2152 W CLIFFORD ST 90026
Certificate Information: 2152 W CLIFFORD ST 90026
- Application / Permit
- 16010-20000-02198
- Plan Check / Job No.
- B16VN06882
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- "Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-71678-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 3-STORY 21'-8" X 34'-6" SFD W/ ATT. 2-CAR GARAGE, PATIO TRELLIS, & ROOF DECK; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-71678-SL).
- Permit Issued
- Issued on 4/27/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2016 | ALEXANDER SBARDELLATI |
| Green Plans Picked Up | 6/30/2016 | APPLICANT |
| Corrections Issued | 7/14/2016 | ALEXANDER SBARDELLATI |
| Quality Review Completed | 7/15/2016 | STEVEN KIM |
| Building Plans Picked Up | 7/19/2016 | APPLICANT |
| Applicant returned to address corrections | 8/3/2016 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 10/5/2016 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 12/14/2016 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 2/2/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 2/24/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/7/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/17/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 4/10/2017 | ALEXANDER SBARDELLATI |
| Plan Check Approved | 4/14/2017 | ALEXANDER SBARDELLATI |
| Issued | 4/27/2017 | LADBS |
| CofO in Progress | 5/22/2020 | SCOTT FINNILA |
| Permit Finaled | 5/29/2020 | DEROLD HAUFF |
| CofO Issued | 5/29/2020 | DEROLD HAUFF |
| Permit Finaled | 5/29/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2016 | RAVIL MANAPOV |
| GPI Written Notices | Cleared | 11/8/2016 | ALEXANDER SBARDELLATI |
| Grading Pre-Inspection | Cleared | 11/8/2016 | ALEXANDER SBARDELLATI |
| Highway dedication | Cleared | 12/5/2016 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 1/20/2017 | JOHN CONNEALLY |
| Green Code | Cleared | 1/27/2017 | MICHAEL AYERS |
| Low Impact Development | Cleared | 2/1/2017 | SAM NAVID |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2017 | RAVIL MANAPOV |
| Sewer availability | Cleared | 3/3/2017 | ALFREDO JARA |
| Miscellaneous | Cleared | 3/8/2017 | LINDA MARGARET |
| Miscellaneous | Cleared | 3/8/2017 | LINDA MARGARET |
| Permit | Cleared | 3/8/2017 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 3/8/2017 | LINDA MARGARET |
| "Q" conditions | Cleared | 4/3/2017 | EDBER MACEDO |
| APC | Cleared | 4/3/2017 | EDBER MACEDO |
| CPC | Cleared | 4/3/2017 | EDBER MACEDO |
| Frnt yard landscape/Water mgmt | Cleared | 4/3/2017 | EDBER MACEDO |
| Miscellaneous | Cleared | 4/3/2017 | EDBER MACEDO |
| Tract Map conditions | Cleared | 4/3/2017 | EDBER MACEDO |
| Driveway location | Cleared | 4/13/2017 | COLLINS ALLAN |
| Miscellaneous | Cleared | 4/13/2017 | COLLINS ALLAN |
Contact Information
| Architect | Tabencki-Dombrowa,, Janek; Lic. No.: C23642 | 506 SANTA MONICA BLVD SANTA MONICA, CA 90401 |
| Contractor | Ark Construction & Development Inc; Lic. No.: 438036-B | 528 PALISADES DR # 530 PACIFIC PALISADES, CA 90272 |
| Engineer | Hill, Edward Foster; Lic. No.: GE2126 | GEOTECH 439 WESTERN AVE GLENDALE, CA 91201 |
| Engineer | Rothman, Roland Patrick; Lic. No.: C47790 | 205 S BROADWAY STE 206 LOS ANGELES, CA 90012 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/15/2017 | Not Ready for Inspection | SCOTT FINNILA |
| Deputy Reinf. Concrete | 12/20/2017 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/21/2017 | Conditional Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 12/22/2017 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 1/5/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Shotcrete | 1/8/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 1/17/2018 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 1/18/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 1/30/2018 | Approved | DOMINIC DANERI |
| Footing/Foundation/Slab | 1/31/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Deputy Reinf. Concrete | 2/15/2018 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 2/26/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 2/27/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 2/27/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 2/28/2018 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 3/12/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/5/2018 | Not Ready for Inspection | MICHAEL FAUNCE |
| Deputy Drilled-In Anchors | 4/9/2018 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/2/2018 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2018 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 5/15/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 5/15/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Drywall Nailing | 5/17/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Green Building Rough | 5/17/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Drywall Nailing | 6/1/2018 | Conditional Approval | MICHAEL FAUNCE |
| Green Building Rough | 6/1/2018 | Conditional Approval | MICHAEL FAUNCE |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2018 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 6/20/2018 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 6/20/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2018 | Not Ready for Inspection | MICHAEL FAUNCE |
| Drywall Nailing | 7/6/2018 | Conditional Approval | MICHAEL FAUNCE |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2018 | Conditional Approval | MICHAEL FAUNCE |
| Green Building Rough | 7/6/2018 | Conditional Approval | MICHAEL FAUNCE |
| Drywall Nailing | 7/10/2018 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 7/10/2018 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 7/12/2018 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 7/12/2018 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2018 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2018 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 7/31/2018 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2018 | Conditional Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/23/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Deputy Reinf. Concrete | 8/24/2018 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 10/17/2018 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2018 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 11/8/2018 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2018 | Partial Approval | SCOTT FINNILA |
| Gas Test | 11/13/2018 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 11/13/2018 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 11/16/2018 | Corrections Issued | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/14/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 12/31/2018 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2019 | Partial Inspection | MICHAEL FAUNCE |
| BUILDING-Rough-Frame | 3/8/2019 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 3/13/2019 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/15/2019 | Approved | SCOTT FINNILA |
| HVAC-Rough | 3/15/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Green Building Rough | 3/20/2019 | Corrections Issued | SCOTT FINNILA |
| Deputy Wood Construction | 3/27/2019 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/10/2019 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 4/10/2019 | Approved | SCOTT FINNILA |
| Insulation | 4/12/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Drywall Nailing | 4/29/2019 | Approved | SCOTT FINNILA |
| Shower Pan | 5/6/2019 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/14/2019 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/15/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Reinforced Concrete Frame | 7/15/2019 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 8/13/2019 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 9/16/2019 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 2/11/2020 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 2/18/2020 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 2/18/2020 | Approved | SCOTT FINNILA |
| HVAC-Final | 2/18/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 2/18/2020 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 2/28/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Service/Power Release | 2/28/2020 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 3/19/2020 | Approved | SCOTT FINNILA |
| Service/Power Release | 3/19/2020 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/31/2020 | Approved | SCOTT FINNILA |
| Final | 3/31/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 3/31/2020 | Partial Approval | SCOTT FINNILA |
| Reinforced Concrete Frame | 3/31/2020 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2020 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 3/31/2020 | Approved | SCOTT FINNILA |
| Structural Steel Frame | 3/31/2020 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 3/31/2020 | Approved | SCOTT FINNILA |
| Final | 5/8/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Final | 5/8/2020 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2020 | SGSOV Approved | SCOTT FINNILA |
| Final | 5/22/2020 | OK to Issue CofO | SCOTT FINNILA |
| PLUMBING-Final | 5/22/2020 | Approved | SCOTT FINNILA |