1657 N GOLDEN GATE AVE 90026

Certificate Information: 1657 N GOLDEN GATE AVE 90026

Application / Permit
16010-20000-03983
Plan Check / Job No.
B16VN12256
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRUCT NEW 2 STORY SFD WITH ATTACHED 2 CAR GARAGE
Permit Issued
Issued on 12/13/2017
Issuing Office
Valley
Current Status
CofO Issued on 1/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2016 APPLICANT
Green Plans Picked Up 10/12/2016 APPLICANT
Assigned to Plan Check Engineer 10/20/2016 VU NGUYEN
Corrections Issued 10/31/2016 VU NGUYEN
Quality Review Completed 11/1/2016 ARMEN SARKISIAN
Building Plans Picked Up 11/7/2016 APPLICANT
Plan Check Approved 10/24/2017 VU NGUYEN
Issued 12/13/2017 LADBS
CofO in Progress 12/17/2021 THOMAS LOGRASSO
Permit Finaled 1/8/2022 DEROLD HAUFF
CofO Issued 1/8/2022 DEROLD HAUFF
Permit Finaled 1/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/14/2017 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 3/14/2017 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 3/14/2017 JOHN DALLAS
Permit Cleared 3/14/2017 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/14/2017 MARKOS PEREZ-BRAN
Low Impact Development Cleared 5/1/2017 MATTHEW JIMENEZ
Permit Cleared 10/3/2017 STEVE MELGAR
Roof/Waste drainage to street Cleared 10/3/2017 STEVE MELGAR
Green Code Cleared 10/20/2017 RUSSELL KELLY
Grading Pre-Inspection Cleared 10/24/2017 VU NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Lee, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/26/2018 Not Ready for Inspection DAVID CHAN
Underground Mechanical 5/3/2018 Approved DAVID CHAN
Excavation/Setback/Form/Re-Bar 5/30/2018 Approved DAVID CHAN
Footing/Foundation/Slab 5/30/2018 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 6/4/2018 No Access for Inspection DAVID CHAN
Deputy Steel/Welding 6/26/2018 Conditional Approval CHARLES BOGHOSKHAN
BUILDING-Rough-Frame 6/27/2018 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 7/17/2018 Partial Approval AJA COLLAY
Green Building Rough 7/17/2018 Not Ready for Inspection AJA COLLAY
Verify Sprinkler Sign Off 7/17/2018 Not Ready for Inspection AJA COLLAY
Deputy Wood Construction 7/18/2018 Conditional Approval DAVID CHAN
ELECTRICAL-Rough 10/31/2018 Approved DAVID CHAN
Green Building Rough 10/31/2018 Approved DAVID CHAN
HVAC-Rough 10/31/2018 Approved DAVID CHAN
Verify Sprinkler Sign Off 10/31/2018 Partial Inspection DAVID CHAN
BUILDING-Rough-Frame 11/5/2018 Corrections Issued DAVID CHAN
PLUMBING-Rough 11/5/2018 Approved DAVID CHAN
Insulation 11/16/2018 Approved DAVID CHAN
Drywall Nailing 11/29/2018 Approved DAVID CHAN
Interior/Exterior Lathing 11/29/2018 Approved DAVID CHAN
Interior/Exterior Lathing 12/24/2018 Approved DAVID CHAN
Special/Order Compliance 8/29/2019 Approved ELMER BLAND
Special/Order Compliance 8/30/2019 Partial Approval DAVID CHAN
Special/Order Compliance 9/3/2019 Not Ready for Inspection DAVID CHAN
Special/Order Compliance 9/5/2019 Approved DAVID CHAN
Special/Order Compliance 4/14/2020 Corrections Issued THOMAS LOGRASSO
Special/Order Compliance 6/16/2020 Approved RUBEN SALAS
BUILDING-Rough-Frame 1/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 1/29/2021 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 1/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 1/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 1/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 1/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/22/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 11/22/2021 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 11/22/2021 Approved THOMAS LOGRASSO
Green Building Final 11/22/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 11/22/2021 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 11/22/2021 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 11/22/2021 Corrections Issued THOMAS LOGRASSO
Verify Sprinkler Sign Off 11/22/2021 Approved THOMAS LOGRASSO
Final 12/7/2021 Corrections Issued THOMAS LOGRASSO
Green Building Final 12/7/2021 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 12/7/2021 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 12/7/2021 Not Ready for Inspection THOMAS LOGRASSO
Final 12/16/2021 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 12/16/2021 Approved THOMAS LOGRASSO
Service/Power Release 12/16/2021 Approved THOMAS LOGRASSO
Smoke Detectors 12/16/2021 Approved THOMAS LOGRASSO