Footing/Foundation/Slab
|
2/20/2018
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
3/13/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SWPPP-Const. Storm Water
|
3/22/2018
|
Not Required
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
4/23/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
5/9/2018
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
6/1/2018
|
Partial Inspection
|
ANDREW DORSO
|
|
Reinforced Concrete Frame
|
6/1/2018
|
Partial Inspection
|
ANDREW DORSO
|
|
Masonry Wall/Backfill
|
6/12/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
6/13/2018
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/13/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
8/13/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/15/2018
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
8/15/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/18/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
10/22/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
10/22/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
10/22/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
10/22/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
10/23/2018
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/23/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wall Anchors
|
10/23/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
10/25/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
10/25/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
10/25/2018
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
10/25/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
10/29/2018
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/26/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
11/26/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
11/26/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
11/26/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Wood Construction
|
11/27/2018
|
Approved
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/27/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
11/29/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
11/29/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wall Anchors
|
11/29/2018
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
11/29/2018
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/4/2018
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
12/4/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
12/4/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wall Anchors
|
12/4/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
12/4/2018
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/11/2019
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/11/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
1/11/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/11/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/29/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/29/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
1/29/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/29/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
3/8/2019
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
3/13/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
3/13/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
3/13/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
3/18/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
3/18/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
3/18/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Wood Construction
|
3/19/2019
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
3/26/2019
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/28/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
3/28/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wall Anchors
|
3/28/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/18/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
4/18/2019
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
4/18/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/23/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
4/23/2019
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
4/23/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
5/1/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
5/1/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
5/1/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
5/7/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
5/7/2019
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
5/7/2019
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
10/13/2020
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/14/2020
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
10/14/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
10/14/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
10/23/2020
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
12/9/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Masonry Wall/Backfill
|
12/9/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Masonry Wall/Backfill
|
12/17/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
12/30/2020
|
Partial Approval
|
JOHN KITCKO
|
|
Masonry Wall/Backfill
|
2/4/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
2/4/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
2/5/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
2/5/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
2/8/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
2/8/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
2/11/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
2/11/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
2/17/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
2/17/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
2/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
2/22/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
3/5/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
3/5/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
3/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
3/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
3/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
4/5/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Pre-Inspection
|
4/6/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
4/14/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
4/22/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
8/10/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
8/10/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Final
|
1/17/2023
|
OK to Issue CofO
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
1/17/2023
|
SGSOV Approved
|
DANNY RODRIGUEZ
|
|
Structural Steel Frame
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
1/17/2023
|
Approved
|
DANNY RODRIGUEZ
|