1834 S PANDORA AVE 2 90025

Certificate Information: 1834 S PANDORA AVE 2 90025

Application / Permit
16010-20000-00874
Plan Check / Job No.
B16VN02952
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD WITH ATTACHED GARAGE. SMALL LOT SUBDIVISION PURSUANT TO VESTING TENENATIVE TRACT MAP NO. AA-2016-702-PMLA-SL. A CERTIFICATE OF OCCUPANCY (TEMP. OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
Permit Issued
Issued on 7/18/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2016 APPLICANT
Assigned to Plan Check Engineer 4/7/2016 RODNEY SAMIIAN
Green Plans Picked Up 4/11/2016 APPLICANT
Corrections Issued 4/18/2016 RODNEY SAMIIAN
Quality Review Completed 4/19/2016 STEVEN KIM
Building Plans Picked Up 4/25/2016 APPLICANT
Applicant returned to address corrections 3/15/2017 RODNEY SAMIIAN
Applicant returned to address corrections 5/18/2017 RODNEY SAMIIAN
Applicant returned to address corrections 6/16/2017 RODNEY SAMIIAN
Plan Check Approved 6/28/2017 RODNEY SAMIIAN
Issued 7/18/2017 LADBS
CofO in Progress 6/16/2020 MATT KELLERMAN
CofO in Progress 6/16/2020 MATT KELLERMAN
Permit Finaled 6/17/2020 VINCENT COTTON
CofO Issued 6/17/2020 VINCENT COTTON
Permit Finaled 6/17/2020 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/14/2017 JOHN LIN
Hydrant and Access approval Cleared 3/14/2017 JOHN DALLAS
Green Code Cleared 3/16/2017 MICHAEL AYERS
Address approval Cleared 4/14/2017 CHEN ZHANG
Permit Cleared 4/14/2017 CHEN ZHANG
Sewer availability Cleared 5/12/2017 ADRIAN SANCHEZ
Miscellaneous Cleared 5/25/2017 SARAH GOLDMAN
ZI Cleared 5/25/2017 SARAH GOLDMAN
Highway dedication Cleared 5/26/2017 ROCHELLE DUNGCA
Low Impact Development Cleared 5/26/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 5/26/2017 ROCHELLE DUNGCA
Specific Plan Cleared 5/31/2017 EILEEN HUNT
Miscellaneous Cleared 6/1/2017 CHEN ZHANG
Frnt yard landscape/Water mgmt Cleared 6/7/2017 NORALI MARTINEZ
Miscellaneous Cleared 6/7/2017 NORALI MARTINEZ

Contact Information

Contractor Wjk Construction And Development; Lic. No.: 1005728-B 16520 BAKE PARKWAY SUITE 105      IRVINE, CA 92618
Engineer Kim, Paul Sungkyo; Lic. No.: GE2066 21266 E SUNDANCE ST      WALNUT, CA 91789
Engineer Morris, Kyle Byron; Lic. No.: C72911 54 SANDPIPER      IRVINE, CA 92604
Engineer Pukkanasut, Jirayus; Lic. No.: C73728 1000 S COAST DRIVE #A204      COSTA MESA, CA 92626

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2017 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 9/26/2017 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/29/2017 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/29/2017 Partial Approval CHRISTOPHER WILSON
METHANE-Subgrade 10/6/2017 Partial Approval CHRISTOPHER WILSON
Deputy Methane Barrier 10/11/2017 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/13/2017 Corrections Issued CHRISTOPHER WILSON
METHANE-Barrier 10/13/2017 Corrections Issued CHRISTOPHER WILSON
METHANE-Subgrade 10/13/2017 Corrections Issued CHRISTOPHER WILSON
Deputy Steel/Welding 10/23/2017 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 10/23/2017 Corrections Issued CHRISTOPHER WILSON
METHANE-Barrier 10/23/2017 Partial Inspection CHRISTOPHER WILSON
METHANE-Subgrade 10/23/2017 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 10/25/2017 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 10/25/2017 Partial Inspection CHRISTOPHER WILSON
METHANE-Barrier 10/25/2017 Partial Inspection CHRISTOPHER WILSON
METHANE-Rough 10/25/2017 Partial Inspection CHRISTOPHER WILSON
METHANE-Subgrade 10/25/2017 Partial Inspection CHRISTOPHER WILSON
Structural Steel Frame 10/25/2017 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/25/2017 Partial Inspection CHRISTOPHER WILSON
Deputy Wood Construction 11/1/2017 Partial Approval CHRISTOPHER WILSON
Wood Frame 11/2/2017 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/7/2017 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/13/2017 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/17/2017 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 11/20/2017 Partial Approval CHRISTOPHER WILSON
Wood Frame 11/20/2017 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/22/2017 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/14/2017 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/22/2017 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/29/2017 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/10/2018 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/12/2018 Partial Approval CHRISTOPHER WILSON
Insulation 1/17/2018 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/29/2018 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/2/2018 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/9/2018 Partial Approval ANTHONY ANDERSON
ELECTRICAL-Rough 2/21/2018 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/21/2018 Partial Approval THOMAS FINNILA
PLUMBING-Rough 2/21/2018 Not Ready for Inspection THOMAS FINNILA
Insulation 5/4/2018 Order to Comply Issued THOMAS FINNILA
Rough-Elec/Plmb/HVAC 6/8/2018 Partial Approval THOMAS FINNILA
HVAC-Rough 6/12/2018 No Access for Inspection ROBERT VORHIS
PLUMBING-Rough 6/12/2018 No Access for Inspection ROBERT VORHIS
PLUMBING-Rough 6/15/2018 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/21/2018 Partial Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/2/2018 Partial Inspection THOMAS FINNILA
Wood Frame 7/9/2018 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 7/19/2018 Partial Approval ROBERT VORHIS
Interior/Exterior Lathing 7/25/2018 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/2/2018 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/6/2018 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 8/10/2018 Partial Inspection THOMAS FINNILA
PLUMBING-Rough 8/10/2018 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 8/16/2018 Partial Approval JOHN LUMB
HVAC-Final 8/17/2018 Partial Approval JOHN LUMB
PLUMBING-Final 8/17/2018 Approved JOHN LUMB
ELECTRICAL-Rough 8/23/2018 Approved JOHN LUMB
HVAC-Rough 8/23/2018 Partial Approval JOHN LUMB
Wood Frame 8/23/2018 Not Ready for Inspection JOHN LUMB
BUILDING-Rough-Frame 8/29/2018 Conditional Approval JOHN LUMB
Green Building Rough 8/29/2018 Approved JOHN LUMB
HVAC-Rough 8/29/2018 Approved JOHN LUMB
METHANE-Rough 8/29/2018 Approved JOHN LUMB
Verify Sprinkler Sign Off 8/29/2018 Approved JOHN LUMB
BUILDING-Rough-Frame 9/13/2018 Approved JOHN LUMB
Insulation 9/19/2018 Approved JOHN LUMB
Interior/Exterior Lathing 9/25/2018 Approved JOHN LUMB
Drywall Nailing 9/28/2018 Not Ready for Inspection JOHN LUMB
Drywall Nailing 10/5/2018 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 10/18/2018 Corrections Issued CARLOS MATAMOROS
Drywall Nailing 10/22/2018 Approved CARLOS MATAMOROS
ELECTRICAL-Final 1/2/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Service/Power Release 1/2/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 1/27/2020 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 1/27/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Gas Test 1/29/2020 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 1/29/2020 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 2/5/2020 Approved GERMAN RODRIGUEZ MENDOZA
Service/Power Release 3/12/2020 Approved GERMAN RODRIGUEZ MENDOZA
Service/Power Release 4/17/2020 Approved GERMAN RODRIGUEZ MENDOZA
Final 4/28/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 4/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 4/28/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 4/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 4/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 4/28/2020 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 4/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
Structural Steel Frame 4/28/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Final 5/1/2020 OK to Issue CofO GERMAN RODRIGUEZ MENDOZA
Green Building Final 5/1/2020 Approved GERMAN RODRIGUEZ MENDOZA
Structural Steel Frame 5/1/2020 Approved GERMAN RODRIGUEZ MENDOZA
Service/Power Release 5/21/2020 Approved KENNETH NAGLE