11115 W MCCORMICK ST 91601

Certificate Information: 11115 W MCCORMICK ST 91601

Application / Permit
16010-20000-03155
Plan Check / Job No.
B16VN09657
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED MIXED USE APARTEMENT/OFFFICE BLDG WITH ONE LEVEL OF BSMT.
Permit Issued
Issued on 4/25/2018
Issuing Office
Valley
Current Status
CofO Corrected on 7/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2016 APPLICANT
Assigned to Plan Check Engineer 9/1/2016 MOURAD AZIZ
Disabled Access Plans Picked Up 9/29/2016 APPLICANT
Green Plans Picked Up 9/29/2016 APPLICANT
Corrections Issued 10/3/2016 MOURAD AZIZ
Quality Review Completed 10/4/2016 GUANG MIN TUNG
Building Plans Picked Up 10/5/2016 APPLICANT
Applicant returned to address corrections 10/13/2016 MOURAD AZIZ
Applicant returned to address corrections 1/30/2017 MOURAD AZIZ
Applicant returned to address corrections 3/17/2017 MOURAD AZIZ
Applicant returned to address corrections 6/22/2017 MOURAD AZIZ
Applicant returned to address corrections 3/29/2018 DOUGLAS NAKATANI
Plan Check Approved 4/25/2018 DOUGLAS NAKATANI
Issued 4/25/2018 LADBS
CofO in Progress 6/29/2020 JOHN KITCKO
CofO Issued-Status Void 7/20/2020 RICKEY JACKSON
Permit Finaled-Status Void 7/20/2020 RICKEY JACKSON
Re-Activate Permit 7/27/2020 RICKEY JACKSON
Permit Finaled 7/29/2020 RICKEY JACKSON
CofO Corrected 7/29/2020 RICKEY JACKSON
Permit Finaled 7/29/2020 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 1/24/2018 MARKOS PEREZ-BRAN
"D" conditions Cleared 3/1/2018 HERMINIGILDO AGUSTIN
Frnt yard landscape/Water mgmt Cleared 3/1/2018 HERMINIGILDO AGUSTIN
Highway dedication Cleared 3/1/2018 KAYLA PEJI
Hydrant and Access approval Cleared 3/1/2018 JOHN DALLAS
Opn space landscape/Water mgmt Cleared 3/1/2018 HERMINIGILDO AGUSTIN
Permit Cleared 3/1/2018 KAYLA PEJI
Project located in CRA area Cleared 3/1/2018 JIM URQUHART
Eng Process Fee Ord 176,300 Cleared 3/13/2018 JOSEPH RHYU
Sewer availability Cleared 3/13/2018 JOSEPH RHYU
DAS Clearance Cleared 3/16/2018 FARUK SEZER
Green Code Cleared 3/20/2018 MICHAEL AYERS
Fire Marshall Fire Life Safety Cleared 3/21/2018 OSCAR SALGADO JR
Work Adjacent to Public Way Cleared 3/21/2018 EDUARDO PEDROZA
Low Impact Development Cleared 3/29/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/30/2018 FATIMA GUERRA
Building over 3-story or 36-ft Cleared 4/25/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/25/2018 CALOSHA APPROVED

Contact Information

Architect Jazayeri, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor M G A M Inc; Lic. No.: 966423-B 18960 KESWICK STREET      RESEDA, CA 91335
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/14/2018 Approved JOHN KITCKO
Piling/Pier/Caisson 5/18/2018 Partial Approval JOHN KITCKO
Piling/Pier/Caisson 5/24/2018 Partial Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/4/2018 Partial Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/9/2018 Partial Inspection JOHN KITCKO
Masonry Wall/Backfill 7/10/2018 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/20/2018 Partial Approval JOHN KITCKO
Green Building Rough 8/8/2018 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 8/8/2018 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 8/8/2018 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 8/9/2018 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/16/2018 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/7/2018 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/13/2018 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/20/2018 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 10/9/2018 Conditional Approval JOHN KITCKO
Deputy Shotcrete 10/10/2018 Approved JOHN KITCKO
Footing/Foundation/Slab 10/24/2018 Partial Approval JOHN KITCKO
Deputy Pre-Stress Concrete 10/26/2018 Approved JOHN KITCKO
Deputy Pre-Stress Concrete 10/30/2018 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/7/2018 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/14/2018 Conditional Approval JOHN KITCKO
Deputy Shotcrete 11/15/2018 Approved JOHN KITCKO
Masonry Wall/Backfill 11/26/2018 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/4/2018 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 12/11/2018 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 12/18/2018 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 12/26/2018 Corrections Issued JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/2/2019 Partial Approval JOHN KITCKO
Deputy Pre-Stress Concrete 1/9/2019 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/22/2019 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 3/8/2019 Approved JOHN KITCKO
Footing/Foundation/Slab 3/27/2019 Partial Approval JOHN KITCKO
Deputy Pre-Stress Concrete 3/29/2019 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/15/2019 Corrections Issued JOHN KITCKO
Green Building Rough 4/17/2019 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 4/17/2019 Not Ready for Inspection JOHN KITCKO
Wood Frame 4/17/2019 Partial Approval JOHN KITCKO
Deputy Pre-Stress Concrete 4/29/2019 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/1/2019 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/13/2019 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 5/16/2019 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/3/2019 Partial Approval MILLARD ARDOIN
Green Building Rough 7/1/2019 Partial Approval JOHN KITCKO
Green Building Rough 7/12/2019 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/12/2019 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/12/2019 Partial Approval JOHN KITCKO
Insulation 7/18/2019 Partial Approval JOHN KITCKO
Green Building Rough 7/23/2019 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/23/2019 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/23/2019 Not Ready for Inspection JOHN KITCKO
Green Building Rough 7/29/2019 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/29/2019 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/29/2019 Partial Approval JOHN KITCKO
Green Building Rough 7/31/2019 No Access for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/31/2019 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/31/2019 No Access for Inspection JOHN KITCKO
Insulation 8/2/2019 Corrections Issued JOHN KITCKO
Green Building Rough 8/5/2019 Approved JOHN KITCKO
Verify Sprinkler Sign Off 8/5/2019 Approved JOHN KITCKO
Wood Frame 8/5/2019 Partial Approval JOHN KITCKO
Wood Frame 8/7/2019 Partial Approval JOHN KITCKO
Wood Frame 8/9/2019 Approved JOHN KITCKO
Insulation 8/14/2019 Partial Approval JOHN KITCKO
Insulation 8/15/2019 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 8/20/2019 Partial Approval JOHN KITCKO
Insulation 8/26/2019 Partial Approval JOHN KITCKO
Drywall Nailing 8/30/2019 Partial Inspection JOHN KITCKO
Drywall Nailing 9/6/2019 Partial Approval JOHN KITCKO
Drywall Nailing 9/10/2019 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 9/19/2019 Corrections Issued JOHN KITCKO
Drywall Nailing 9/25/2019 Partial Approval JOHN KITCKO
Drywall Nailing 9/27/2019 Partial Approval JOHN KITCKO
Drywall Nailing 10/1/2019 Partial Approval JOHN KITCKO
Drywall Nailing 10/3/2019 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 10/3/2019 Partial Approval JOHN KITCKO
Drywall Nailing 10/7/2019 Partial Approval JOHN KITCKO
Drywall Nailing 10/9/2019 Partial Approval JOHN KITCKO
Drywall Nailing 10/16/2019 Partial Approval JOHN KITCKO
Drywall Nailing 10/24/2019 Partial Approval JOHN KITCKO
Special/Order Compliance 1/3/2020 Partial Inspection JOHN KITCKO
Drywall Nailing 2/20/2020 Not Ready for Inspection JOHN KITCKO
Final 2/20/2020 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 2/20/2020 Not Ready for Inspection JOHN KITCKO
Green Building Final 2/20/2020 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 2/20/2020 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 2/20/2020 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 2/20/2020 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 2/20/2020 Not Ready for Inspection JOHN KITCKO
Structural Steel Frame 2/20/2020 Approved JOHN KITCKO
Drywall Nailing 6/8/2020 Approved JOHN KITCKO
Final 6/8/2020 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 6/8/2020 Approved JOHN KITCKO
Green Building Final 6/8/2020 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 6/8/2020 Approved JOHN KITCKO
Reinforced Masonry Frame 6/8/2020 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 6/8/2020 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 6/8/2020 Not Ready for Inspection JOHN KITCKO
Final 6/15/2020 Partial Inspection JOHN KITCKO
Green Building Final 6/15/2020 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 6/15/2020 SGSOV Approved JOHN KITCKO
Smoke Detectors 6/15/2020 Approved JOHN KITCKO
Final 6/29/2020 OK to Issue CofO JOHN KITCKO