12417 W HAMLIN ST 91606
Certificate Information: 12417 W HAMLIN ST 91606
- Application / Permit
- 16010-20000-01375
- Plan Check / Job No.
- B16VN04475
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) TWO STORY ACCESSORY DWELLING UNIT W/ ATTACHED GARAGE PER AB 2299 AND SB 1069.
- Permit Issued
- Issued on 9/25/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2016 | JEROME MAGAT PALMA |
| Plans on Hold | 5/11/2016 | STEVEN KIM |
| Green Plans Picked Up | 7/20/2016 | APPLICANT |
| Hold Released | 11/18/2016 | TIEN JEN WANG |
| Corrections Issued | 11/21/2016 | JEROME MAGAT PALMA |
| Quality Review Completed | 11/23/2016 | MOURAD AZIZ |
| Building Plans Picked Up | 11/30/2016 | APPLICANT |
| Plan Check Approved | 9/5/2017 | JEROME MAGAT PALMA |
| Issued | 9/25/2017 | LADBS |
| CofO in Progress | 12/4/2020 | BRENDAN LOONEY |
| CofO Issued | 3/10/2021 | DANIEL ORRANTE |
| Permit Finaled | 3/10/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2017 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/7/2017 | JOHN DALLAS |
| Permit | Cleared | 3/7/2017 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/7/2017 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 3/10/2017 | RYAN HUDSON |
| Address approval | Cleared | 8/29/2017 | EDUARDO PEDROZA |
| Green Code | Cleared | 8/29/2017 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 8/29/2017 | EDUARDO PEDROZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ostowari, Sohrab; Lic. No.: C41014 | 7012 HELMSDALE RD WEST HILLS, CA 91307 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/13/2018 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 7/6/2018 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2018 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2018 | Partial Approval | GREG ALLTON |
| BUILDING-Rough-Frame | 10/11/2018 | Conditional Approval | GREG ALLTON |
| Green Building Rough | 10/11/2018 | Not Ready for Inspection | GREG ALLTON |
| MERV13>=Rough | 10/11/2018 | Approved | GREG ALLTON |
| Rough-Elec/Plmb/HVAC | 10/11/2018 | Partial Approval | GREG ALLTON |
| Verify Sprinkler Sign Off | 10/11/2018 | Not Ready for Inspection | GREG ALLTON |
| ELECTRICAL-Rough | 10/15/2018 | Approved | GREG ALLTON |
| HVAC-Rough | 10/15/2018 | Approved | GREG ALLTON |
| Rough-Elec/Plmb/HVAC | 10/15/2018 | Approved | GREG ALLTON |
| Insulation | 10/23/2018 | Approved | GREG ALLTON |
| Interior/Exterior Lathing | 10/23/2018 | Partial Approval | GREG ALLTON |
| Drywall Nailing | 10/31/2018 | Approved | GREG ALLTON |
| Green Building Rough | 10/31/2018 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 5/20/2019 | Not Ready for Inspection | GREG ALLTON |
| Final | 5/20/2019 | Not Ready for Inspection | GREG ALLTON |
| Green Building Final | 5/20/2019 | Not Ready for Inspection | GREG ALLTON |
| MERV13>=Final | 5/20/2019 | Approved | GREG ALLTON |
| SGSOV-Seismic Gas S/O Valve | 5/20/2019 | SGSOV Approved | GREG ALLTON |
| Service/Power Release | 5/20/2019 | Not Ready for Inspection | GREG ALLTON |
| Smoke Detectors | 5/20/2019 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 7/9/2019 | Approved | GREG ALLTON |
| Final | 7/9/2019 | Not Ready for Inspection | GREG ALLTON |
| Green Building Final | 7/9/2019 | Approved | GREG ALLTON |
| Service/Power Release | 7/9/2019 | Not Ready for Inspection | GREG ALLTON |
| Verify Sprinkler Sign Off | 7/9/2019 | Approved | GREG ALLTON |
| Final | 7/29/2019 | Not Ready for Inspection | GREG ALLTON |
| Service/Power Release | 7/29/2019 | Not Ready for Inspection | GREG ALLTON |
| Final | 3/17/2020 | Not Ready for Inspection | GREG ALLTON |
| Service/Power Release | 3/17/2020 | Conditional Approval | GREG ALLTON |
| Final | 9/21/2020 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 9/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 10/13/2020 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 10/13/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/27/2020 | Conditional Approval | BRENDAN LOONEY |
| Service/Power Release | 10/27/2020 | Approved | BRENDAN LOONEY |
| Final | 12/2/2020 | Conditional Approval | BRENDAN LOONEY |
| Final | 12/4/2020 | OK to Issue CofO | BRENDAN LOONEY |