13741 W MULHOLLAND DR 90210

Certificate Information: 13741 W MULHOLLAND DR 90210

Application / Permit
16010-20000-04614
Plan Check / Job No.
B16VN13923
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH ATT. GARAGE & BASEMENT. <SPRINKLERS RREQ'D THROUGHOUT>
Permit Issued
Issued on 5/9/2017
Issuing Office
Valley
Current Status
CofO Issued on 12/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2016 APPLICANT
Assigned to Plan Check Engineer 11/3/2016 ABDUL CHEGENI
Green Plans Picked Up 11/4/2016 APPLICANT
Corrections Issued 11/7/2016 ABDUL CHEGENI
Quality Review Completed 11/10/2016 TIEN JEN WANG
Building Plans Picked Up 11/15/2016 APPLICANT
Applicant returned to address corrections 12/27/2016 ABDUL CHEGENI
Applicant returned to address corrections 2/16/2017 ABDUL CHEGENI
Applicant returned to address corrections 4/26/2017 ABDUL CHEGENI
Plan Check Approved 5/9/2017 ABDUL CHEGENI
Issued 5/9/2017 LADBS
CofO in Progress 12/8/2022 MISAEL ESPARZA
Permit Finaled 12/20/2022 MICHAEL SMITH
CofO Issued 12/20/2022 MICHAEL SMITH
Permit Finaled 12/20/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/27/2016 ERIK MUNOZ
BHO/Hillside ordinance Cleared 12/27/2016 ERIK MUNOZ
BHO/Hillside ordinance Cleared 12/27/2016 ERIK MUNOZ
Eng Process Fee Ord 176,300 Cleared 12/27/2016 ERIK MUNOZ
Highway dedication Cleared 12/27/2016 ERIK MUNOZ
Work Adjacent to Public Way Cleared 12/27/2016 ERIK MUNOZ
Hydrant and Access approval Cleared 1/17/2017 JOHN DALLAS
Disturb/Remove Protected Trees Cleared 1/20/2017 ADRIAN SANCHEZ
Green Code Cleared 1/30/2017 RICHARD DOCKUS
Miscellaneous Cleared 1/30/2017 TREVOR MARTIN
Specific Plan Cleared 1/30/2017 TREVOR MARTIN
ZA Case Cleared 1/30/2017 TREVOR MARTIN
Private street Cleared 1/31/2017 TREVOR MARTIN
Low Impact Development Cleared 2/3/2017 MARTIN FRAGOSO
Excavation more than 5-ft deep Cleared 2/16/2017 CALOSHA APPROVED
GPI Written Notices Cleared 2/16/2017 ABDUL CHEGENI
Grading Pre-Inspection Cleared 2/16/2017 ABDUL CHEGENI
Miscellaneous Cleared 2/16/2017 ABDUL CHEGENI
Roof/Waste drainage to street Cleared 4/26/2017 IRENE CHIA
Private sewage disp. approval Cleared 4/27/2017 ABDUL CHEGENI

Contact Information

Architect Hoffman, Fred; Lic. No.: C8128 11558 KLING STREET      NORTH HOLLYWOOD, CA 91602
Contractor Owner-Builder       ,
Engineer Babakhanian, Oksen; Lic. No.: S3500 6854 FOOTHILL BLVD      TUJUNGA, CA 91042
Engineer Boghossian, George Gourgen; Lic. No.: C34361 1101 KILDONAN DRIVE      GLENDALE, CA 91207
Engineer Hollingsworth, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Geologist Grover, David J; Lic. No.: EG1095 31129 VIA COLINAS #707      WESTLAKE VILLAGE, CA 91362

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/14/2018 Partial Approval RAYMOND KEHOE
Deputy Reinf. Concrete 11/15/2018 No Access for Inspection ROBERT SHELLY
Footing/Foundation/Slab 12/17/2018 Partial Approval JEFFREY PARD
Reinforced Concrete Frame 12/17/2018 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 1/11/2019 Partial Approval RAYMOND KEHOE
Underground Mechanical 1/30/2019 Partial Approval COREY HUPP
Footing/Foundation/Slab 2/19/2019 Partial Approval COREY HUPP
Footing/Foundation/Slab 3/20/2019 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 3/21/2019 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 7/10/2019 Approved THOMAS FINNILA
Piling/Pier/Caisson 7/11/2019 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 7/12/2019 Approved THOMAS FINNILA
Piling/Pier/Caisson 7/15/2019 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 7/23/2019 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 8/5/2019 Approved THOMAS FINNILA
Footing/Foundation/Slab 8/21/2019 Partial Approval THOMAS FINNILA
Deputy Shotcrete 8/22/2019 Conditional Approval THOMAS FINNILA
Underground Mechanical 9/5/2019 Partial Approval RAYMOND KEHOE
Deputy Reinf. Concrete 9/25/2019 Approved RAYMOND KEHOE
Footing/Foundation/Slab 9/25/2019 Partial Approval RAYMOND KEHOE
Deputy Reinf. Concrete 10/1/2019 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 10/18/2019 Approved THOMAS FINNILA
Reinforced Concrete Frame 10/18/2019 Partial Approval THOMAS FINNILA
Deputy Shotcrete 10/21/2019 Conditional Approval THOMAS FINNILA
Deputy Steel/Welding 11/25/2019 Conditional Approval DANIEL ORRANTE
Green Building Rough 2/10/2020 Not Ready for Inspection CHARLES POWELL
Structural Steel Frame 2/10/2020 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 2/10/2020 Not Ready for Inspection CHARLES POWELL
Deputy Drilled-In Anchors 2/11/2020 Approved CHARLES POWELL
Light Gage Steel Frame 2/13/2020 Partial Approval CHARLES POWELL
Special/Order Compliance 2/13/2020 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Not Ready for Inspection CHARLES POWELL
Insulation 6/24/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 7/22/2020 Approved CHARLES POWELL
Underground Mechanical 8/13/2020 Partial Approval CHARLES POWELL
Underground Mechanical 8/24/2020 Approved CHARLES POWELL
Deputy Steel/Welding 10/23/2020 Approved CHARLES POWELL
Wood Frame 10/23/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Approved CHARLES POWELL
Piling/Pier/Caisson 11/18/2020 Approved CHARLES POWELL
Insulation 12/8/2020 Partial Approval CHARLES POWELL
Deputy Steel/Welding 12/15/2020 Partial Approval CHARLES POWELL
Interior/Exterior Lathing 2/8/2021 Approved CHARLES POWELL
Sewer 2/25/2021 Approved CHARLES POWELL
Excavation/Setback/Form/Re-Bar 4/16/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 5/14/2021 Approved MARK JOHNSON
HVAC-Rough 5/14/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 5/20/2021 Corrections Issued CHARLES POWELL
Green Building Rough 5/20/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 5/20/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 6/1/2021 Partial Approval CHARLES POWELL
Green Building Rough 6/1/2021 Partial Approval CHARLES POWELL
Verify Sprinkler Sign Off 6/1/2021 Approved CHARLES POWELL
Deputy Wood Construction 7/2/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 7/21/2021 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Approved CHARLES POWELL
Insulation 8/17/2021 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/17/2021 Approved ALIZAH MAYAGOITIA
Insulation 8/24/2021 Partial Approval ALIZAH MAYAGOITIA
Insulation 9/8/2021 Partial Inspection THOMAS FINNILA
BUILDING-Rough-Frame 9/22/2021 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 9/22/2021 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 9/22/2021 Approved ALIZAH MAYAGOITIA
Insulation 9/22/2021 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 10/22/2021 Partial Approval MISAEL ESPARZA
Insulation 2/2/2022 Approved MISAEL ESPARZA
Drywall Nailing 2/16/2022 Partial Approval MISAEL ESPARZA
Drywall Nailing 4/29/2022 Approved ARAM AVEDISIAN
Pre-Inspection 7/14/2022 Approved MISAEL ESPARZA
Gas Test 8/24/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/30/2022 Approved MISAEL ESPARZA
Footing/Foundation/Slab 8/30/2022 Approved MISAEL ESPARZA
Green Building Final 8/30/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 8/30/2022 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 8/30/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 9/6/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 9/6/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/11/2022 Partial Approval DAVID MATSON
HVAC-Final 10/18/2022 Corrections Issued MISAEL ESPARZA
Final 11/2/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 11/2/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 11/2/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/2/2022 Approved MISAEL ESPARZA
Final 12/5/2022 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 12/5/2022 Approved MISAEL ESPARZA
Reinforced Masonry Frame 12/6/2022 Approved MISAEL ESPARZA
Service/Power Release 12/6/2022 Approved MISAEL ESPARZA
Structural Steel Frame 12/6/2022 Approved MISAEL ESPARZA