Excavation/Setback/Form/Re-Bar
|
9/26/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
9/26/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/29/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
9/29/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
METHANE-Subgrade
|
10/6/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Methane Barrier
|
10/11/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
10/13/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
METHANE-Barrier
|
10/13/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
METHANE-Subgrade
|
10/13/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
10/23/2017
|
Approved
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
10/23/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
METHANE-Barrier
|
10/23/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
METHANE-Subgrade
|
10/23/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
10/25/2017
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
10/25/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
METHANE-Barrier
|
10/25/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
METHANE-Rough
|
10/25/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
METHANE-Subgrade
|
10/25/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
10/25/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
10/25/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
11/1/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
11/2/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/7/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/13/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/17/2017
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
11/20/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
11/20/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
11/22/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/22/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/29/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/10/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/12/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
1/17/2018
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/29/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/2/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/9/2018
|
Partial Approval
|
ANTHONY ANDERSON
|
|
ELECTRICAL-Rough
|
2/21/2018
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/21/2018
|
Partial Approval
|
THOMAS FINNILA
|
|
PLUMBING-Rough
|
2/21/2018
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
Insulation
|
5/4/2018
|
Order to Comply Issued
|
THOMAS FINNILA
|
|
Rough-Elec/Plmb/HVAC
|
6/8/2018
|
Partial Approval
|
THOMAS FINNILA
|
|
HVAC-Rough
|
6/12/2018
|
No Access for Inspection
|
ROBERT VORHIS
|
|
PLUMBING-Rough
|
6/12/2018
|
No Access for Inspection
|
ROBERT VORHIS
|
|
PLUMBING-Rough
|
6/15/2018
|
Conditional Approval
|
THOMAS FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/21/2018
|
Partial Inspection
|
THOMAS FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2018
|
Partial Inspection
|
THOMAS FINNILA
|
|
Wood Frame
|
7/9/2018
|
Partial Approval
|
THOMAS FINNILA
|
|
Interior/Exterior Lathing
|
7/19/2018
|
Partial Approval
|
ROBERT VORHIS
|
|
Interior/Exterior Lathing
|
7/25/2018
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
PLUMBING-Rough
|
8/2/2018
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
PLUMBING-Rough
|
8/6/2018
|
Corrections Issued
|
THOMAS FINNILA
|
|
ELECTRICAL-Rough
|
8/10/2018
|
Partial Inspection
|
THOMAS FINNILA
|
|
PLUMBING-Rough
|
8/10/2018
|
Conditional Approval
|
THOMAS FINNILA
|
|
Interior/Exterior Lathing
|
8/16/2018
|
Partial Approval
|
JOHN LUMB
|
|
HVAC-Final
|
8/17/2018
|
Partial Approval
|
JOHN LUMB
|
|
PLUMBING-Final
|
8/17/2018
|
Approved
|
JOHN LUMB
|
|
ELECTRICAL-Rough
|
8/23/2018
|
Approved
|
JOHN LUMB
|
|
HVAC-Rough
|
8/23/2018
|
Partial Approval
|
JOHN LUMB
|
|
Wood Frame
|
8/23/2018
|
Not Ready for Inspection
|
JOHN LUMB
|
|
BUILDING-Rough-Frame
|
8/29/2018
|
Conditional Approval
|
JOHN LUMB
|
|
Green Building Rough
|
8/29/2018
|
Approved
|
JOHN LUMB
|
|
HVAC-Rough
|
8/29/2018
|
Approved
|
JOHN LUMB
|
|
METHANE-Rough
|
8/29/2018
|
Approved
|
JOHN LUMB
|
|
Verify Sprinkler Sign Off
|
8/29/2018
|
Approved
|
JOHN LUMB
|
|
BUILDING-Rough-Frame
|
9/13/2018
|
Approved
|
JOHN LUMB
|
|
Insulation
|
9/19/2018
|
Approved
|
JOHN LUMB
|
|
Interior/Exterior Lathing
|
9/25/2018
|
Approved
|
JOHN LUMB
|
|
Drywall Nailing
|
9/28/2018
|
Not Ready for Inspection
|
JOHN LUMB
|
|
Drywall Nailing
|
10/5/2018
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Drywall Nailing
|
10/18/2018
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Drywall Nailing
|
10/22/2018
|
Approved
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
1/2/2020
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Service/Power Release
|
1/2/2020
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Final
|
1/27/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
HVAC-Final
|
1/27/2020
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Gas Test
|
1/29/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Final
|
1/29/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
HVAC-Final
|
2/5/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Service/Power Release
|
3/12/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Service/Power Release
|
4/17/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Final
|
4/28/2020
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Footing/Foundation/Slab
|
4/28/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Green Building Final
|
4/28/2020
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Barrier
|
4/28/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Subgrade
|
4/28/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
4/28/2020
|
SGSOV Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Smoke Detectors
|
4/28/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Structural Steel Frame
|
4/28/2020
|
Partial Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Final
|
5/1/2020
|
OK to Issue CofO
|
GERMAN RODRIGUEZ MENDOZA
|
|
Green Building Final
|
5/1/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Structural Steel Frame
|
5/1/2020
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Service/Power Release
|
5/21/2020
|
Approved
|
KENNETH NAGLE
|