734 E INDIANA AVE 90291

Certificate Information: 734 E INDIANA AVE 90291

Application / Permit
16010-20000-03184
Plan Check / Job No.
B16VN09744
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED 6-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 7/10/2017
Issuing Office
Valley
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2016 APPLICANT
Green Plans Picked Up 8/2/2016 APPLICANT
Assigned to Plan Check Engineer 8/18/2016 NILOOFAR MEHRAIN
Corrections Issued 8/22/2016 NILOOFAR MEHRAIN
Quality Review Completed 8/22/2016 GUANG MIN TUNG
Building Plans Picked Up 8/23/2016 APPLICANT
Applicant returned to address corrections 7/7/2017 NILOOFAR MEHRAIN
Plan Check Approved 7/10/2017 NILOOFAR MEHRAIN
Issued 7/10/2017 LADBS
Intent to Revoke-Status Void 12/8/2017 SHAHEN AKELYAN
Re-Activate Permit 8/27/2018 SHAHEN AKELYAN
CofO in Progress 8/30/2024 HERBERT GIRON
Permit Finaled 9/3/2024 RICHARD STEINBACH
CofO Issued 9/3/2024 RICHARD STEINBACH
Permit Finaled 9/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/21/2016 ERIK MUNOZ
Hydrant and Access approval Cleared 9/21/2016 JOHN DALLAS
Miscellaneous Cleared 9/21/2016 ANNA VIDAL
Miscellaneous Cleared 9/21/2016 ANNA VIDAL
ZA Case Cleared 9/21/2016 ANNA VIDAL
ZA Case Cleared 9/21/2016 ANNA VIDAL
Address approval Cleared 9/22/2016 HOWARD COOPER
Sewer availability Cleared 10/19/2016 JUSTIN ZHANG
Coastal Zone Cleared 11/22/2016 ANNA VIDAL
Miscellaneous Cleared 11/22/2016 ANNA VIDAL
Miscellaneous Cleared 11/22/2016 ANNA VIDAL
Specific Plan Cleared 11/22/2016 ANNA VIDAL
ZA Case Cleared 11/22/2016 ANNA VIDAL
Specific Plan Cleared 12/9/2016 EDER ROMERO
Specific Plan Cleared 12/9/2016 EDER ROMERO
Miscellaneous Cleared 3/24/2017 ANNA VIDAL
Green Code Cleared 5/16/2017 RUSSELL KELLY
Permit Cleared 6/23/2017 CHEN ZHANG
Low Impact Development Cleared 7/6/2017 MITESH PATEL
Roof/Waste drainage to street Cleared 7/6/2017 HISASHI KOBAYAKAWA
Miscellaneous Cleared 7/7/2017 LEE GUILBEAUX

Contact Information

Contractor Alon Dov; Lic. No.: 630785-B 13811 CALVERT STREET      VAN NUYS, CA 91401
Engineer Durand, Paul Henri Jr; Lic. No.: S4222 29 BLUERIDGE RD      FAIRFIELD, CT 06825

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/21/2018 Conditional Approval BOB DUNN
Footing/Foundation/Slab 9/21/2018 Not Ready for Inspection BOB DUNN
Sewer 9/21/2018 Not Ready for Inspection BOB DUNN
Footing/Foundation/Slab 9/25/2018 Partial Approval BOB DUNN
Sewer 9/28/2018 Approved CRAIG DAVIS
Footing/Foundation/Slab 10/17/2018 Approved RONALD WEBER
Piling/Pier/Caisson 11/7/2018 Not Ready for Inspection JONATHAN HOM
Deputy Steel/Welding 11/9/2018 No Access for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/18/2018 Partial Approval CRAIG DAVIS
Wood Frame 4/5/2019 Partial Approval DAVID HEINE
PLUMBING-Rough 7/1/2019 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 9/12/2019 Approved DAVID HEINE
HVAC-Rough 9/12/2019 Approved DAVID HEINE
PLUMBING-Rough 9/12/2019 Approved DAVID HEINE
Wood Frame 9/12/2019 Partial Approval DAVID HEINE
Deputy Wood Construction 9/16/2019 Partial Approval DAVID HEINE
Wood Frame 9/27/2019 Corrections Issued DAVID HEINE
ELECTRICAL-Rough 12/12/2019 Approved DAVID HEINE
HVAC-Rough 12/12/2019 Approved DAVID HEINE
PLUMBING-Rough 12/12/2019 Approved DAVID HEINE
Insulation 2/28/2020 Approved DAVID HEINE
Drywall Nailing 3/12/2020 Corrections Issued DAVID HEINE
Green Building Rough 3/12/2020 Corrections Issued DAVID HEINE
Drywall Nailing 6/29/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 6/29/2022 Corrections Issued DAVID FEILER
Final 6/29/2022 Corrections Issued DAVID FEILER
Green Building Rough 6/29/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 6/29/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 6/29/2022 Corrections Issued DAVID FEILER
Wood Frame 6/29/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 12/12/2022 Approved EVAN COOPER
Drywall Nailing 12/12/2022 Approved EVAN COOPER
Final 12/12/2022 Corrections Issued EVAN COOPER
Green Building Final 12/12/2022 Approved EVAN COOPER
Green Building Rough 12/12/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Approved EVAN COOPER
Service/Power Release 12/12/2022 Approved EVAN COOPER
Smoke Detectors 12/12/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 12/12/2022 Approved EVAN COOPER
Final 12/21/2022 Corrections Issued EVAN COOPER
Service/Power Release 1/12/2023 Not Required EVAN COOPER
ELECTRICAL-Final 8/29/2024 Approved HERBERT GIRON
Final 8/29/2024 OK to Issue CofO HERBERT GIRON
HVAC-Final 8/29/2024 Approved HERBERT GIRON
PLUMBING-Final 8/29/2024 Approved HERBERT GIRON
Service/Power Release 8/29/2024 Approved HERBERT GIRON