11974 W FOXBORO DR 90049
Certificate Information: 11974 W FOXBORO DR 90049
- Application / Permit
- 16010-20000-00618
- Plan Check / Job No.
- B16VN01969
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 68'-7" x 49'-6" NEW 2-STORY SINGLE FAMILY DWELLING WITH 34'-2" X 59'-9" BASEMENT AND ATTACHED GARAGE; BASEMENT INCLUDES REC ROOM, BEDROOM, 3/4 BATHROOM, AND LAUNDRY ROOM; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGH OUT
- Permit Issued
- Issued on 8/11/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2016 | SELLA BENYAMIN |
| Green Plans Picked Up | 3/1/2016 | APPLICANT |
| Corrections Issued | 3/2/2016 | SELLA BENYAMIN |
| Quality Review Completed | 3/2/2016 | CHON CHIO KUO |
| Building Plans Picked Up | 3/2/2016 | APPLICANT |
| Plan Check Approved | 4/28/2017 | SELLA BENYAMIN |
| Issued | 8/11/2017 | LADBS |
| CofO in Progress | 2/26/2021 | JOHN KIDWELL |
| Permit Finaled | 3/4/2021 | KENNETH NAGLE |
| CofO Issued | 3/4/2021 | KENNETH NAGLE |
| Permit Finaled | 3/4/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2016 | BRIAN KELLY |
| Hydrant and Access approval | Cleared | 3/3/2016 | JOHN CONNEALLY |
| Sewer availability | Cleared | 3/3/2016 | BRIAN KELLY |
| Low Impact Development | Cleared | 8/26/2016 | SAM NAVID |
| Permit | Cleared | 8/29/2016 | TAO YANG |
| Roof/Waste drainage to street | Cleared | 8/29/2016 | TAO YANG |
| Green Code | Cleared | 4/26/2017 | MICHAEL AYERS |
Contact Information
| Architect | Walters, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Levin, Vladimir; Lic. No.: C35001 | 207 N BOWLING GREEN WAY LOS ANGELES, CA 90049 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/2/2018 | Partial Inspection | VINCENT SCIPIONI |
| Pre-Inspection | 2/7/2019 | Approved | ANDREW NAVE |
| Pre-Inspection | 8/2/2019 | Partial Inspection | DANNY TOLENTINO |
| PLUMBING-Rough | 1/28/2020 | Corrections Issued | DANNY TOLENTINO |
| Underground Mechanical | 1/29/2020 | Partial Inspection | DANNY TOLENTINO |
| PLUMBING-Rough | 1/30/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 2/3/2020 | Corrections Issued | DANNY TOLENTINO |
| Footing/Foundation/Slab | 2/4/2020 | Partial Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 2/12/2020 | No Access for Inspection | DANNY TOLENTINO |
| Reinforced Concrete Frame | 2/18/2020 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/2/2020 | Partial Approval | DANNY TOLENTINO |
| Underground Mechanical | 4/2/2020 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Wood Construction | 6/4/2020 | Approved | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/9/2020 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/24/2020 | Corrections Issued | TIM CHRISTENSEN |
| PLUMBING-Rough | 6/24/2020 | Corrections Issued | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 6/26/2020 | Approved | TIM CHRISTENSEN |
| PLUMBING-Rough | 6/26/2020 | Approved | TIM CHRISTENSEN |
| HVAC-Rough | 6/30/2020 | Corrections Issued | ROBERT SHELLY |
| HVAC-Rough | 7/8/2020 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/9/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/9/2020 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 7/9/2020 | Approved | JOHN KIDWELL |
| Wood Frame | 7/9/2020 | Approved | JOHN KIDWELL |
| Drywall Nailing | 7/16/2020 | Approved | KENNETH NAGLE |
| Insulation | 7/16/2020 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 7/21/2020 | Corrections Issued | TIM CHRISTENSEN |
| Shower Pan | 7/21/2020 | Corrections Issued | TIM CHRISTENSEN |
| Gas Test | 7/24/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Interior/Exterior Lathing | 7/24/2020 | Approved | TIM CHRISTENSEN |
| Shower Pan | 7/24/2020 | Approved | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 11/5/2020 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 11/5/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/5/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 11/16/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Final | 11/16/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 11/16/2020 | Approved | KENNETH NAGLE |
| Green Building Final | 11/16/2020 | Not Ready for Inspection | KENNETH NAGLE |
| HVAC-Final | 11/16/2020 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Final | 11/16/2020 | Corrections Issued | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Approved | KENNETH NAGLE |
| Service/Power Release | 11/16/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Smoke Detectors | 11/16/2020 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 11/25/2020 | Approved | JOHN KIDWELL |
| Final | 2/22/2021 | Conditional Approval | JOHN KIDWELL |
| Green Building Final | 2/22/2021 | Approved | JOHN KIDWELL |
| Service/Power Release | 2/22/2021 | Approved | JOHN KIDWELL |
| Final | 2/26/2021 | OK to Issue CofO | JOHN KIDWELL |