129 S ROCKINGHAM AVE 90049

Certificate Information: 129 S ROCKINGHAM AVE 90049

Application / Permit
16010-20000-03524
Plan Check / Job No.
B16VN10857
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2 story sfd with basement and attached garage. Attached deck and front porch.
Permit Issued
Issued on 9/20/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2016 APPLICANT
Assigned to Plan Check Engineer 9/22/2016 RODNEY SAMIIAN
Corrections Issued 10/4/2016 RODNEY SAMIIAN
Quality Review Completed 10/4/2016 GUANG MIN TUNG
Building Plans Picked Up 10/5/2016 APPLICANT
Green Plans Picked Up 10/5/2016 APPLICANT
Applicant returned to address corrections 10/30/2017 RODNEY SAMIIAN
Applicant returned to address corrections 1/26/2018 RODNEY SAMIIAN
Applicant returned to address corrections 2/8/2018 RODNEY SAMIIAN
Applicant returned to address corrections 6/12/2018 RODNEY SAMIIAN
Applicant returned to address corrections 6/27/2018 RODNEY SAMIIAN
Applicant returned to address corrections 7/12/2018 RODNEY SAMIIAN
Plan Check Approved 8/7/2018 RODNEY SAMIIAN
Issued 9/20/2018 LADBS
CofO in Progress 12/9/2022 DAVID FEILER
Permit Finaled 1/18/2023 DANIEL ORRANTE
CofO Issued 1/18/2023 DANIEL ORRANTE
Permit Finaled 1/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 6/4/2018 DIANA JIMENEZ
Eng Process Fee Ord 176,300 Cleared 6/4/2018 STEVE MELGAR
Highway dedication Cleared 6/4/2018 STEVE MELGAR
Hydrant and Access approval Cleared 6/4/2018 JOHN CONNEALLY
Permit Cleared 6/4/2018 STEVE MELGAR
Sewer availability Cleared 6/4/2018 STEVE MELGAR
Green Code Cleared 6/27/2018 MICHAEL AYERS
Low Impact Development Cleared 8/3/2018 SAM NAVID
Excavation more than 5-ft deep Cleared 8/7/2018 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 8/7/2018 STEVEN JIN

Contact Information

Contractor Gaia Construction Inc; Lic. No.: 912485-B 2800 GLENDON AVENUE      LOS ANGELES, CA 90064
Engineer Almalla, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Tsai, Wan-Lain; Lic. No.: GE2121 3831 ARDEN DR      EL MONTE, CA 91731

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/1/2019 Partial Inspection KENNETH NAGLE
PLUMBING-Rough 4/2/2019 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 4/5/2019 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 5/13/2019 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 5/31/2019 Corrections Issued TIM CHRISTENSEN
ELECTRICAL-Rough 6/6/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 6/6/2019 Partial Approval RICHARD STEINBACH
Deputy Shotcrete 6/13/2019 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 6/14/2019 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 6/24/2019 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 6/25/2019 Conditional Approval MICHAEL TEMPLE
Deputy Shotcrete 6/26/2019 Conditional Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 9/5/2019 Partial Inspection TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 9/9/2019 Corrections Issued TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 9/13/2019 Partial Approval TIM CHRISTENSEN
Deputy Reinf. Concrete 9/17/2019 Conditional Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 11/12/2019 Corrections Issued TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/15/2019 Corrections Issued TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/19/2019 Conditional Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/2/2019 Partial Approval TIM CHRISTENSEN
Wood Frame 12/2/2019 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 12/10/2019 Corrections Issued TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 12/11/2019 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/2/2020 Conditional Approval DANNY TOLENTINO
Green Building Rough 1/2/2020 Not Ready for Inspection DANNY TOLENTINO
Verify Sprinkler Sign Off 1/2/2020 Not Ready for Inspection DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 1/7/2020 Partial Approval TIM CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/14/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 1/17/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 1/28/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 2/28/2020 Partial Approval DANNY TOLENTINO
Deputy Shotcrete 3/13/2020 Corrections Issued ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval DANNY TOLENTINO
BUILDING-Rough-Frame 5/1/2020 Partial Inspection DANNY TOLENTINO
Green Building Rough 5/1/2020 Not Ready for Inspection DANNY TOLENTINO
Verify Sprinkler Sign Off 5/1/2020 Not Ready for Inspection DANNY TOLENTINO
ELECTRICAL-Rough 6/12/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 7/14/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 7/15/2020 Partial Inspection JOHN KIDWELL
Gas Test 8/5/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 8/5/2020 Partial Approval JOHN KIDWELL
Sewer 8/5/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 8/18/2020 Not Ready for Inspection ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 9/14/2020 Corrections Issued ANTHONY MCDOWALL
Drywall Nailing 9/22/2020 Partial Approval JOHN KIDWELL
Green Building Rough 9/22/2020 Partial Approval JOHN KIDWELL
HVAC-Rough 10/6/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 10/8/2020 Approved JOHN KIDWELL
ELECTRICAL-Rough 10/9/2020 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/15/2020 Partial Approval JOHN KIDWELL
Green Building Rough 10/15/2020 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 10/15/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 11/4/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 11/13/2020 No Access for Inspection JOHN KIDWELL
HVAC-Rough 11/17/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 11/18/2020 Approved JOHN KIDWELL
BUILDING-Rough-Frame 11/20/2020 Approved MICHAEL PELHAM
Deputy Wood Construction 11/20/2020 Conditional Approval MICHAEL PELHAM
Green Building Rough 11/20/2020 Approved MICHAEL PELHAM
HVAC-Rough 11/20/2020 Approved MICHAEL PELHAM
Verify Sprinkler Sign Off 11/20/2020 Approved MICHAEL PELHAM
Drywall Nailing 12/10/2020 Approved DAVID HEINE
Insulation 12/10/2020 Approved DAVID HEINE
Interior/Exterior Lathing 12/14/2020 Partial Approval JOHN KIDWELL
Shower Pan 2/9/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/8/2021 Partial Approval JOHN KIDWELL
Sewer 3/26/2021 Approved JOHN KIDWELL
Sewer 4/7/2021 Approved PIERRE VEGA
Footing/Foundation/Slab 4/16/2021 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 6/16/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 6/22/2021 No Access for Inspection JOHN KIDWELL
PLUMBING-Rough 6/22/2021 No Access for Inspection JOHN KIDWELL
ELECTRICAL-Rough 6/29/2021 Partial Approval JOHN KIDWELL
Gas Test 6/29/2021 Partial Approval JOHN KIDWELL
Sewer 7/9/2021 Partial Approval JACK MATTILLO
Sewer 7/12/2021 Partial Inspection JOHN KIDWELL
ELECTRICAL-Rough 8/18/2021 Partial Inspection JUAN VALENZUELA
Sewer 8/18/2021 Partial Approval JUAN VALENZUELA
Sewer 9/7/2021 Partial Approval JESUS RODRIGUEZ
Underground Mechanical 9/7/2021 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 9/8/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 9/8/2021 Corrections Issued CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 9/13/2021 Partial Approval JUAN VALENZUELA
Underground Mechanical 9/13/2021 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 9/16/2021 Conditional Approval JESUS RODRIGUEZ
Underground Mechanical 9/16/2021 Conditional Approval JESUS RODRIGUEZ
Gas Test 10/7/2021 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 10/7/2021 Not Ready for Inspection JOHN KIDWELL
Gas Test 10/12/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 10/12/2021 Partial Approval JOHN KIDWELL
Gas Test 11/3/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 11/4/2021 Conditional Approval JOHN KIDWELL
ELECTRICAL-Final 1/27/2022 Corrections Issued JUAN VALENZUELA
Gas Test 3/15/2022 Approved JOHN KIDWELL
Pre-Inspection 3/31/2022 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Final 4/7/2022 Approved JOHN KIDWELL
HVAC-Final 4/11/2022 No Access for Inspection JOHN KIDWELL
HVAC-Final 4/12/2022 Approved JOHN KIDWELL
PLUMBING-Final 5/18/2022 Approved JOHN KIDWELL
Green Building Final 8/26/2022 Corrections Issued ANDREW NAVE
Verify Rec and Parks Fee Memo 8/26/2022 Approved ANDREW NAVE
Final 11/28/2022 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 11/28/2022 Approved KEVIN SARGSYAN
Green Building Final 11/28/2022 Approved KEVIN SARGSYAN
Reinforced Concrete Frame 11/28/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Not Ready KEVIN SARGSYAN
Service/Power Release 11/28/2022 Approved KEVIN SARGSYAN
Smoke Detectors 11/28/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 12/6/2022 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 12/6/2022 Not Ready for Inspection DAVID FEILER
Final 12/9/2022 OK to Issue CofO DAVID FEILER
Smoke Detectors 12/9/2022 Approved DAVID FEILER