2152 W CLIFFORD ST 90026

Certificate Information: 2152 W CLIFFORD ST 90026

Application / Permit
16010-20000-02198
Plan Check / Job No.
B16VN06882
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
"Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-71678-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 3-STORY 21'-8" X 34'-6" SFD W/ ATT. 2-CAR GARAGE, PATIO TRELLIS, & ROOF DECK; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-71678-SL).
Permit Issued
Issued on 4/27/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2016 APPLICANT
Assigned to Plan Check Engineer 6/30/2016 ALEXANDER SBARDELLATI
Green Plans Picked Up 6/30/2016 APPLICANT
Corrections Issued 7/14/2016 ALEXANDER SBARDELLATI
Quality Review Completed 7/15/2016 STEVEN KIM
Building Plans Picked Up 7/19/2016 APPLICANT
Applicant returned to address corrections 8/3/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 10/5/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 12/14/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/2/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/24/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/7/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/17/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 4/10/2017 ALEXANDER SBARDELLATI
Plan Check Approved 4/14/2017 ALEXANDER SBARDELLATI
Issued 4/27/2017 LADBS
CofO in Progress 5/22/2020 SCOTT FINNILA
Permit Finaled 5/29/2020 DEROLD HAUFF
CofO Issued 5/29/2020 DEROLD HAUFF
Permit Finaled 5/29/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/19/2016 RAVIL MANAPOV
GPI Written Notices Cleared 11/8/2016 ALEXANDER SBARDELLATI
Grading Pre-Inspection Cleared 11/8/2016 ALEXANDER SBARDELLATI
Highway dedication Cleared 12/5/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 1/20/2017 JOHN CONNEALLY
Green Code Cleared 1/27/2017 MICHAEL AYERS
Low Impact Development Cleared 2/1/2017 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 2/24/2017 RAVIL MANAPOV
Sewer availability Cleared 3/3/2017 ALFREDO JARA
Miscellaneous Cleared 3/8/2017 LINDA MARGARET
Miscellaneous Cleared 3/8/2017 LINDA MARGARET
Permit Cleared 3/8/2017 LINDA MARGARET
Roof/Waste drainage to street Cleared 3/8/2017 LINDA MARGARET
"Q" conditions Cleared 4/3/2017 EDBER MACEDO
APC Cleared 4/3/2017 EDBER MACEDO
CPC Cleared 4/3/2017 EDBER MACEDO
Frnt yard landscape/Water mgmt Cleared 4/3/2017 EDBER MACEDO
Miscellaneous Cleared 4/3/2017 EDBER MACEDO
Tract Map conditions Cleared 4/3/2017 EDBER MACEDO
Driveway location Cleared 4/13/2017 COLLINS ALLAN
Miscellaneous Cleared 4/13/2017 COLLINS ALLAN

Contact Information

Architect Tabencki-Dombrowa,, Janek; Lic. No.: C23642 506 SANTA MONICA BLVD      SANTA MONICA, CA 90401
Contractor Ark Construction & Development Inc; Lic. No.: 438036-B 528 PALISADES DR # 530      PACIFIC PALISADES, CA 90272
Engineer Hill, Edward Foster; Lic. No.: GE2126 GEOTECH 439 WESTERN AVE      GLENDALE, CA 91201
Engineer Rothman, Roland Patrick; Lic. No.: C47790 205 S BROADWAY STE 206      LOS ANGELES, CA 90012

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/15/2017 Not Ready for Inspection SCOTT FINNILA
Deputy Reinf. Concrete 12/20/2017 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 12/21/2017 Conditional Approval SCOTT FINNILA
Deputy Reinf. Concrete 12/22/2017 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 1/5/2018 Partial Approval SCOTT FINNILA
Deputy Shotcrete 1/8/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 1/17/2018 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 1/18/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 1/30/2018 Approved DOMINIC DANERI
Footing/Foundation/Slab 1/31/2018 Not Ready for Inspection SCOTT FINNILA
Deputy Reinf. Concrete 2/15/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 2/26/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 2/27/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 2/27/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 2/28/2018 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 3/12/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/5/2018 Not Ready for Inspection MICHAEL FAUNCE
Deputy Drilled-In Anchors 4/9/2018 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/2/2018 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/15/2018 Partial Approval SCOTT FINNILA
Green Building Rough 5/15/2018 Not Ready for Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 5/15/2018 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 5/17/2018 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 5/17/2018 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 6/1/2018 Conditional Approval MICHAEL FAUNCE
Green Building Rough 6/1/2018 Conditional Approval MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 6/5/2018 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 6/20/2018 Corrections Issued SCOTT FINNILA
Green Building Rough 6/20/2018 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/28/2018 Not Ready for Inspection MICHAEL FAUNCE
Drywall Nailing 7/6/2018 Conditional Approval MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 7/6/2018 Conditional Approval MICHAEL FAUNCE
Green Building Rough 7/6/2018 Conditional Approval MICHAEL FAUNCE
Drywall Nailing 7/10/2018 Partial Approval SCOTT FINNILA
Green Building Rough 7/10/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 7/12/2018 Partial Approval SCOTT FINNILA
Green Building Rough 7/12/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/25/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/26/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 7/31/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/22/2018 Conditional Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 8/23/2018 Not Ready for Inspection SCOTT FINNILA
Deputy Reinf. Concrete 8/24/2018 Partial Approval SCOTT FINNILA
PLUMBING-Rough 10/17/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/5/2018 Corrections Issued SCOTT FINNILA
HVAC-Rough 11/8/2018 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/13/2018 Partial Approval SCOTT FINNILA
Gas Test 11/13/2018 Partial Approval SCOTT FINNILA
PLUMBING-Rough 11/13/2018 Partial Approval SCOTT FINNILA
HVAC-Rough 11/16/2018 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 12/14/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 12/31/2018 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/3/2019 Partial Inspection MICHAEL FAUNCE
BUILDING-Rough-Frame 3/8/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 3/13/2019 Approved SCOTT FINNILA
ELECTRICAL-Rough 3/15/2019 Approved SCOTT FINNILA
HVAC-Rough 3/15/2019 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 3/20/2019 Corrections Issued SCOTT FINNILA
Deputy Wood Construction 3/27/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 4/10/2019 Corrections Issued SCOTT FINNILA
Green Building Rough 4/10/2019 Approved SCOTT FINNILA
Insulation 4/12/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 4/29/2019 Approved SCOTT FINNILA
Shower Pan 5/6/2019 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 5/14/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/15/2019 Not Ready for Inspection SCOTT FINNILA
Reinforced Concrete Frame 7/15/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 8/13/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 9/16/2019 Approved ALEJANDRO DE ARTOLA
Gas Test 2/11/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 2/18/2020 Corrections Issued SCOTT FINNILA
Gas Test 2/18/2020 Approved SCOTT FINNILA
HVAC-Final 2/18/2020 Approved SCOTT FINNILA
PLUMBING-Final 2/18/2020 Corrections Issued SCOTT FINNILA
HVAC-Final 2/28/2020 Not Ready for Inspection SCOTT FINNILA
Service/Power Release 2/28/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 3/19/2020 Approved SCOTT FINNILA
Service/Power Release 3/19/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 3/31/2020 Approved SCOTT FINNILA
Final 3/31/2020 Corrections Issued SCOTT FINNILA
Green Building Final 3/31/2020 Partial Approval SCOTT FINNILA
Reinforced Concrete Frame 3/31/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/31/2020 SGSOV Not Ready SCOTT FINNILA
Smoke Detectors 3/31/2020 Approved SCOTT FINNILA
Structural Steel Frame 3/31/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 3/31/2020 Approved SCOTT FINNILA
Final 5/8/2020 Partial Approval SCOTT FINNILA
Green Building Final 5/8/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/8/2020 SGSOV Approved SCOTT FINNILA
Final 5/22/2020 OK to Issue CofO SCOTT FINNILA
PLUMBING-Final 5/22/2020 Approved SCOTT FINNILA