11341 W MIRANDA ST 91601

Certificate Information: 11341 W MIRANDA ST 91601

Application / Permit
16010-20000-04033
Plan Check / Job No.
B16VN12375
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single family dwelling with attached garage. (Parcel 3)
Permit Issued
Issued on 11/27/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2016 APPLICANT
Green Plans Picked Up 9/27/2016 APPLICANT
Assigned to Plan Check Engineer 9/29/2016 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/3/2016 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/6/2016 TIEN JEN WANG
Building Plans Picked Up 10/6/2016 APPLICANT
Applicant returned to address corrections 5/10/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/18/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/2/2017 DOUGLAS NAKATANI
Applicant returned to address corrections 10/19/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/2/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/13/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/26/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/25/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/31/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/30/2018 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/3/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 9/18/2019 KAMRAN GHOTBI RAVANDI
Issued 11/27/2019 LADBS
CofO in Progress 2/13/2024 HENRY KIM
Permit Finaled 2/13/2024 JOHN JANSON
CofO Issued 2/13/2024 JOHN JANSON
Permit Finaled 2/13/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/13/2016 YESENIA DIAZ
Address approval Cleared 10/17/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 10/18/2016 JOHN DALLAS
Project located in CRA area Cleared 11/18/2016 JIM URQUHART
Tract Map conditions Cleared 4/12/2017 JOHN DACEY
Green Code Cleared 10/23/2017 DAVID MATSON
Low Impact Development Cleared 10/31/2017 RYAN HUDSON
Sewer availability Cleared 6/25/2019 JULIUS GARCIA
Miscellaneous Cleared 9/3/2019 JULIUS GARCIA
Permit Cleared 9/3/2019 JULIUS GARCIA
Roof/Waste drainage to street Cleared 9/3/2019 JULIUS GARCIA

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B 345 W LORAINE ST #3      GLENDALE, CA 91202
Engineer Nguyen, Lam Thanh; Lic. No.: C36957 12277 BAJA PANORAMA      SANTA ANA, CA 92705

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 2/14/2020 Partial Approval JOSEPH SAGEN
Underground Mechanical 2/14/2020 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 3/12/2020 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 3/17/2020 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 3/18/2020 Partial Approval JOSEPH SAGEN
Excavation/Setback/Form/Re-Bar 4/3/2020 Approved JOSEPH SAGEN
Footing/Foundation/Slab 4/3/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 7/2/2020 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 8/25/2020 Partial Approval JOSEPH SAGEN
PLUMBING-Rough 11/25/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Not Ready for Inspection DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Partial Approval JOSEPH SAGEN
Shower Pan 3/3/2021 Partial Approval JOSEPH SAGEN
ELECTRICAL-Rough 3/4/2021 Approved JOSEPH SAGEN
HVAC-Rough 3/4/2021 Approved JOSEPH SAGEN
Interior/Exterior Lathing 4/9/2021 Not Ready for Inspection JOSEPH SAGEN
Interior/Exterior Lathing 4/23/2021 Partial Approval JOSEPH SAGEN
BUILDING-Rough-Frame 6/2/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Rough 6/2/2021 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 6/2/2021 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 7/15/2021 Not Ready for Inspection JOSEPH SAGEN
Insulation 7/15/2021 Partial Approval JOSEPH SAGEN
Verify Sprinkler Sign Off 7/15/2021 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 8/26/2022 Approved HENRY KIM
Drywall Nailing 8/26/2022 Approved HENRY KIM
Interior/Exterior Lathing 8/30/2022 Approved HENRY KIM
Shower Pan 8/30/2022 Approved HENRY KIM
ELECTRICAL-Rough 10/26/2022 Not Ready for Inspection HENRY KIM
Underground Mechanical 10/26/2022 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 9/21/2023 Corrections Issued HENRY KIM
HVAC-Final 9/21/2023 Approved HENRY KIM
PLUMBING-Final 9/21/2023 Corrections Issued HENRY KIM
Service/Power Release 9/21/2023 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Approved HENRY KIM
ELECTRICAL-Final 1/31/2024 Approved HENRY KIM
HVAC-Final 1/31/2024 Approved HENRY KIM
PLUMBING-Final 1/31/2024 Approved HENRY KIM
Final 2/12/2024 OK to Issue CofO HENRY KIM
Green Building Final 2/12/2024 Approved HENRY KIM
Smoke Detectors 2/12/2024 Approved HENRY KIM