12680 N BRADLEY AVE UNIT # 7 91342

Certificate Information: 12680 N BRADLEY AVE UNIT # 7 91342

Application / Permit
16010-20000-04821
Plan Check / Job No.
B16VN14405
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(VTT-74518-CN) PROPOSE TWO STORY SFD WITH ATTACHED 2 CAR GARAGE
Permit Issued
Issued on 2/23/2018
Issuing Office
Valley
Current Status
CofO Issued on 7/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2016 APPLICANT
Assigned to Plan Check Engineer 11/22/2016 DAWN MC NULTY
Green Plans Picked Up 11/23/2016 APPLICANT
Corrections Issued 12/9/2016 DAWN MC NULTY
Quality Review Completed 12/9/2016 GUANG MIN TUNG
Building Plans Picked Up 12/12/2016 APPLICANT
Applicant returned to address corrections 8/18/2017 DAWN MC NULTY
Applicant returned to address corrections 9/11/2017 DAWN MC NULTY
Applicant returned to address corrections 10/17/2017 DAWN MC NULTY
Applicant returned to address corrections 11/28/2017 DAWN MC NULTY
Plan Check Approved 2/15/2018 DAWN MC NULTY
Issued 2/23/2018 LADBS
CofO in Progress 7/12/2021 JOSEPH SAGEN
CofO Issued 7/13/2021 MICHAEL SMITH
Permit Finaled 7/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/1/2017 JOHN DALLAS
CPC Cleared 12/11/2017 HERMINIGILDO AGUSTIN
Miscellaneous Cleared 12/11/2017 HERMINIGILDO AGUSTIN
Tract Map conditions Cleared 12/27/2017 HERMINIGILDO AGUSTIN
Tract Map conditions Cleared 12/27/2017 HERMINIGILDO AGUSTIN
CPC Cleared 2/8/2018 HERMINIGILDO AGUSTIN
Frnt yard landscape/Water mgmt Cleared 2/8/2018 HERMINIGILDO AGUSTIN
Opn space landscape/Water mgmt Cleared 2/8/2018 HERMINIGILDO AGUSTIN
Low Impact Development Cleared 2/12/2018 MITESH PATEL
Green Code Cleared 2/14/2018 MICHAEL AYERS
Address approval Cleared 2/15/2018 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 2/15/2018 MARKOS PEREZ-BRAN
Highway dedication Cleared 2/15/2018 MARKOS PEREZ-BRAN
Miscellaneous Cleared 2/15/2018 CHRISTINE BUSTILLOS
Roof/Waste drainage to street Cleared 2/15/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/15/2018 MARKOS PEREZ-BRAN
Work Adjacent to Public Way Cleared 2/15/2018 MARKOS PEREZ-BRAN
ZI Cleared 2/15/2018 CHRISTINE BUSTILLOS
Permit Cleared 2/22/2018 MARKOS PEREZ-BRAN

Contact Information

Engineer Chamberlain, Robert Douglas; Lic. No.: C67937 7235 DE CELIS PL      VAN NUYS, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/1/2019 Corrections Issued BRUCE ROZAK
Underground Mechanical 5/3/2019 Approved BRUCE ROZAK
Excavation/Setback/Form/Re-Bar 5/15/2019 Approved DONALD SUNSERI
Footing/Foundation/Slab 5/15/2019 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Partial Approval DONALD SUNSERI
Deputy Wood Construction 6/28/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 6/28/2019 Approved JOSEPH SAGEN
ELECTRICAL-Rough 8/14/2019 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 8/14/2019 Approved JOSEPH SAGEN
PLUMBING-Rough 8/14/2019 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Rough 8/20/2019 Approved JOSEPH SAGEN
PLUMBING-Rough 8/20/2019 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 8/27/2019 Not Ready for Inspection JOSEPH SAGEN
Green Building Rough 8/27/2019 Not Ready for Inspection JOSEPH SAGEN
Verify Sprinkler Sign Off 8/27/2019 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 8/29/2019 Approved JOSEPH SAGEN
Green Building Rough 8/29/2019 Approved JOSEPH SAGEN
Insulation 9/4/2019 Approved JOSEPH SAGEN
Drywall Nailing 9/27/2019 Approved JOSEPH SAGEN
Interior/Exterior Lathing 9/27/2019 Approved JOSEPH SAGEN
Sewer 5/28/2020 Approved JOSEPH SAGEN
Underground Mechanical 7/6/2020 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 7/8/2020 Partial Approval JOSEPH SAGEN
Service/Power Release 7/10/2020 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 9/17/2020 Partial Approval JOSEPH SAGEN
Underground Mechanical 9/21/2020 Partial Approval JOSEPH SAGEN
Gas Test 10/27/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 10/27/2020 SGSOV Approved JOSEPH SAGEN
Service/Power Release 11/9/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 4/26/2021 Approved JOSEPH SAGEN
HVAC-Final 4/26/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 4/26/2021 Approved JOSEPH SAGEN
Final 5/21/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 5/21/2021 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 5/21/2021 Approved JOSEPH SAGEN
Final 6/3/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 6/3/2021 Not Ready for Inspection JOSEPH SAGEN
Final 6/15/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 6/15/2021 Approved JOSEPH SAGEN
HVAC-Final 6/15/2021 Approved JOSEPH SAGEN
Final 7/9/2021 OK to Issue CofO JOSEPH SAGEN