10002 N VALLEY CIRCLE BLVD 91311
Certificate Information: 10002 N VALLEY CIRCLE BLVD 91311
- Application / Permit
- 16010-20000-04492
- Plan Check / Job No.
- B16VN13642
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER AB494 & SB229 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 11/6/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2016 | APPLICANT |
| Green Plans Picked Up | 10/19/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2016 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/1/2016 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/2/2016 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/3/2016 | APPLICANT |
| Applicant returned to address corrections | 9/13/2018 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/28/2018 | NILOOFAR MEHRAIN |
| Issued | 11/6/2018 | LADBS |
| CofO in Progress | 11/15/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 12/28/2022 | MICHAEL SMITH |
| CofO Issued | 12/28/2022 | MICHAEL SMITH |
| Permit Finaled | 12/28/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/13/2016 | HOWARD COOPER |
| Permit | Cleared | 12/13/2016 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2017 | EDUARDO PEDROZA |
| Hydrant and Access approval | Cleared | 9/12/2017 | JOHN DALLAS |
| Low Impact Development | Cleared | 9/12/2017 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 9/12/2017 | EDUARDO PEDROZA |
| Flood clearance | Cleared | 2/5/2018 | CHANG LIN |
| Green Code | Cleared | 7/6/2018 | RUSSELL KELLY |
| GPI Written Notices | Cleared | 8/27/2018 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 8/27/2018 | NILOOFAR MEHRAIN |
| Private sewage disp. approval | Cleared | 8/27/2018 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bedassian, Norik; Lic. No.: C53083 | 16540 SULTUS ST SANTA CLARITA, CA 91387 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 8/5/2019 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 8/5/2019 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 8/20/2019 | Not Ready for Inspection | PETER FOLLING |
| FLOOD-Elevation Certificate | 8/20/2019 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 8/20/2019 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 8/27/2019 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 8/27/2019 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 8/29/2019 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 9/3/2019 | No Access for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2019 | Partial Approval | PETER FOLLING |
| Interior/Exterior Lathing | 12/24/2019 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 7/31/2020 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 7/31/2020 | Partial Approval | DAVID STEPANYAN |
| HVAC-Rough | 9/21/2020 | Corrections Issued | DAVID STEPANYAN |
| Underground Mechanical | 9/29/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 10/14/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 2/1/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 2/1/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 4/19/2021 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 4/19/2021 | Approved | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 4/19/2021 | Approved | DAVID STEPANYAN |
| Insulation | 4/28/2021 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 5/19/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 9/27/2021 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 9/6/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Final | 9/6/2022 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Final | 9/6/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 9/15/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 9/15/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | CHRIS CHRISTENSEN |
| FLOOD-Proofing Certificate | 11/14/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 11/14/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 11/14/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 11/14/2022 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/14/2022 | Approved | CHRIS CHRISTENSEN |