Sewer
|
1/30/2019
|
Approved
|
JOHN KIDWELL
|
|
Underground Mechanical
|
1/30/2019
|
Partial Approval
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
2/20/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Footing/Foundation/Slab
|
4/9/2019
|
Approved
|
DONALD SUNSERI
|
|
Deputy Reinf. Concrete
|
4/11/2019
|
Approved
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/6/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/28/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/10/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/14/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/19/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/18/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/1/2019
|
Partial Approval
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/13/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2019
|
Partial Approval
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/5/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
HVAC-Rough
|
10/10/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/16/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/7/2019
|
Partial Approval
|
JOSEPH SAGEN
|
|
ELECTRICAL-Rough
|
11/12/2019
|
Approved
|
JOSEPH SAGEN
|
|
HVAC-Rough
|
11/12/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
PLUMBING-Rough
|
11/12/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
HVAC-Rough
|
11/15/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
PLUMBING-Rough
|
11/15/2019
|
Approved
|
JOSEPH SAGEN
|
|
HVAC-Rough
|
11/22/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
PLUMBING-Rough
|
11/22/2019
|
Approved
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/2/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
HVAC-Rough
|
12/2/2019
|
Approved
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/5/2019
|
Partial Approval
|
JOSEPH SAGEN
|
|
Green Building Rough
|
12/5/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Verify Sprinkler Sign Off
|
12/5/2019
|
Approved
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/20/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/3/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
BUILDING-Rough-Frame
|
1/6/2020
|
Approved
|
JOSEPH SAGEN
|
|
Green Building Rough
|
1/6/2020
|
Approved
|
JOSEPH SAGEN
|
|
Drywall Nailing
|
1/14/2020
|
Approved
|
JOSEPH SAGEN
|
|
Shower Pan
|
1/14/2020
|
Approved
|
JOSEPH SAGEN
|
|
Interior/Exterior Lathing
|
1/22/2020
|
Partial Approval
|
JOSEPH SAGEN
|
|
Interior/Exterior Lathing
|
1/29/2020
|
Approved
|
JOSEPH SAGEN
|
|
Gas Test
|
3/3/2020
|
Approved
|
JOSEPH SAGEN
|
|
Underground Mechanical
|
5/11/2020
|
Partial Approval
|
JOSEPH SAGEN
|
|
Service/Power Release
|
5/20/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
SGSOV-Seismic Gas S/O Valve
|
6/11/2020
|
SGSOV Approved
|
JOSEPH SAGEN
|
|
Service/Power Release
|
6/11/2020
|
Approved
|
JOSEPH SAGEN
|
|
ELECTRICAL-Final
|
7/16/2020
|
Approved
|
JOSEPH SAGEN
|
|
HVAC-Final
|
7/16/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
PLUMBING-Final
|
7/16/2020
|
Approved
|
JOSEPH SAGEN
|
|
Final
|
8/25/2020
|
OK to Issue CofO
|
JOSEPH SAGEN
|
|
Green Building Final
|
8/25/2020
|
Approved
|
JOSEPH SAGEN
|
|
HVAC-Final
|
8/25/2020
|
Approved
|
JOSEPH SAGEN
|
|
Smoke Detectors
|
8/25/2020
|
Approved
|
JOSEPH SAGEN
|
|
Structural Steel Frame
|
8/25/2020
|
Approved
|
JOSEPH SAGEN
|