6100 W HORNER ST LOT 2 90035
Certificate Information: 6100 W HORNER ST LOT 2 90035
- Application / Permit
- 16010-20000-00727
- Plan Check / Job No.
- B16VN02430
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 4-STORY SFD W/ ATTACHED 2-CAR GARAGE (NFPA-13 FIRE SPRINKLERS THROUGHOUT) <<Small Lot Subdivision pursuant to Preliminary Parcel Map No. AA-2015-4510-PMLA. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded >>
- Permit Issued
- Issued on 12/19/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2016 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/31/2016 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/1/2016 | STEVEN KIM |
| Building Plans Picked Up | 4/5/2016 | APPLICANT |
| Green Plans Picked Up | 4/5/2016 | APPLICANT |
| Applicant returned to address corrections | 8/7/2017 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/11/2017 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/25/2017 | NILOOFAR MEHRAIN |
| Issued | 12/19/2018 | LADBS |
| CofO in Progress | 4/18/2023 | SCOTT FINNILA |
| Permit Finaled | 4/22/2023 | DEROLD HAUFF |
| CofO Issued | 4/22/2023 | DEROLD HAUFF |
| Permit Finaled | 4/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2016 | HOWARD COOPER |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2016 | RICHARD SOUTHERLAND |
| Miscellaneous | Cleared | 9/19/2016 | RICK TORRES |
| Sewer availability | Cleared | 9/19/2016 | RICHARD SOUTHERLAND |
| Green Code | Cleared | 9/20/2016 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 7/21/2017 | JOHN DALLAS |
| Permit | Cleared | 7/21/2017 | KENNETH PHAM |
| Miscellaneous | Cleared | 7/24/2017 | ZEMAMU GEBREWOLD |
| Low Impact Development | Cleared | 8/3/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 8/21/2017 | ZEMAMU GEBREWOLD |
Contact Information
| Architect | Brumer, Aaron Jason; Lic. No.: C30005 | 16757 MORRISON STREET ENCINO, CA 91436 |
| Contractor | Silver Star Construction Engineering Inc; Lic. No.: 971938-B | 1153 N BRAND BLVD GLENDALE, CA 91202 |
| Engineer | Onishi, Robert K; Lic. No.: S3705 | 14426 S RAYMOND AVE GARDENA, CA 90247 |
| Engineer | Pukkanasut, Jirayus; Lic. No.: C73728 | 1000 S COAST DRIVE #A204 COSTA MESA, CA 92626 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 4/22/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 4/22/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/13/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/13/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/14/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 5/14/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 5/14/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Deputy Methane Barrier | 5/15/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/21/2019 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 5/23/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/24/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 5/24/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/31/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 5/31/2019 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 5/31/2019 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/14/2019 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 6/14/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/15/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/15/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/12/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/12/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Structural Steel Frame | 8/26/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/24/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/24/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/4/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/5/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/13/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 11/19/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/2/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2019 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 12/6/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 12/17/2019 | Approved | SCOTT FINNILA |
| METHANE-Rough | 12/18/2019 | Approved | SCOTT FINNILA |
| HVAC-Rough | 1/22/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Insulation | 2/5/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 2/11/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/20/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/24/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/25/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/25/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/25/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 2/26/2020 | Partial Approval | SCOTT FINNILA |
| Insulation | 3/5/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/19/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/23/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/23/2020 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/1/2020 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/11/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 4/7/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/9/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 9/10/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/28/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/12/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/18/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/11/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/15/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/4/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 8/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 8/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/31/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/27/2022 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 2/9/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | SCOTT FINNILA |
| Final | 4/18/2023 | OK to Issue CofO | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/18/2023 | Approved | SCOTT FINNILA |