901 S ABBOT KINNEY BLVD 90291

Certificate Information: 901 S ABBOT KINNEY BLVD 90291

Application / Permit
16010-20000-04655
Plan Check / Job No.
B16VN14052
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(35) Condo-Multi Family
Work Description
(N) MIXED USE 2-STORY TYPE V-A HOTEL & 5-UNIT CONDO OVER 1-STORY TYPE I-A HOTEL, RETAIL TENANT SPACES & 2-LEVEL SUBTERRANEAN PARKING GARAGE W/ AUTO MECHANICAL LIFT (NFPA-13 FIRE SPRINKLERS THROUHOUT)
Permit Issued
Issued on 8/8/2022
Issuing Office
Metro
Current Status
Issued on 8/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/11/2016 APPLICANT
Assigned to Plan Check Engineer 11/3/2016 NILOOFAR MEHRAIN
Disabled Access Plans Picked Up 11/3/2016 APPLICANT
Green Plans Picked Up 11/3/2016 APPLICANT
Corrections Issued 11/14/2016 NILOOFAR MEHRAIN
Quality Review Completed 11/15/2016 GUANG MIN TUNG
Building Plans Picked Up 11/29/2016 APPLICANT
Applicant returned to address corrections 1/24/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/27/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/26/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/28/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/1/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/15/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/6/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/27/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/15/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/2/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/13/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/30/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/19/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/25/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/14/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/30/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/13/2019 NILOOFAR MEHRAIN
Plan Check Approved 12/18/2019 NILOOFAR MEHRAIN
Issued 8/8/2022 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/5/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 3/21/2019 KARAN PATEL
Building over 3-story or 36-ft Cleared 5/13/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/13/2019 CALOSHA APPROVED
Encroachment in public way Cleared 6/6/2019 STEVEN JIN
Highway dedication Cleared 6/20/2019 JOSE CRUZ RODRIGUEZ
Green Code Cleared 6/25/2019 RICHARD DOCKUS
Mechanical Car Lift Cleared 7/9/2019 DOMINIQUE MEDINA
Low Impact Development Cleared 7/10/2019 RYAN HUDSON
Stormwater Pollution Mitigatn Cleared 7/10/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 7/24/2019 HISASHI KOBAYAKAWA
Miscellaneous Cleared 8/7/2019 STEVEN JIN
DAS Clearance Cleared 8/9/2019 NORLITO MEDRANO
Bicycle Parking Cleared 8/12/2019 STEVEN JIN
Permit Cleared 9/23/2019 KATHLEEN HUGHEY
Sewer availability Cleared 9/23/2019 DINAH GARIN
Specific Plan Cleared 9/25/2019 VALERIA CEJA
Specific Plan Cleared 9/25/2019 VALERIA CEJA
Work Adjacent to Public Way Cleared 11/25/2019 ANTHONY MAINEZ
Fire Marshall Fire Life Safety Cleared 12/10/2019 DOMINIQUE MEDINA
Coastal Zone Cleared 12/11/2019 LATANYA ROUX
Comm Cor/Mini-Mall Cleared 12/11/2019 LATANYA ROUX
Mello Bill Cleared 12/11/2019 LATANYA ROUX
Miscellaneous Cleared 12/11/2019 LATANYA ROUX
Miscellaneous Cleared 12/11/2019 LATANYA ROUX
Miscellaneous Cleared 12/11/2019 LATANYA ROUX
Miscellaneous Cleared 12/11/2019 LATANYA ROUX
Miscellaneous Cleared 12/11/2019 LATANYA ROUX
Specific Plan Cleared 12/11/2019 LATANYA ROUX
Tract Map conditions Cleared 12/11/2019 LATANYA ROUX
ZA Case Cleared 12/11/2019 LATANYA ROUX
ZA Case Cleared 12/11/2019 LATANYA ROUX
Address approval Cleared 6/27/2022 HISASHI KOBAYAKAWA

Contact Information

Architect Thibodeau,, Robert E; Lic. No.: C25585 812 LINCOLN BLVD      VENICE, CA 90291
Contractor Hb Parkco Construction Inc; Lic. No.: 816387-B 2973 HARBOR BLVD STE E      COSTA MESA, CA 92626
Engineer Howe, Carl William; Lic. No.: C44773 3347 MOTOR AVE STE 200   C W HOWE PARTNERS INC.    LOS ANGELES, CA 90034
Engineer Prince,, Scott Taylor; Lic. No.: C83961 1720 BUTLER AVE 3      LOS ANGELES, CA 90025

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/26/2024 Partial Approval PAUL DAVIDSON
METHANE-Barrier 6/26/2024 Partial Approval PAUL DAVIDSON
METHANE-Subgrade 6/26/2024 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 7/10/2024 Partial Approval PAUL DAVIDSON
METHANE-Barrier 7/10/2024 Partial Approval PAUL DAVIDSON
METHANE-Subgrade 7/10/2024 Partial Approval PAUL DAVIDSON
Green Building Rough 7/16/2024 Not Ready for Inspection PAUL DAVIDSON
METHANE-Rough 7/16/2024 Partial Approval PAUL DAVIDSON
Reinforced Concrete Frame 7/16/2024 Partial Approval PAUL DAVIDSON
Verify Sprinkler Sign Off 7/16/2024 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 7/24/2024 Not Ready for Inspection PAUL DAVIDSON
METHANE-Rough 7/24/2024 Partial Approval PAUL DAVIDSON
Reinforced Concrete Frame 7/24/2024 Partial Approval PAUL DAVIDSON
Verify Sprinkler Sign Off 7/24/2024 Not Ready for Inspection PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 7/29/2024 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 8/14/2024 Partial Approval DERRICK SPENCER
METHANE-Barrier 8/14/2024 Approved DERRICK SPENCER
METHANE-Subgrade 8/14/2024 Approved DERRICK SPENCER
Piling/Pier/Caisson 8/19/2024 Partial Approval DERRICK SPENCER
Green Building Rough 9/3/2024 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 9/3/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 9/3/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 9/3/2024 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 9/18/2024 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 9/18/2024 Corrections Issued DANIEL VARNUM
Green Building Rough 9/18/2024 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 9/18/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 9/18/2024 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 9/18/2024 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 9/21/2024 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 9/21/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 9/21/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 9/21/2024 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 9/23/2024 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 10/1/2024 Approved DERRICK SPENCER
Deputy Reinf. Concrete 10/3/2024 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 10/4/2024 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 10/4/2024 Conditional Approval DANIEL VARNUM
Green Building Rough 10/4/2024 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 10/4/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 10/4/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 10/4/2024 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 10/7/2024 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 10/10/2024 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 10/10/2024 Conditional Approval DANIEL VARNUM
Green Building Rough 10/10/2024 Partial Inspection DANIEL VARNUM
METHANE-Rough 10/10/2024 Partial Inspection DANIEL VARNUM
Reinforced Concrete Frame 10/10/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 10/10/2024 Not Ready for Inspection DANIEL VARNUM
Deputy Shotcrete 10/11/2024 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 10/11/2024 Partial Approval DANIEL VARNUM
Deputy Shotcrete 10/15/2024 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 10/16/2024 Conditional Approval DANIEL VARNUM
Green Building Rough 10/17/2024 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 10/17/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 10/17/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 10/17/2024 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 10/23/2024 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 10/23/2024 Partial Approval DANIEL VARNUM
Reinforced Concrete Frame 10/23/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 10/23/2024 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 10/28/2024 Not Ready for Inspection DANIEL VARNUM
METHANE-Rough 10/28/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 10/28/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 10/28/2024 Not Ready for Inspection DANIEL VARNUM
Deputy Shotcrete 11/4/2024 Conditional Approval PAUL DAVIDSON
Green Building Rough 11/18/2024 Not Ready for Inspection PAUL DAVIDSON
METHANE-Rough 11/18/2024 Approved PAUL DAVIDSON
Reinforced Concrete Frame 11/18/2024 Not Ready for Inspection PAUL DAVIDSON
Verify Sprinkler Sign Off 11/18/2024 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 11/25/2024 Not Ready for Inspection PAUL DAVIDSON
Reinforced Concrete Frame 11/25/2024 Partial Approval PAUL DAVIDSON
Verify Sprinkler Sign Off 11/25/2024 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 12/5/2024 Not Ready for Inspection PAUL DAVIDSON
Reinforced Concrete Frame 12/5/2024 Partial Approval PAUL DAVIDSON
Verify Sprinkler Sign Off 12/5/2024 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 12/19/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 12/19/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 12/19/2024 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 12/26/2024 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 12/26/2024 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 12/26/2024 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 1/2/2025 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 1/2/2025 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 1/2/2025 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 4/22/2025 Approved DERRICK SPENCER
Reinforced Concrete Frame 4/22/2025 Partial Approval DERRICK SPENCER
Verify Sprinkler Sign Off 4/22/2025 Approved DERRICK SPENCER
Reinforced Concrete Frame 5/12/2025 Corrections Issued DANIEL VARNUM
Reinforced Concrete Frame 5/16/2025 Partial Approval RICARDO ROBLES
Reinforced Concrete Frame 5/27/2025 Partial Approval PAUL DAVIDSON
Special/Order Compliance 6/25/2025 Partial Inspection PAUL DAVIDSON
Footing/Foundation/Slab 7/25/2025 Partial Approval DANIEL VARNUM
Pre-Inspection 8/7/2025 Partial Inspection PAUL DAVIDSON
Footing/Foundation/Slab 8/22/2025 Partial Approval DANIEL VARNUM
Special/Order Compliance 11/24/2025 Partial Inspection PAUL DAVIDSON
Deputy Shotcrete 4/16/2026 Conditional Approval PAUL DAVIDSON
Special/Order Compliance 7/8/2026 Partial Inspection PAUL DAVIDSON