1657 N GOLDEN GATE AVE 90026
Certificate Information: 1657 N GOLDEN GATE AVE 90026
- Application / Permit
- 16010-20000-03983
- Plan Check / Job No.
- B16VN12256
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONSTRUCT NEW 2 STORY SFD WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 12/13/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2016 | APPLICANT |
| Green Plans Picked Up | 10/12/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2016 | VU NGUYEN |
| Corrections Issued | 10/31/2016 | VU NGUYEN |
| Quality Review Completed | 11/1/2016 | ARMEN SARKISIAN |
| Building Plans Picked Up | 11/7/2016 | APPLICANT |
| Plan Check Approved | 10/24/2017 | VU NGUYEN |
| Issued | 12/13/2017 | LADBS |
| CofO in Progress | 12/17/2021 | THOMAS LOGRASSO |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
| CofO Issued | 1/8/2022 | DEROLD HAUFF |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2017 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2017 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 3/14/2017 | JOHN DALLAS |
| Permit | Cleared | 3/14/2017 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 3/14/2017 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 5/1/2017 | MATTHEW JIMENEZ |
| Permit | Cleared | 10/3/2017 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/3/2017 | STEVE MELGAR |
| Green Code | Cleared | 10/20/2017 | RUSSELL KELLY |
| Grading Pre-Inspection | Cleared | 10/24/2017 | VU NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Lee, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/26/2018 | Not Ready for Inspection | DAVID CHAN |
| Underground Mechanical | 5/3/2018 | Approved | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 5/30/2018 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 5/30/2018 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 6/4/2018 | No Access for Inspection | DAVID CHAN |
| Deputy Steel/Welding | 6/26/2018 | Conditional Approval | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 6/27/2018 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 7/17/2018 | Partial Approval | AJA COLLAY |
| Green Building Rough | 7/17/2018 | Not Ready for Inspection | AJA COLLAY |
| Verify Sprinkler Sign Off | 7/17/2018 | Not Ready for Inspection | AJA COLLAY |
| Deputy Wood Construction | 7/18/2018 | Conditional Approval | DAVID CHAN |
| ELECTRICAL-Rough | 10/31/2018 | Approved | DAVID CHAN |
| Green Building Rough | 10/31/2018 | Approved | DAVID CHAN |
| HVAC-Rough | 10/31/2018 | Approved | DAVID CHAN |
| Verify Sprinkler Sign Off | 10/31/2018 | Partial Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 11/5/2018 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 11/5/2018 | Approved | DAVID CHAN |
| Insulation | 11/16/2018 | Approved | DAVID CHAN |
| Drywall Nailing | 11/29/2018 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/29/2018 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 12/24/2018 | Approved | DAVID CHAN |
| Special/Order Compliance | 8/29/2019 | Approved | ELMER BLAND |
| Special/Order Compliance | 8/30/2019 | Partial Approval | DAVID CHAN |
| Special/Order Compliance | 9/3/2019 | Not Ready for Inspection | DAVID CHAN |
| Special/Order Compliance | 9/5/2019 | Approved | DAVID CHAN |
| Special/Order Compliance | 4/14/2020 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 6/16/2020 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 1/29/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 1/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 1/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 1/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 1/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/22/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 11/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/22/2021 | Approved | THOMAS LOGRASSO |
| Green Building Final | 11/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 11/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 11/22/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 11/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 11/22/2021 | Approved | THOMAS LOGRASSO |
| Final | 12/7/2021 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 12/7/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 12/7/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 12/7/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 12/16/2021 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 12/16/2021 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/16/2021 | Approved | THOMAS LOGRASSO |