9875 W RIMMELE DR 90210
Certificate Information: 9875 W RIMMELE DR 90210
- Application / Permit
- 16010-20000-02408
- Plan Check / Job No.
- B16VN07618
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3- story irregular shape single family dwelling over (1-) level of basement garage. The proposed structure shall be fully sprinklered per NFPA-13D requirements.
- Permit Issued
- Issued on 4/1/2019
- Issuing Office
- Valley
- Current Status
- Issued on 4/1/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/7/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2016 | ARMEN SARKISIAN |
| Corrections Issued | 7/13/2016 | ARMEN SARKISIAN |
| Quality Review Completed | 7/18/2016 | RUDOLF KINAR MELIKOFF |
| Building Plans Picked Up | 7/21/2016 | APPLICANT |
| Applicant returned to address corrections | 7/26/2016 | ARMEN SARKISIAN |
| Applicant returned to address corrections | 8/11/2016 | ARMEN SARKISIAN |
| Applicant returned to address corrections | 12/9/2016 | ARMEN SARKISIAN |
| Applicant returned to address corrections | 4/20/2017 | ARMEN SARKISIAN |
| Applicant returned to address corrections | 5/16/2017 | ARMEN SARKISIAN |
| Applicant returned to address corrections | 5/24/2017 | ARMEN SARKISIAN |
| Applicant returned to address corrections | 7/20/2017 | ARMEN SARKISIAN |
| Applicant returned to address corrections | 7/28/2017 | ARMEN SARKISIAN |
| Plan Check Approved | 8/1/2017 | ARMEN SARKISIAN |
| Issued | 4/1/2019 | LADBS |
| Permit Expired-Status Void | 12/11/2024 | MICHAEL PELHAM |
| Re-Activate Permit | 12/13/2024 | MICHAEL PELHAM |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 8/24/2016 | SUSAN ZERMENO |
| Address approval | Cleared | 8/31/2016 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 8/31/2016 | JACOB BIGLER |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2016 | RAVIL MANAPOV |
| Sewer availability | Cleared | 9/29/2016 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 4/5/2017 | ROBERT DUFF |
| Work Adjacent to Public Way | Cleared | 4/5/2017 | RAVIL MANAPOV |
| Private street | Cleared | 4/6/2017 | DWAYNE WYATT |
| Low Impact Development | Cleared | 5/9/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 5/9/2017 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 5/15/2017 | ANDREW SLUSSER |
| BHO/Hillside ordinance | Cleared | 5/15/2017 | LUZ RABELO |
| BHO/Hillside ordinance | Cleared | 5/15/2017 | LUZ RABELO |
| Excavation more than 5-ft deep | Cleared | 5/24/2017 | CALOSHA APPROVED |
| Green Code | Cleared | 6/1/2017 | ROLLIN GETTLE III |
Contact Information
| Architect | Elmanovich, Vladimir; Lic. No.: C25822 | 16987 ENCINO HILLS DRIVE ENCINO, CA 91436 |
| Contractor | Newform Construction Company; Lic. No.: 833302-B | 7405 DEL ZURO DRIVE LOS ANGELES, CA 90046 |
| Engineer | Balshem, Efim Bercovich; Lic. No.: C34313 | 1125 16TH ST UNIT 5 SANTA MONICA, CA 90403 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/19/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Special/Order Compliance | 1/4/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 1/7/2022 | Order to Comply Issued | MICHAEL PELHAM |
| Special/Order Compliance | 1/13/2022 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 1/31/2022 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 2/7/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 7/25/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 7/25/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 2/1/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 3/2/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Grading | 3/3/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 5/18/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/20/2023 | Corrections Issued | BRENDAN LOONEY |
| Piling/Pier/Caisson | 12/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| Special/Order Compliance | 12/11/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 12/27/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 2/24/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 2/25/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 2/26/2025 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 2/24/2026 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/27/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 3/3/2026 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 3/26/2026 | Conditional Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 4/13/2026 | Corrections Issued | CHRISTOPHER WILSON |