5617 N STROHM AVE Unit #11 91601
Certificate Information: 5617 N STROHM AVE Unit #11 91601
- Application / Permit
- 16010-20000-03438
- Plan Check / Job No.
- B16VN10602
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (35) Condo-Single Family
- Work Description
- Propose type-V construction NFPA13-D sprinkler throughout IRR shape 20'2" x 38.5' 3-story SFD with attached garage (building type A) Per small lot subdivision pursuant to Tentative Tract Map No. 73907-SL. A certification of occupancy (temporary or final) shall not be issued until after the final map has been recorded.
- Permit Issued
- Issued on 11/29/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/28/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2016 | ALDOUS CHIC |
| Corrections Issued | 9/6/2016 | ALDOUS CHIC |
| Quality Review Completed | 9/9/2016 | GUANG MIN TUNG |
| Building Plans Picked Up | 9/16/2016 | APPLICANT |
| Applicant returned to address corrections | 4/21/2017 | ALDOUS CHIC |
| Applicant returned to address corrections | 8/3/2017 | ALDOUS CHIC |
| Applicant returned to address corrections | 10/20/2017 | ALDOUS CHIC |
| Applicant returned to address corrections | 1/18/2018 | ALDOUS CHIC |
| Applicant returned to address corrections | 6/26/2018 | ALDOUS CHIC |
| Plan Check Approved | 11/26/2018 | ALDOUS CHIC |
| Issued | 11/29/2018 | LADBS |
| CofO in Progress | 8/28/2020 | JOSEPH SAGEN |
| Permit Finaled | 8/28/2020 | DONALD SUNSERI |
| CofO Issued | 8/28/2020 | DONALD SUNSERI |
| Permit Finaled | 8/28/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/8/2016 | JOHN DACEY |
| Tract Map conditions | Cleared | 9/8/2016 | JOHN DACEY |
| Tract Map conditions | Cleared | 9/8/2016 | JOHN DACEY |
| Miscellaneous | Cleared | 9/9/2016 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2016 | RAVIL MANAPOV |
| Disturb/Remove Protected Trees | Cleared | 6/28/2017 | ADRIAN SANCHEZ |
| Fire Marshall Fire Life Safety | Cleared | 10/20/2017 | JOHN DALLAS |
| Hydrant and Access approval | Cleared | 10/20/2017 | JOHN DALLAS |
| Green Code | Cleared | 11/2/2017 | MICHAEL AYERS |
| Address approval | Cleared | 5/21/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 7/30/2018 | EDUARDO PEDROZA |
| Highway dedication | Cleared | 8/7/2018 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 8/7/2018 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/7/2018 | LEE GUILBEAUX |
Contact Information
| Architect | Holtz, Donald Lee; Lic. No.: C21677 | 2404 WILSHIRE BLVD SUITE 6F LOS ANGELES, CA 90057 |
| Architect | Sant, Architects Inc; Lic. No.: BUS3657 | 1613 ABBOT KINNEY BLVD VENICE, CA 90291 |
| Contractor | D B Builders Inc; Lic. No.: 812896-B | 9748 TOPANGA CANYON BLVD CHATSWORTH, CA 91311 |
| Engineer | Nguyen, Lam Thanh; Lic. No.: C36957 | 12277 BAJA PANORAMA SANTA ANA, CA 92705 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/8/2019 | Approved | JOHN KIDWELL |
| Underground Mechanical | 2/8/2019 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/26/2019 | Not Ready for Inspection | DONALD SUNSERI |
| Footing/Foundation/Slab | 2/28/2019 | Partial Approval | DONALD SUNSERI |
| Footing/Foundation/Slab | 4/9/2019 | Approved | DONALD SUNSERI |
| Drywall Nailing | 5/7/2019 | Partial Approval | DONALD SUNSERI |
| Deputy Steel/Welding | 5/21/2019 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2019 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2019 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2019 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2019 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2019 | Partial Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Rough | 10/22/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Rough | 10/24/2019 | Partial Inspection | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2019 | Partial Approval | JOSEPH SAGEN |
| ELECTRICAL-Rough | 11/12/2019 | Approved | JOSEPH SAGEN |
| HVAC-Rough | 11/12/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Rough | 11/12/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Rough | 11/15/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| PLUMBING-Rough | 11/15/2019 | Approved | JOSEPH SAGEN |
| HVAC-Rough | 11/22/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Rough | 12/2/2019 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2019 | Partial Approval | JOSEPH SAGEN |
| Green Building Rough | 12/5/2019 | Not Ready for Inspection | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 12/5/2019 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2019 | Not Ready for Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 1/6/2020 | Approved | JOSEPH SAGEN |
| Green Building Rough | 1/6/2020 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 1/14/2020 | Approved | JOSEPH SAGEN |
| Shower Pan | 1/14/2020 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 1/22/2020 | Partial Approval | JOSEPH SAGEN |
| Interior/Exterior Lathing | 1/29/2020 | Approved | JOSEPH SAGEN |
| Gas Test | 3/3/2020 | Approved | JOSEPH SAGEN |
| Underground Mechanical | 3/27/2020 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2020 | SGSOV Approved | JOSEPH SAGEN |
| Service/Power Release | 6/11/2020 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 7/23/2020 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Final | 7/31/2020 | Approved | JOSEPH SAGEN |
| Final | 8/27/2020 | OK to Issue CofO | JOSEPH SAGEN |
| Green Building Final | 8/27/2020 | Approved | JOSEPH SAGEN |
| HVAC-Final | 8/27/2020 | Approved | JOSEPH SAGEN |
| Smoke Detectors | 8/27/2020 | Approved | JOSEPH SAGEN |