7661 W CURSON TER 90046

Certificate Information: 7661 W CURSON TER 90046

Application / Permit
16010-20000-02268
Plan Check / Job No.
B16VN07164
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. (SEE COMMENT)
Permit Issued
Issued on 4/6/2017
Issuing Office
Valley
Current Status
Issued on 4/6/2017
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/27/2016 APPLICANT
Assigned to Plan Check Engineer 6/9/2016 KAMRAN GHOTBI RAVANDI
Corrections Issued 6/13/2016 KAMRAN GHOTBI RAVANDI
Quality Review Completed 6/13/2016 RUDOLF KINAR MELIKOFF
Building Plans Picked Up 6/14/2016 APPLICANT
Green Plans Picked Up 6/16/2016 APPLICANT
Applicant returned to address corrections 6/28/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/16/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/22/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/19/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/25/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/7/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/14/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/28/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/20/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/10/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/6/2017 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/14/2017 KAMRAN GHOTBI RAVANDI
Plan Check Approved 4/6/2017 KAMRAN GHOTBI RAVANDI
Issued 4/6/2017 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/23/2016 SEVAK ISAKHAYAN
Eng Process Fee Ord 176,300 Cleared 6/23/2016 SEVAK ISAKHAYAN
Public Works-Highway Ded. Cleared 8/10/2016 JAMES MORALEZ
Public Works-Open Permits Cleared 8/10/2016 JAMES MORALEZ
Public Works-Sewers Cleared 8/10/2016 JAMES MORALEZ
Hydrant and Access approval Cleared 9/27/2016 ROBERT DUFF
ZA Case Cleared 10/21/2016 CASSANDRA ZWEEP
Certificate of Compliance Cleared 10/24/2016 SUSAN ZERMENO
Green Code Cleared 12/5/2016 MICHAEL AYERS
BHO/Hillside ordinance Cleared 12/13/2016 IRENE CHIA
BHO/Hillside ordinance Cleared 12/13/2016 IRENE CHIA
BHO/Hillside ordinance Cleared 12/13/2016 ROBERT SAMONTE
Permit Cleared 12/13/2016 IRENE CHIA
Construction within easement Cleared 12/21/2016 WALTER RAMIREZ
Low Impact Development Cleared 1/24/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/3/2017 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 3/6/2017 CALOSHA APPROVED

Contact Information

Contractor Gibson Construction; Lic. No.: 524012-B 3000 31 STREET SUITE G      SANTA MONICA, CA 90405
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 10/19/2017 Approved RAUL BARAJAS
Deputy Grading 10/20/2017 No Access for Inspection RAUL BARAJAS
Piling/Pier/Caisson 11/6/2017 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 11/9/2017 Approved RAUL BARAJAS
Piling/Pier/Caisson 11/13/2017 Partial Approval LUIS BARRALES
Piling/Pier/Caisson 11/14/2017 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 11/15/2017 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/29/2017 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/1/2017 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/20/2017 Partial Approval RAUL BARAJAS
PLUMBING-Rough 1/5/2018 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/23/2018 Not Ready for Inspection RAUL BARAJAS
Deputy Shotcrete 1/24/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/29/2018 Partial Approval RAUL BARAJAS
Deputy Shotcrete 1/31/2018 Approved RAUL BARAJAS
Deputy Reinf. Concrete 2/6/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/6/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/6/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/7/2018 Approved LUIS BARRALES
Deputy Reinf. Concrete 2/14/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/14/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 2/16/2018 Approved RAUL BARAJAS
Footing/Foundation/Slab 2/20/2018 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 2/20/2018 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 2/20/2018 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 2/20/2018 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 2/27/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/27/2018 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 2/27/2018 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/2/2018 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 3/2/2018 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/5/2018 Partial Approval RAUL BARAJAS
Underground Mechanical 3/9/2018 Partial Approval RAUL BARAJAS
Underground Mechanical 3/13/2018 Approved RAUL BARAJAS
ELECTRICAL-Rough 3/14/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/14/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/22/2018 No Access for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/23/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/28/2018 Partial Approval RAUL BARAJAS
Underground Mechanical 3/28/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/6/2018 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 4/9/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/9/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/12/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/12/2018 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 4/13/2018 Approved RAUL BARAJAS
Reinforced Concrete Frame 4/13/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/16/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/18/2018 Approved RAUL BARAJAS
ELECTRICAL-Rough 4/18/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/18/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 4/18/2018 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/20/2018 Not Ready for Inspection RAUL BARAJAS
Deputy Shotcrete 4/23/2018 Approved LUIS BARRALES
Deputy Reinf. Concrete 4/24/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/24/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/25/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/1/2018 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/2/2018 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 5/3/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/3/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/4/2018 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 5/8/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/15/2018 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 5/30/2018 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/30/2018 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 5/30/2018 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 5/31/2018 Approved RONALD COWAN
ELECTRICAL-Rough 5/31/2018 Not Ready for Inspection RONALD COWAN
Excavation/Setback/Form/Re-Bar 5/31/2018 Partial Approval RONALD COWAN
HVAC-Rough 5/31/2018 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 5/31/2018 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 6/4/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/4/2018 Partial Approval RAUL BARAJAS
HVAC-Rough 6/4/2018 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 6/4/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/13/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/14/2018 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/15/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/22/2018 Approved RAUL BARAJAS
Footing/Foundation/Slab 6/22/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/26/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/29/2018 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 6/29/2018 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 7/2/2018 Approved LUIS BARRALES
Excavation/Setback/Form/Re-Bar 7/2/2018 Partial Approval LUIS BARRALES
Deputy Reinf. Concrete 7/6/2018 Approved RAUL BARAJAS
Footing/Foundation/Slab 7/12/2018 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 7/12/2018 Partial Approval RAUL BARAJAS
Deputy Shotcrete 7/13/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/20/2018 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 7/20/2018 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/23/2018 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 7/24/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/24/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/26/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 7/27/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/2/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/9/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/23/2018 No Access for Inspection RONALD COWAN
ELECTRICAL-Rough 9/13/2018 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 9/13/2018 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 10/2/2018 No Access for Inspection RONALD COWAN
Excavation/Setback/Form/Re-Bar 10/2/2018 No Access for Inspection RONALD COWAN
Excavation/Setback/Form/Re-Bar 10/4/2018 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 10/5/2018 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 10/26/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 10/29/2018 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 10/31/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/2/2018 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 11/19/2018 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/21/2018 Partial Approval RAUL BARAJAS
PLUMBING-Rough 11/26/2018 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 11/27/2018 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 12/12/2018 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/19/2018 Partial Approval RAUL BARAJAS
Deputy Shotcrete 12/27/2018 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 1/9/2019 Partial Inspection BRIAN SULLIVAN
PLUMBING-Rough 1/9/2019 Partial Inspection BRIAN SULLIVAN
Sewer 1/9/2019 Partial Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/25/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/11/2019 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/12/2019 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 2/28/2019 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/13/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/18/2019 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/28/2019 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 3/29/2019 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/1/2019 Partial Approval BRIAN SULLIVAN
Sewer 4/1/2019 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/15/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/25/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 4/26/2019 Conditional Approval CHARLES BOGHOSKHAN
Excavation/Setback/Form/Re-Bar 5/3/2019 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 5/3/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 5/8/2019 Approved BRIAN SULLIVAN
Deputy Reinf. Concrete 5/15/2019 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/17/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/24/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/31/2019 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 6/3/2019 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 6/11/2019 Approved RAUL BARAJAS
Deputy Other (see comments) 6/18/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/18/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/20/2019 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/2/2019 Partial Approval BRIAN SULLIVAN
Deputy Shotcrete 7/15/2019 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/16/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/22/2019 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 7/25/2019 Conditional Approval BRIAN SULLIVAN
Reinforced Concrete Frame 7/29/2019 Partial Approval RAUL BARAJAS
Deputy Drilled-In Anchors 8/8/2019 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 8/8/2019 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/9/2019 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/29/2019 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/25/2019 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 10/31/2019 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 11/22/2019 Partial Approval RAUL BARAJAS
HVAC-Rough 11/22/2019 Partial Approval RAUL BARAJAS
PLUMBING-Rough 11/22/2019 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 11/22/2019 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/6/2019 Partial Approval BRIAN SULLIVAN
Underground Mechanical 1/7/2020 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 1/22/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/22/2020 Partial Approval BRIAN SULLIVAN
Gas Test 1/22/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/29/2020 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 2/6/2020 Partial Approval RAUL BARAJAS
Underground Mechanical 2/6/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/10/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/10/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 3/5/2020 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/5/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/5/2020 Partial Approval RAUL BARAJAS
Sewer 3/5/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 3/9/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/9/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/9/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/10/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 4/10/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/20/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 4/20/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/26/2020 Partial Approval RAUL BARAJAS
PLUMBING-Rough 5/26/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/28/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 6/26/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/26/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/10/2020 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 7/20/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/20/2020 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 7/20/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/7/2020 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 8/19/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/19/2020 Partial Approval BRIAN SULLIVAN
HVAC-Rough 8/19/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 8/19/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 8/25/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/8/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/11/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 9/29/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/1/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/9/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/22/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/4/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/17/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 12/2/2020 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 12/2/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 12/7/2020 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 12/22/2020 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 12/31/2020 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 12/31/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/7/2021 Partial Approval BRIAN SULLIVAN
Deputy Wood Construction 3/5/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 3/9/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 3/9/2021 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 3/9/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Partial Approval RAUL BARAJAS
Green Building Rough 8/11/2021 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/11/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 8/18/2021 Partial Approval BRIAN SULLIVAN
Drywall Nailing 9/15/2021 Partial Approval BRIAN SULLIVAN
Sewer 9/15/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 9/16/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 9/17/2021 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 9/20/2021 Partial Approval BRIAN SULLIVAN
Sewer 9/20/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 9/22/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 9/23/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 9/24/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 9/27/2021 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 9/28/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 9/30/2021 Partial Inspection RAUL BARAJAS
Pre-Inspection 10/5/2021 Not Ready for Inspection BRIAN SULLIVAN
Pre-Inspection 10/5/2021 Partial Inspection ANTHONY DE SANTIS
Pre-Inspection 10/7/2021 Partial Inspection ANTHONY DE SANTIS
Pre-Inspection 10/7/2021 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 11/15/2021 Partial Approval CHRIS CHRISTENSEN
Sewer 11/23/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 11/30/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 12/2/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 12/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 12/16/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 12/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 12/16/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 12/20/2021 Not Ready for Inspection BRIAN SULLIVAN
Insulation 2/3/2022 Partial Approval BRIAN SULLIVAN
Wood Frame 2/3/2022 Partial Approval BRIAN SULLIVAN
Service/Power Release 2/17/2022 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 2/24/2022 Partial Inspection SCOTT FINNILA
Shower Pan 2/24/2022 Approved SCOTT FINNILA
Shower Pan 2/25/2022 Approved BRIAN SULLIVAN
HVAC-Rough 3/10/2022 Partial Approval BRIAN SULLIVAN
Shower Pan 5/3/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 6/10/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 6/13/2022 Partial Approval BRIAN SULLIVAN
HVAC-Rough 6/13/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 6/14/2022 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 6/15/2022 Conditional Approval BRIAN SULLIVAN
Green Building Rough 6/15/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 6/15/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 6/23/2022 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 6/23/2022 Partial Approval BRIAN SULLIVAN
Insulation 6/27/2022 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/30/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 10/6/2022 Partial Approval BRIAN SULLIVAN
HVAC-Rough 10/19/2022 Partial Approval BRIAN SULLIVAN
HVAC-Rough 10/20/2022 Partial Approval BRIAN SULLIVAN
Insulation 12/6/2022 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 12/6/2022 Partial Approval BRIAN SULLIVAN
Insulation 12/15/2022 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 12/20/2022 Partial Inspection BRIAN SULLIVAN
Drywall Nailing 12/29/2022 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 1/5/2023 Approved RAUL BARAJAS
Service/Power Release 1/5/2023 Approved RAUL BARAJAS
HVAC-Rough 2/13/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 2/16/2023 Approved BRIAN SULLIVAN
HVAC-Rough 2/16/2023 Corrections Issued BRIAN SULLIVAN
Drywall Nailing 2/27/2023 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 2/27/2023 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 2/27/2023 Partial Inspection RUBEN SALAS
Interior/Exterior Lathing 4/10/2023 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/9/2023 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 5/26/2023 Approved BRIAN SULLIVAN
SUSMP-Std. Urban Storm Water 6/21/2023 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 7/17/2023 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/31/2023 Approved BRIAN SULLIVAN
Final 8/31/2023 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/31/2023 Approved BRIAN SULLIVAN
Green Building Final 8/31/2023 Partial Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 8/31/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 8/31/2023 Partial Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 8/31/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Final 10/25/2023 Partial Approval BRIAN SULLIVAN
HVAC-Final 10/25/2023 Partial Approval BRIAN SULLIVAN
PLUMBING-Final 10/25/2023 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Final 10/26/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 10/26/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 10/26/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 11/20/2023 Partial Inspection BRIAN SULLIVAN
HVAC-Final 11/20/2023 Partial Inspection BRIAN SULLIVAN
PLUMBING-Final 11/20/2023 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Final 1/4/2024 Approved RAUL BARAJAS
HVAC-Final 1/4/2024 Approved RAUL BARAJAS
PLUMBING-Final 1/4/2024 Approved RAUL BARAJAS
ELECTRICAL-Final 1/8/2024 Approved BRIAN SULLIVAN
HVAC-Final 1/8/2024 Approved BRIAN SULLIVAN
PLUMBING-Final 1/8/2024 Approved BRIAN SULLIVAN
Grading Pre-Inspection 3/14/2024 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 3/17/2026 Corrections Issued BRIAN SULLIVAN