10224 N HILLHAVEN AVE 91042

Certificate Information: 10224 N HILLHAVEN AVE 91042

Application / Permit
16010-20000-00870
Plan Check / Job No.
B16VN02946
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 131'-8" X 24'-9", 3-STORY (TYPE IIIA) AND BASEMENT (TYPE IA), 4-UNIT APARTMENT WITH ATTACHED GARAGE. FIRE SPRINKLERS REQ'D THROUGH-OUT. (SEE COMMENTS)
Permit Issued
Issued on 3/6/2019
Issuing Office
Valley
Current Status
Issued on 3/6/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/7/2016 APPLICANT
Assigned to Plan Check Engineer 3/31/2016 ALEXANDER SBARDELLATI
Disabled Access Plans Picked Up 4/5/2016 APPLICANT
Corrections Issued 4/7/2016 ALEXANDER SBARDELLATI
Quality Review Completed 4/8/2016 STEVEN KIM
Building Plans Picked Up 4/8/2016 APPLICANT
Green Plans Picked Up 4/11/2016 APPLICANT
Applicant returned to address corrections 6/2/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 6/20/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 7/8/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 7/19/2016 ALEXANDER SBARDELLATI
Applicant returned to address corrections 1/26/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/22/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 6/26/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 7/11/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 7/27/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 9/6/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 9/29/2017 ALEXANDER SBARDELLATI
Plan Check Approved 10/18/2017 ALEXANDER SBARDELLATI
Plan Check Approved 9/5/2018 ALEXANDER SBARDELLATI
Issued 3/6/2019 LADBS

Permit Application Clearance Information

GPI Written Notices Cleared 4/4/2016 ALEXANDER SBARDELLATI
Grading Pre-Inspection Cleared 4/4/2016 ALEXANDER SBARDELLATI
Address approval Cleared 5/23/2016 RICHARD SOUTHERLAND
CPC Cleared 5/23/2016 RICK TORRES
Highway dedication Cleared 5/23/2016 RICHARD SOUTHERLAND
Permit Cleared 5/23/2016 RICHARD SOUTHERLAND
Eng Process Fee Ord 176,300 Cleared 6/7/2016 ARMEN DERMENJIAN
Hydrant and Access approval Cleared 6/7/2016 JOHN DALLAS
Sewer availability Cleared 6/7/2016 ARMEN DERMENJIAN
Specific Plan Cleared 6/7/2016 TOM GLICK
Frnt yard landscape/Water mgmt Cleared 7/19/2016 DENNIS CHEW
Low Impact Development Cleared 7/21/2016 SAM NAVID
Roof/Waste drainage to street Cleared 7/21/2016 RICHARD SOUTHERLAND
Miscellaneous Cleared 7/11/2017 ALEXANDER SBARDELLATI
Green Code Cleared 9/1/2017 MICKEY YAMASHITA
DAS Clearance Cleared 9/6/2017 NORLITO MEDRANO
Fire Marshall Fire Life Safety Cleared 9/21/2017 OSCAR SALGADO JR

Contact Information

Architect Maly, Farzin; Lic. No.: C33731 PO BOX 57002      SHERMAN OAKS, CA 91413
Contractor Owner-Builder       ,
Engineer Basseri, Siavash; Lic. No.: C45487 1205 MAPLE ST      SANTA MONICA, CA 90405

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2019 No Access for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/25/2020 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 3/11/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/15/2021 No Access for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/30/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 4/15/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/16/2021 No Access for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 4/21/2021 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 6/17/2021 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/8/2021 Partial Approval JEFFREY DURAN
Masonry Wall/Backfill 10/25/2021 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 5/10/2022 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 5/16/2022 Corrections Issued ROBERT DAVIS
Masonry Wall/Backfill 6/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 6/6/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/29/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/29/2022 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/7/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/8/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 10/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/17/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 12/13/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 12/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/14/2023 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 5/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/18/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 5/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 5/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 5/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 6/14/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 6/27/2023 Corrections Issued DANNY RODRIGUEZ
Reinforced Masonry Frame 6/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/18/2023 No Access for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/19/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/21/2023 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 8/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 8/14/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/23/2023 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/24/2023 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/25/2023 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/25/2023 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 8/30/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/18/2023 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 10/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 10/13/2023 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 10/16/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 10/20/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/23/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/24/2023 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 11/17/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 11/17/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 11/17/2023 Partial Approval DANNY RODRIGUEZ
Structural Steel Frame 11/17/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/17/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 2/6/2024 No Access for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 No Access for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 12/5/2024 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 12/13/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/24/2025 Not Ready for Inspection GREGORY POMISH
Reinforced Masonry Frame 3/24/2025 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 3/24/2025 Not Ready for Inspection GREGORY POMISH
Green Building Rough 4/7/2025 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 4/7/2025 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/7/2025 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/7/2025 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Not Ready for Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Corrections Issued ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Partial Approval GREGORY POMISH
Green Building Rough 11/13/2025 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 11/13/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 11/13/2025 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 12/22/2025 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 1/21/2026 Partial Inspection JOHN KITCKO
Interior/Exterior Lathing 1/29/2026 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 2/2/2026 Conditional Approval JOHN KITCKO
Green Building Rough 3/27/2026 Not Ready for Inspection JOHN KITCKO
Insulation 3/27/2026 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 3/27/2026 Not Ready for Inspection JOHN KITCKO
Wood Frame 3/27/2026 Not Ready for Inspection JOHN KITCKO
Green Building Rough 4/1/2026 Not Ready for Inspection JOHN KITCKO
Insulation 4/1/2026 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 4/1/2026 Not Ready for Inspection JOHN KITCKO
Wood Frame 4/1/2026 Partial Approval JOHN KITCKO
Deputy Steel/Welding 4/27/2026 No Access for Inspection JOHN KITCKO
Deputy Steel/Welding 4/28/2026 Conditional Approval JOHN KITCKO