3672 S JASMINE AVE #1-17 90034

Certificate Information: 3672 S JASMINE AVE #1-17 90034

Application / Permit
16010-20000-01377
Plan Check / Job No.
B16VN04501
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 72'-0" X 85'-0" IRREGULAR FIVE-STORY (17 UNITS, 2 ARE VERY LOW INCOME) APARTMENT BUILDING - TYPE IIIA OVER TWO LEVEL BASEMENTS OF ENCLOSED PARKING GARAGE - TYPE IA. FIRE SPRINKLER NFPA13 - SEE COMMENTS.
Permit Issued
Issued on 4/5/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2016 APPLICANT
Assigned to Plan Check Engineer 5/5/2016 MOURAD AZIZ
Corrections Issued 5/25/2016 MOURAD AZIZ
Quality Review Completed 5/26/2016 STEVEN KIM
Building Plans Picked Up 8/4/2016 APPLICANT
Disabled Access Plans Picked Up 8/4/2016 APPLICANT
Green Plans Picked Up 8/4/2016 APPLICANT
Applicant returned to address corrections 3/28/2017 MOURAD AZIZ
Applicant returned to address corrections 5/16/2017 MOURAD AZIZ
Applicant returned to address corrections 6/9/2017 MOURAD AZIZ
Applicant returned to address corrections 12/12/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 12/21/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/3/2018 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/27/2018 ALEXANDER SBARDELLATI
Plan Check Approved 4/4/2018 ALEXANDER SBARDELLATI
Issued 4/5/2018 LADBS
TCO Issued (Expire Date: 12-06-2022) 6/9/2022 HENRY BAGHDASSARIAN
CofO in Progress 12/27/2022 DERRICK SPENCER
CofO in Progress 12/27/2022 DERRICK SPENCER
Permit Finaled 12/27/2022 HENRY BAGHDASSARIAN
CofO Issued 12/27/2022 HENRY BAGHDASSARIAN
Permit Finaled 12/27/2022 HENRY BAGHDASSARIAN

Permit Application Clearance Information

GPI Written Notices Cleared 5/10/2016 MOURAD AZIZ
Grading Pre-Inspection Cleared 5/10/2016 MOURAD AZIZ
Address approval Cleared 1/3/2017 HUGO RICO
Highway dedication Cleared 1/3/2017 HUGO RICO
Eng Process Fee Ord 176,300 Cleared 1/26/2017 CELINA MORENO
Fire Marshall Fire Life Safety Cleared 6/15/2017 ANDREW KO
DAS Clearance Cleared 6/16/2017 FARUK SEZER
Hydrant and Access approval Cleared 6/19/2017 ROBERT DUFF
Tract Map conditions Cleared 6/22/2017 RICK TORRES
ZA Case Cleared 6/22/2017 RICK TORRES
ZA Case Cleared 6/22/2017 RICK TORRES
ZA Case Cleared 6/22/2017 RICK TORRES
ZI Cleared 6/22/2017 RICK TORRES
Housing density bonus Cleared 8/29/2017 RICHARD TRUONG
Sewer availability Cleared 8/29/2017 HISASHI KOBAYAKAWA
Frnt yard landscape/Water mgmt Cleared 11/9/2017 RICK TORRES
Miscellaneous Cleared 11/9/2017 RICK TORRES
Miscellaneous Cleared 11/9/2017 RICK TORRES
Miscellaneous Cleared 11/9/2017 RICK TORRES
Miscellaneous Cleared 11/9/2017 RICK TORRES
Opn space landscape/Water mgmt Cleared 11/9/2017 RICK TORRES
Green Code Cleared 11/14/2017 MICHAEL AYERS
Low Impact Development Cleared 12/1/2017 IDA MEISAMI-FARD
Specific Plan Cleared 1/23/2018 EDER ROMERO
Construction near power lines Cleared 2/20/2018 ERNEST FRESQUEZ
Building over 3-story or 36-ft Cleared 3/13/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/13/2018 CALOSHA APPROVED
Permit Cleared 3/29/2018 OSCAR GUTIERREZ
Roof/Waste drainage to street Cleared 4/2/2018 CHRISTOPHER LAW
Work Adjacent to Public Way Cleared 4/4/2018 CHIU TAM

Contact Information

Architect Hefner, Charles David; Lic. No.: C23963 28378 ROADSIDE DRIVE      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,
Engineer Almalla, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Babayan, Raffi Samuel; Lic. No.: C72168 1140 N COLUMBUS AVE 112      GLENDALE, CA 91202
Engineer Zweigler, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/15/2018 Partial Inspection TONY HARTONO
Pre-Inspection 8/15/2018 Partial Inspection TONY HARTONO
Deputy Reinf. Concrete 9/7/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 12/19/2018 Corrections Issued TONY HARTONO
Footing/Foundation/Slab 1/8/2019 Not Ready for Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 1/10/2019 Not Ready for Inspection TONY HARTONO
Footing/Foundation/Slab 1/11/2019 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 2/25/2019 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 3/1/2019 Partial Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 3/5/2019 Not Ready for Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 3/11/2019 Partial Approval JASON BORUTA
Footing/Foundation/Slab 3/11/2019 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 3/21/2019 Partial Approval JASON BORUTA
Excavation/Setback/Form/Re-Bar 4/1/2019 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 4/3/2019 Approved TONY HARTONO
Deputy Shotcrete 4/3/2019 Approved TONY HARTONO
Footing/Foundation/Slab 4/8/2019 Partial Approval JASON BORUTA
Deputy Reinf. Concrete 4/24/2019 Approved TONY HARTONO
Footing/Foundation/Slab 5/1/2019 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 5/13/2019 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 5/14/2019 Partial Approval TONY HARTONO
Masonry Wall/Backfill 5/15/2019 Partial Approval TONY HARTONO
Green Building Rough 6/27/2019 Not Ready for Inspection TONY HARTONO
Reinforced Concrete Frame 6/27/2019 Partial Inspection TONY HARTONO
Verify Sprinkler Sign Off 6/27/2019 Not Ready for Inspection TONY HARTONO
Footing/Foundation/Slab 6/28/2019 Not Ready for Inspection DERRICK SPENCER
Reinforced Masonry Frame 7/1/2019 No Access for Inspection TONY HARTONO
Footing/Foundation/Slab 7/8/2019 Partial Inspection TONY HARTONO
Structural Steel Frame 7/8/2019 Partial Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 7/9/2019 Partial Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 7/12/2019 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 7/15/2019 Partial Approval DERRICK SPENCER
Green Building Rough 7/22/2019 Not Ready for Inspection TONY HARTONO
Reinforced Concrete Frame 7/22/2019 Not Ready for Inspection TONY HARTONO
Verify Sprinkler Sign Off 7/22/2019 Not Ready for Inspection TONY HARTONO
Footing/Foundation/Slab 7/24/2019 Partial Inspection TONY HARTONO
Green Building Rough 7/25/2019 Not Ready for Inspection TONY HARTONO
Reinforced Concrete Frame 7/25/2019 Partial Approval TONY HARTONO
Verify Sprinkler Sign Off 7/25/2019 Not Ready for Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 7/30/2019 Partial Approval TONY HARTONO
Footing/Foundation/Slab 9/23/2019 Partial Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 9/24/2019 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 9/27/2019 Conditional Approval TONY HARTONO
Footing/Foundation/Slab 10/9/2019 Partial Inspection TONY HARTONO
Wood Frame 11/27/2019 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 12/3/2019 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 1/8/2020 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 1/9/2020 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 1/27/2020 Conditional Approval JEFF BYTHEWAY
Deputy Wood Construction 1/28/2020 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 2/6/2020 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 2/7/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/11/2020 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/11/2020 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/12/2020 Approved JEFF BYTHEWAY
Deputy Wood Construction 2/19/2020 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Partial Approval JEFF BYTHEWAY
Green Building Rough 2/20/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 2/20/2020 Not Ready for Inspection JEFF BYTHEWAY
Verify Sprinkler Sign Off 2/20/2020 Approved JEFF BYTHEWAY
Green Building Rough 3/3/2020 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 3/3/2020 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 3/6/2020 Approved TED RIES
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 3/23/2020 Approved JEFF BYTHEWAY
Structural Steel Frame 3/24/2020 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 3/26/2020 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 4/1/2020 Approved JEFF BYTHEWAY
Wood Frame 4/3/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 4/8/2020 Partial Approval JEFF BYTHEWAY
Pre-Inspection 4/9/2020 Approved JEFF BYTHEWAY
Wood Frame 4/16/2020 Not Ready for Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 4/20/2020 Conditional Approval SORIN CIRSTOIU
Deputy Wood Construction 5/26/2020 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 6/4/2020 Not Ready for Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 6/9/2020 Partial Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 6/12/2020 Partial Inspection JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval JEFF BYTHEWAY
Insulation 6/30/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 7/2/2020 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 7/14/2020 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 7/21/2020 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 7/22/2020 Partial Approval JEFF BYTHEWAY
Insulation 7/22/2020 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 7/22/2020 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 7/24/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 7/28/2020 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 7/30/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 7/30/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/4/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/6/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/10/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/11/2020 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 8/11/2020 Partial Approval JEFF BYTHEWAY
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Not Ready JEFF BYTHEWAY
Drywall Nailing 8/18/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 8/20/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 9/2/2020 Not Ready for Inspection DERRICK SPENCER
Wood Frame 9/2/2020 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Approved DERRICK SPENCER
Wood Frame 9/9/2020 Not Ready for Inspection DERRICK SPENCER
Wood Frame 9/14/2020 Partial Inspection SORIN CIRSTOIU
Insulation 9/16/2020 Partial Approval SORIN CIRSTOIU
Wood Frame 9/16/2020 Partial Approval SORIN CIRSTOIU
Insulation 9/18/2020 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 9/22/2020 Partial Approval JOHN DODGE
Insulation 9/22/2020 Partial Approval JOHN DODGE
Wood Frame 9/22/2020 Not Ready for Inspection JOHN DODGE
Interior/Exterior Lathing 9/25/2020 Approved DERRICK SPENCER
Drywall Nailing 10/8/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 10/20/2020 Partial Approval JOHN DODGE
Insulation 10/20/2020 Partial Approval JOHN DODGE
Drywall Nailing 10/21/2020 Partial Approval DERRICK SPENCER
Drywall Nailing 10/23/2020 Partial Approval JOHN DODGE
Insulation 10/23/2020 Partial Inspection JOHN DODGE
Drywall Nailing 10/27/2020 Partial Approval JEFF BYTHEWAY
Insulation 10/27/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 10/28/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 10/28/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 10/29/2020 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 11/4/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 11/18/2020 Partial Approval JEFF BYTHEWAY
Interior/Exterior Lathing 12/1/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 12/1/2020 Approved JEFF BYTHEWAY
Insulation 12/7/2020 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 12/18/2020 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 1/12/2021 Partial Approval NICK LAROCCA
Drywall Nailing 2/9/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 2/22/2021 Partial Approval JEFF BYTHEWAY
Drywall Nailing 3/1/2021 Partial Approval JEFF BYTHEWAY
Special/Order Compliance 3/16/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/19/2021 Partial Inspection JEFF BYTHEWAY
Masonry Wall/Backfill 4/19/2021 Approved JEFF BYTHEWAY
Drywall Nailing 5/3/2021 Approved JEFF BYTHEWAY
Deputy Steel/Welding 5/12/2021 Approved JEFF BYTHEWAY
Masonry Wall/Backfill 5/24/2021 Partial Inspection JEFF BYTHEWAY
Structural Steel Frame 6/8/2021 Partial Inspection JEFF BYTHEWAY
Final 1/4/2022 Not Ready for Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 1/4/2022 Approved JEFF BYTHEWAY
Green Building Final 1/4/2022 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 1/4/2022 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 1/4/2022 Approved JEFF BYTHEWAY
SGSOV-Seismic Gas S/O Valve 1/4/2022 SGSOV Not Ready JEFF BYTHEWAY
Smoke Detectors 1/4/2022 Approved JEFF BYTHEWAY
Final 5/17/2022 Not Ready for Inspection JEFF BYTHEWAY
Green Building Final 5/17/2022 Not Ready for Inspection JEFF BYTHEWAY
SGSOV-Seismic Gas S/O Valve 5/17/2022 SGSOV Approved JEFF BYTHEWAY
Green Building Final 6/2/2022 Approved JEFF BYTHEWAY
Special/Order Compliance 6/2/2022 Not Ready for Inspection JEFF BYTHEWAY
Final 6/3/2022 OK for TCO JEFF BYTHEWAY
Special/Order Compliance 6/3/2022 Approved JEFF BYTHEWAY
Final 8/11/2022 Corrections Issued JEFF BYTHEWAY
Special/Order Compliance 8/16/2022 Partial Inspection JEFF BYTHEWAY
Drywall Nailing 9/7/2022 Partial Approval JEFF BYTHEWAY
Final 9/13/2022 Corrections Issued JEFF BYTHEWAY
Drywall Nailing 9/15/2022 Partial Approval JEFF BYTHEWAY
Posting Pre-Inspection 9/15/2022 Approved JEFF BYTHEWAY
Special/Order Compliance 9/15/2022 Approved JEFF BYTHEWAY
Special/Order Compliance 11/9/2022 Approved DERRICK SPENCER
Final 11/16/2022 Not Ready for Inspection DERRICK SPENCER
Final 12/14/2022 OK to Issue CofO DERRICK SPENCER