKSON

Permit Application Clearance Information

Project located in CRA area Cleared 1/4/2017 JIM URQUHART
Address approval Cleared 1/6/2017 IRENE CHIA
Eng Process Fee Ord 176,300 Cleared 1/6/2017 IRENE CHIA
Hydrant and Access approval Cleared 1/9/2017 JOHN DALLAS
Green Code Cleared 1/12/2017 RICHARD DOCKUS
Driveway location Cleared 1/13/2017 ALBERT ISAGULIAN
Internal circulation Cleared 1/13/2017 ALBERT ISAGULIAN
Construction near power lines Cleared 1/17/2017 LUCIO FERRER
DAS Clearance Cleared 1/26/2017 HAYATO TSUCHIYA
Permit Cleared 2/1/2017 LEE GUILBEAUX
Sewer availability Cleared 2/1/2017 LEE GUILBEAUX
Low Impact Development Cleared 4/6/2017 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 4/6/2017 SEVAK ISAKHAYAN
Highway dedication Cleared 4/18/2017 MARKOS PEREZ-BRAN
Frnt yard landscape/Water mgmt Cleared 7/25/2017 DAISY BENICIA
Opn space landscape/Water mgmt Cleared 7/25/2017 DAISY BENICIA

Contact Information

Contractor Owner-Builder       ,
Engineer Ni, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/20/2018 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/13/2018 Not Ready for Inspection DANNY RODRIGUEZ
SWPPP-Const. Storm Water 3/22/2018 Not Required DANNY RODRIGUEZ
Masonry Wall/Backfill 4/23/2018 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 5/9/2018 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 6/1/2018 Partial Inspection ANDREW DORSO
Reinforced Concrete Frame 6/1/2018 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 6/12/2018 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 6/13/2018 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/13/2018 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/13/2018 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/15/2018 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/15/2018 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/18/2018 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/22/2018 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/22/2018 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 10/22/2018 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/22/2018 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/23/2018 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 10/23/2018 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 10/23/2018 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/25/2018 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/25/2018 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 10/25/2018 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/25/2018 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/29/2018 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/26/2018 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 11/26/2018 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/26/2018 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 11/26/2018 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 11/27/2018 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/27/2018 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 11/29/2018 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/29/2018 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 11/29/2018 No Access for Inspection DANNY RODRIGUEZ
Wood Frame 11/29/2018 No Access for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/4/2018 Partial Approval DANNY RODRIGUEZ
Green Building Rough 12/4/2018 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/4/2018 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 12/4/2018 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/4/2018 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/11/2019 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 1/11/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/11/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/11/2019 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/29/2019 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/29/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/29/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/29/2019 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 3/8/2019 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 3/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/13/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 3/19/2019 Approved DANNY RODRIGUEZ
Deputy Drilled-In Anchors 3/26/2019 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/28/2019 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 3/28/2019 Not Ready for Inspection DANNY RODRIGUEZ
Wall Anchors 3/28/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 4/18/2019 Corrections Issued DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/18/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/23/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 4/23/2019 No Access for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/23/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 5/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/1/2019 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/7/2019 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 5/7/2019 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/7/2019 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/13/2020 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 10/14/2020 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 10/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 10/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 10/23/2020 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 12/9/2020 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 12/9/2020 Not Ready for Inspection JOHN KITCKO
Masonry Wall/Backfill 12/17/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 12/30/2020 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/5/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/5/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/8/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/8/2021 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 2/11/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/11/2021 Partial Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/17/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/17/2021 Partial Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/22/2021 Partial Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/5/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 3/5/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/23/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 3/23/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/30/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 4/5/2021 Approved HAMID PISHEHVAR
Pre-Inspection 4/6/2021 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 4/14/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 4/22/2021 Partial Inspection DANNY RODRIGUEZ
Final 8/10/2022 Partial Inspection DANNY RODRIGUEZ
Smoke Detectors 8/10/2022 Approved DANNY RODRIGUEZ
Drywall Nailing 1/17/2023 Approved DANNY RODRIGUEZ
Final 1/17/2023 OK to Issue CofO DANNY RODRIGUEZ
Footing/Foundation/Slab 1/17/2023 Approved DANNY RODRIGUEZ
Green Building Final 1/17/2023 Approved DANNY RODRIGUEZ
Green Building Rough 1/17/2023 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 1/17/2023 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 1/17/2023 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Approved DANNY RODRIGUEZ
Structural Steel Frame 1/17/2023 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/17/2023 Approved DANNY RODRIGUEZ
Wood Frame 1/17/2023 Approved DANNY RODRIGUEZ