533 N LEWIS ST 90042
Certificate Information: 533 N LEWIS ST 90042
- Application / Permit
- 16010-20000-04891
- Plan Check / Job No.
- B16VN14633
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD W/ BASEMENT ATTACHED CARPORT & ROOF TOP DECK (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 4/20/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2016 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/21/2016 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/22/2016 | TIEN JEN WANG |
| Building Plans Picked Up | 11/22/2016 | APPLICANT |
| Green Plans Picked Up | 11/22/2016 | APPLICANT |
| Applicant returned to address corrections | 2/15/2017 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/17/2018 | NILOOFAR MEHRAIN |
| Issued | 4/20/2018 | LADBS |
| CofO in Progress | 10/19/2021 | SCOTT FINNILA |
| Permit Finaled | 10/22/2021 | DEROLD HAUFF |
| CofO Issued | 10/22/2021 | DEROLD HAUFF |
| Permit Finaled | 10/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/1/2017 | SAM NAVID |
| Address approval | Cleared | 2/8/2017 | IRENE CHIA |
| BHO/Hillside ordinance | Cleared | 2/8/2017 | IRENE CHIA |
| BHO/Hillside ordinance | Cleared | 2/8/2017 | IRENE CHIA |
| BHO/Hillside ordinance | Cleared | 2/8/2017 | IRENE CHIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2017 | IRENE CHIA |
| Miscellaneous | Cleared | 2/8/2017 | TRACY WILLIAMS |
| Permit | Cleared | 2/8/2017 | IRENE CHIA |
| Roof/Waste drainage to street | Cleared | 2/8/2017 | IRENE CHIA |
| Sewer availability | Cleared | 2/8/2017 | IRENE CHIA |
| Hydrant and Access approval | Cleared | 10/25/2017 | JOHN DALLAS |
| Excavation more than 5-ft deep | Cleared | 4/17/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/17/2018 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 4/17/2018 | NILOOFAR MEHRAIN |
| Work Adjacent to Public Way | Cleared | 4/18/2018 | BOK GOH |
| Green Code | Cleared | 4/20/2018 | RUSSELL KELLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Taroian, Armen; Lic. No.: C78011 | 404 W STOCKER ST APT 1 GLENDALE, CA 91202 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/4/2019 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/23/2019 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 5/24/2019 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/28/2019 | Partial Approval | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 6/28/2019 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/1/2019 | No Access for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/1/2019 | No Access for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/12/2019 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 7/12/2019 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/12/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2019 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2019 | Corrections Issued | RUBEN SALAS |
| HVAC-Rough | 9/6/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/6/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2019 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 9/20/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/26/2019 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 9/26/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 10/4/2019 | Approved | ENRIQUE MIRELES |
| Insulation | 10/9/2019 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/22/2019 | Approved | ENRIQUE MIRELES |
| Deck | 12/5/2019 | Approved | RUBEN SALAS |
| Shower Pan | 12/6/2019 | Corrections Issued | ENRIQUE MIRELES |
| Shower Pan | 12/9/2019 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/12/2019 | Not Ready for Inspection | RUBEN SALAS |
| Interior/Exterior Lathing | 12/17/2019 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/19/2019 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 2/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 2/28/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 3/4/2020 | Approved | ENRIQUE MIRELES |
| Reinforced Concrete Frame | 3/4/2020 | Approved | ENRIQUE MIRELES |
| Reinforced Masonry Frame | 3/4/2020 | Approved | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 5/6/2020 | Partial Approval | OSVALDO PARAMO |
| Sewer | 5/19/2020 | Approved | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 5/27/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 6/3/2020 | Approved | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 6/12/2020 | Partial Approval | COREY HUPP |
| Masonry Wall/Backfill | 6/15/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/6/2020 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 8/11/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Gas Test | 8/31/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 9/4/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/8/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 9/11/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/9/2020 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 7/15/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 7/15/2021 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 7/15/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 7/15/2021 | SGSOV Not Ready | COREY HUPP |
| Service/Power Release | 7/15/2021 | Not Ready for Inspection | COREY HUPP |
| Smoke Detectors | 7/15/2021 | Not Ready for Inspection | COREY HUPP |
| Verify Sprinkler Sign Off | 7/15/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 7/28/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 7/28/2021 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 7/28/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Not Ready | COREY HUPP |
| Service/Power Release | 7/28/2021 | Not Ready for Inspection | COREY HUPP |
| Smoke Detectors | 7/28/2021 | Not Ready for Inspection | COREY HUPP |
| Verify Sprinkler Sign Off | 7/28/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 8/4/2021 | Approved | COREY HUPP |
| Final | 8/4/2021 | Partial Inspection | COREY HUPP |
| Green Building Final | 8/4/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Not Ready | COREY HUPP |
| Service/Power Release | 8/4/2021 | Not Ready for Inspection | COREY HUPP |
| Smoke Detectors | 8/4/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 8/4/2021 | Approved | COREY HUPP |
| Final | 8/9/2021 | Corrections Issued | COREY HUPP |
| Green Building Final | 8/9/2021 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Approved | COREY HUPP |
| Service/Power Release | 8/9/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 8/11/2021 | Corrections Issued | COREY HUPP |
| Service/Power Release | 8/11/2021 | Approved | COREY HUPP |
| Final | 8/16/2021 | Corrections Issued | COREY HUPP |
| Final | 8/19/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 8/20/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 8/25/2021 | Corrections Issued | RUBEN SALAS |
| Final | 9/3/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 10/5/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 10/5/2021 | Partial Approval | SCOTT FINNILA |
| Final | 10/7/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 10/19/2021 | OK to Issue CofO | SCOTT FINNILA |