2311 N VASANTA WAY 90068

Certificate Information: 2311 N VASANTA WAY 90068

Application / Permit
16010-20000-03877
Plan Check / Job No.
B16VN11857
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY W/ ATTACHED 2-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 10/12/2017
Issuing Office
Metro
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2016 APPLICANT
Green Plans Picked Up 9/19/2016 APPLICANT
Assigned to Plan Check Engineer 9/22/2016 NILOOFAR MEHRAIN
Corrections Issued 9/27/2016 NILOOFAR MEHRAIN
Quality Review Completed 9/28/2016 GUANG MIN TUNG
Building Plans Picked Up 9/29/2016 APPLICANT
Applicant returned to address corrections 1/23/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/22/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/26/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/9/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/10/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/11/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/25/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/6/2017 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/15/2017 NILOOFAR MEHRAIN
Plan Check Approved 9/29/2017 NILOOFAR MEHRAIN
Issued 10/12/2017 LADBS
CofO in Progress 10/4/2022 JOAQUIN GREENOUGH
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/7/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 11/7/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 11/7/2016 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 11/17/2016 ROCHELLE DUNGCA
Hydrant and Access approval Cleared 11/17/2016 ROBERT DUFF
Permit Cleared 11/17/2016 ROCHELLE DUNGCA
Sewer availability Cleared 11/17/2016 ROCHELLE DUNGCA
Green Code Cleared 1/23/2017 ROLLIN GETTLE III
GPI Written Notices Cleared 5/9/2017 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 5/9/2017 NILOOFAR MEHRAIN
BHO/Hillside ordinance Cleared 6/22/2017 ROCHELLE DUNGCA
Disturb/Remove Protected Trees Cleared 6/26/2017 LUIS TORRES
Low Impact Development Cleared 9/8/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/12/2017 MARKOS PEREZ-BRAN
Excavation more than 5-ft deep Cleared 9/15/2017 CALOSHA APPROVED

Contact Information

Engineer Watry, Stephen Matthew; Lic. No.: GE2238 820 IDYLBERRY RD      SAN RAFAEL, CA 94903
Engineer Yaghi, Shucri Ibrahim; Lic. No.: C43205 112 E CHAPMAN AVE STE D      ORANGE, CA 92866
Geologist Watry, Stephen Matthew; Lic. No.: EG1260 820 IDYLBERRY ROAD      SAN RAFAEL, CA 94903

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2017 Approved LUIS BARRALES
Special/Order Compliance 12/12/2017 Conditional Approval TIMOTHY O CONNER
Deputy Shotcrete 9/13/2018 Approved LUIS BARRALES
Footing/Foundation/Slab 2/11/2019 Partial Approval RONALD COWAN
PLUMBING-Rough 2/11/2019 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 2/12/2019 Approved RONALD COWAN
Piling/Pier/Caisson 3/12/2019 No Access for Inspection RONALD COWAN
Structural Steel Frame 3/12/2019 No Access for Inspection RONALD COWAN
Footing/Foundation/Slab 4/2/2019 Partial Approval RONALD COWAN
Footing/Foundation/Slab 5/1/2019 Partial Approval DANNY TOLENTINO
Deputy Drilled-In Anchors 5/7/2019 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 5/7/2019 Not Ready for Inspection BRIAN SULLIVAN
Piling/Pier/Caisson 5/7/2019 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 6/3/2019 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 8/22/2019 Not Ready for Inspection ROBERT CORNELL
Footing/Foundation/Slab 8/28/2019 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 8/28/2019 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/29/2019 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 8/29/2019 Corrections Issued ROBERT CORNELL
Deputy Reinf. Concrete 9/3/2019 Conditional Approval ROBERT CORNELL
Masonry Wall/Backfill 9/16/2019 Corrections Issued ROBERT CORNELL
Footing/Foundation/Slab 10/8/2019 Partial Approval ROBERT CORNELL
Pre-Inspection 10/8/2019 Partial Approval ROBERT CORNELL
Footing/Foundation/Slab 11/6/2019 Partial Approval ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 11/26/2019 Partial Approval ROBERT CORNELL
Green Building Rough 11/26/2019 Not Ready for Inspection ROBERT CORNELL
Verify Sprinkler Sign Off 11/26/2019 Not Ready for Inspection ROBERT CORNELL
Pre-Inspection 12/23/2019 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 1/14/2020 Not Ready for Inspection ROBERT CORNELL
PLUMBING-Rough 1/14/2020 Corrections Issued ROBERT CORNELL
Verify Sprinkler Sign Off 1/14/2020 Not Ready for Inspection ROBERT CORNELL
ELECTRICAL-Rough 1/22/2020 Approved ROBERT CORNELL
HVAC-Rough 3/2/2020 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 4/2/2020 Approved ROBERT CORNELL
Wood Frame 4/2/2020 Corrections Issued ROBERT CORNELL
Special/Order Compliance 5/6/2020 Approved BRIAN SULLIVAN
Pre-Inspection 1/27/2021 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 2/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Insulation 6/1/2021 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 6/1/2021 Partial Approval BRIAN SULLIVAN
Grounding or Bonding 7/16/2021 Not Ready for Inspection JOSEPH MCGARRY
Drywall Nailing 8/23/2021 Partial Inspection SCOTT FINNILA
Pre-Inspection 8/23/2021 Partial Inspection SCOTT FINNILA
Drywall Nailing 9/9/2021 Partial Approval BRIAN SULLIVAN
Green Building Rough 9/9/2021 Approved BRIAN SULLIVAN
Drywall Nailing 9/20/2021 Partial Approval ROBERT VORHIS
Shower Pan 9/29/2021 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Partial Inspection DANIEL GONZALEZ
Interior/Exterior Lathing 10/8/2021 Partial Approval DANIEL GONZALEZ
Wood Frame 3/23/2022 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Final 4/26/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 4/26/2022 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 6/1/2022 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 6/22/2022 Corrections Issued STUART CHAPMAN
Gas Test 6/22/2022 Approved STUART CHAPMAN
HVAC-Final 6/22/2022 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/7/2022 Approved BRIAN SULLIVAN
Drywall Nailing 7/7/2022 Approved BRIAN SULLIVAN
Final 7/7/2022 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 7/7/2022 Approved BRIAN SULLIVAN
Green Building Final 7/7/2022 Approved BRIAN SULLIVAN
Service/Power Release 7/7/2022 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 7/7/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/7/2022 Approved BRIAN SULLIVAN
Service/Power Release 7/18/2022 Approved RYAN SALAZAR
Service/Power Release 8/2/2022 Not Ready for Inspection RYAN SALAZAR
Final 8/15/2022 Corrections Issued BRIAN SULLIVAN
Final 8/25/2022 Corrections Issued BRIAN SULLIVAN
Gas Test 8/25/2022 Approved BRIAN SULLIVAN
Final 9/13/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Final 9/23/2022 Approved BRIAN SULLIVAN
Final 9/23/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 9/23/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 9/23/2022 Approved BRIAN SULLIVAN
Final 9/28/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 10/3/2022 OK to Issue CofO JOAQUIN GREENOUGH