1055 N STRADELLA ROAD 90077

Certificate Information: 1055 N STRADELLA ROAD 90077

Application / Permit
16010-20000-03806
Plan Check / Job No.
B16VN11587
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 2-STORY SFD W/ ROOF DECK, BASEMENT (GARAGE & HABITABLE ROOMS) AND ATTACHED RAISED SWIMMING POOL W/ SPA (UNDER SEPARATE PERMIT). NEW SPA OVER 2ND FLR DECK. SEE COMMENTS.
Permit Issued
Issued on 7/5/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2016 APPLICANT
Green Plans Picked Up 10/5/2016 APPLICANT
Assigned to Plan Check Engineer 10/6/2016 HAYATO TSUCHIYA
Corrections Issued 11/1/2016 HAYATO TSUCHIYA
Quality Review Completed 11/3/2016 GUANG MIN TUNG
Building Plans Picked Up 11/17/2016 APPLICANT
Applicant returned to address corrections 9/22/2017 HAYATO TSUCHIYA
Applicant returned to address corrections 9/26/2017 HAYATO TSUCHIYA
Applicant returned to address corrections 9/29/2017 HAYATO TSUCHIYA
Applicant returned to address corrections 10/6/2017 HAYATO TSUCHIYA
Plan Check Approved 5/24/2018 HAYATO TSUCHIYA
Issued 7/5/2018 LADBS
CofO in Progress 5/20/2023 CHRISTOPHER WILSON
CofO in Progress 5/20/2023 CHRISTOPHER WILSON
Permit Finaled 5/24/2023 DANIEL ORRANTE
CofO Issued 5/24/2023 DANIEL ORRANTE
Permit Finaled 5/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/8/2017 ARMENIA AGUILAR
BHO/Hillside ordinance Cleared 3/8/2017 ARMENIA AGUILAR
Permit Cleared 3/8/2017 ARMENIA AGUILAR
GPI Written Notices Cleared 7/5/2017 HAYATO TSUCHIYA
Grading Pre-Inspection Cleared 7/5/2017 HAYATO TSUCHIYA
Frnt yard landscape/Water mgmt Cleared 7/24/2017 NOAH MCCOY
Low Impact Development Cleared 9/22/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/12/2017 ALFREDO JARA
BHO/Hillside ordinance Cleared 10/13/2017 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 11/1/2017 ROBERT DUFF
Green Code Cleared 11/8/2017 ROLLIN GETTLE III
Eng Process Fee Ord 176,300 Cleared 3/30/2018 STEVEN JIN
Miscellaneous Cleared 3/30/2018 STEVEN JIN
Sewer availability Cleared 3/30/2018 STEVEN JIN
Work Adjacent to Public Way Cleared 5/1/2018 BOK GOH

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/8/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/27/2018 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 11/28/2018 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/4/2018 Approved DANIEL ORRANTE
Deputy Reinf. Concrete 12/5/2018 Conditional Approval JOEL LAUNCHBAUGH
Excavation/Setback/Form/Re-Bar 12/18/2018 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 12/26/2018 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 12/27/2018 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 1/3/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 1/4/2019 Conditional Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 2/1/2019 Partial Inspection MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 4/15/2019 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/6/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/6/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/6/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/7/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/7/2019 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 5/20/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 5/22/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 5/23/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/23/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Shotcrete 5/24/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/24/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/14/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/14/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/17/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/26/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/26/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/26/2019 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 7/1/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/5/2019 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 7/10/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 7/11/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/11/2019 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 7/12/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/22/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/22/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/23/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/25/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/30/2019 Partial Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 7/31/2019 Partial Approval MICHAEL TEMPLE
Deputy Reinf. Concrete 8/1/2019 Conditional Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 8/13/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/11/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 9/30/2019 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/4/2019 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/7/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/8/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/10/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 10/28/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Steel/Welding 11/5/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/15/2019 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/15/2019 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/9/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/21/2020 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 2/7/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/11/2020 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 2/27/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/6/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/17/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/18/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/9/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/21/2020 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/4/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/8/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/12/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 6/19/2020 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/2/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/4/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/10/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/11/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 8/11/2020 Conditional Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 8/24/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/25/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/31/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/4/2020 Conditional Approval MATT KELLERMAN
Piling/Pier/Caisson 9/4/2020 Conditional Approval MATT KELLERMAN
Wood Frame 11/12/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/24/2020 Partial Approval MATT KELLERMAN
PLUMBING-Rough 12/11/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/19/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/5/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/8/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/22/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/24/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 4/15/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 4/15/2021 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 5/10/2021 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/12/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/12/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/20/2021 Corrections Issued CHRISTOPHER WILSON
Insulation 5/20/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/25/2021 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/28/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 7/6/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 7/6/2021 Partial Inspection AMY COLIN
ELECTRICAL-Rough 7/16/2021 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 7/22/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 7/26/2021 Approved CHRISTOPHER WILSON
PLUMBING-Rough 7/26/2021 Approved CHRISTOPHER WILSON
HVAC-Rough 8/10/2021 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/16/2021 Approved CHRISTOPHER WILSON
Green Building Rough 8/16/2021 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 8/16/2021 Approved CHRISTOPHER WILSON
Insulation 8/20/2021 Partial Approval CHRISTOPHER WILSON
Final 8/25/2021 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 8/25/2021 Partial Approval CHRISTOPHER WILSON
Insulation 9/29/2021 Approved JAVIER RAMOS JR
Pre-Inspection 9/29/2021 Partial Inspection RICHARD STEINBACH
Interior/Exterior Lathing 10/8/2021 Partial Approval RYAN SALAZAR
PLUMBING-Rough 10/21/2021 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/19/2021 Partial Approval BRENDAN LOONEY
Drywall Nailing 1/21/2022 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 1/21/2022 Not Ready for Inspection DEANDRE HOFFMAN
Shower Pan 1/21/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 1/28/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 1/28/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 2/7/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/7/2022 Partial Approval CHRISTOPHER WILSON
Shower Pan 2/7/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 3/29/2022 Approved CHRISTOPHER WILSON
Special/Order Compliance 4/20/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 6/6/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/6/2022 Corrections Issued CHRISTOPHER WILSON
Gas Test 7/15/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 7/19/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/22/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/22/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 9/23/2022 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 9/23/2022 Partial Approval CHRISTOPHER WILSON
Service/Power Release 10/14/2022 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 10/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Service/Power Release 11/3/2022 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/27/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/4/2023 Approved CHRISTOPHER WILSON
PLUMBING-Final 3/2/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 3/6/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 3/10/2023 Approved CHRISTOPHER WILSON
PLUMBING-Final 3/10/2023 Approved CHRISTOPHER WILSON
HVAC-Final 3/14/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Final 3/22/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 5/1/2023 Approved CHRISTOPHER WILSON
Final 5/1/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 5/1/2023 Approved CHRISTOPHER WILSON
Green Building Final 5/1/2023 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 5/1/2023 Approved CHRISTOPHER WILSON
Final 5/18/2023 OK to Issue CofO CHRISTOPHER WILSON