2180 N STRADELLA ROAD 90077

Certificate Information: 2180 N STRADELLA ROAD 90077

Application / Permit
16010-20000-00585
Plan Check / Job No.
B16VN01854
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/BASEMENT AND ATT. GARAGE
Permit Issued
Issued on 6/15/2018
Issuing Office
Valley
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2016 APPLICANT
Assigned to Plan Check Engineer 3/10/2016 CHON CHIO KUO
Green Plans Picked Up 3/21/2016 APPLICANT
Corrections Issued 4/13/2016 CHON CHIO KUO
Quality Review Completed 4/13/2016 TIEN JEN WANG
Building Plans Picked Up 4/14/2016 APPLICANT
Applicant returned to address corrections 5/6/2016 CHON CHIO KUO
Applicant returned to address corrections 5/8/2017 CHON CHIO KUO
Applicant returned to address corrections 2/26/2018 CHON CHIO KUO
Applicant returned to address corrections 3/6/2018 CHON CHIO KUO
Applicant returned to address corrections 3/12/2018 CHON CHIO KUO
Applicant returned to address corrections 4/10/2018 CHON CHIO KUO
Applicant returned to address corrections 4/23/2018 CHON CHIO KUO
Plan Check Approved 6/1/2018 CHON CHIO KUO
Issued 6/15/2018 LADBS
CofO in Progress 1/12/2026 CHRISTOPHER WILSON
Permit Finaled 1/13/2026 RICHARD STEINBACH
CofO Issued 1/13/2026 RICHARD STEINBACH
Permit Finaled 1/13/2026 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/8/2017 YESENIA DIAZ
BHO/Hillside ordinance Cleared 5/8/2017 YESENIA DIAZ
BHO/Hillside ordinance Cleared 5/8/2017 YESENIA DIAZ
BHO/Hillside ordinance Cleared 5/8/2017 YESENIA DIAZ
Permit Cleared 5/8/2017 YESENIA DIAZ
Eng Process Fee Ord 176,300 Cleared 5/22/2017 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 5/22/2017 JOHN DALLAS
Sewer availability Cleared 5/22/2017 MARKOS PEREZ-BRAN
ZI Cleared 12/18/2017 HERMINIGILDO AGUSTIN
GPI Written Notices Cleared 2/26/2018 CHON CHIO KUO
Grading Pre-Inspection Cleared 2/26/2018 CHON CHIO KUO
Low Impact Development Cleared 3/15/2018 MARTIN FRAGOSO
Work Adjacent to Public Way Cleared 3/15/2018 KRISTEN LY
ZA Case Cleared 3/19/2018 STEVEN WECHSLER
ZA Case Cleared 3/19/2018 STEVEN WECHSLER
Green Code Cleared 3/23/2018 ROLLIN GETTLE III
Roof/Waste drainage to street Cleared 4/2/2018 KENNETH PHAM
Excavation more than 5-ft deep Cleared 4/10/2018 CALOSHA APPROVED

Contact Information

Architect Motamen, Azita; Lic. No.: C28112 16614 OAKVIEW COURT      ENCINO, CA 91436
Contractor K N D D Inc; Lic. No.: 794816-B 211 N SWALL DR      BEVERLY HILLS, CA 90211
Engineer Berkoz, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer De, Leon Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Minas, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/22/2019 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 6/3/2019 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 12/11/2019 Partial Inspection MATT KELLERMAN
Piling/Pier/Caisson 6/5/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/26/2020 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 6/26/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/16/2020 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 7/16/2020 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 7/22/2020 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 8/1/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/8/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 8/14/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 8/21/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 9/9/2020 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 9/11/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/17/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/6/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/6/2020 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 10/7/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/20/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/22/2020 Partial Approval CHRISTOPHER WILSON
Service/Power Release 11/2/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 11/10/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/13/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/13/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/2/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/22/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 12/22/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/15/2021 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Corrections Issued CHRISTOPHER WILSON
Verify Sprinkler Sign Off 4/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 4/8/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/12/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Partial Approval CHRISTOPHER WILSON
Green Building Rough 6/25/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/25/2021 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 10/15/2021 Conditional Approval CHRISTOPHER WILSON
Wood Frame 10/26/2021 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 11/30/2021 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 12/16/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 12/20/2021 Partial Inspection CLAYTON GRAHAM
Footing/Foundation/Slab 1/20/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/17/2022 Corrections Issued CHRISTOPHER WILSON
Wood Frame 5/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 5/20/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 5/26/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/27/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/27/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 6/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/14/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 6/16/2022 Approved CHRISTOPHER WILSON
HVAC-Rough 6/20/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 6/23/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 7/29/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 8/10/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 8/15/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/6/2022 Partial Approval CHRISTOPHER WILSON
Insulation 9/6/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/6/2022 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 9/7/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 9/15/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 9/19/2022 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/21/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 9/21/2022 Partial Approval CHRISTOPHER WILSON
Shower Pan 9/28/2022 Partial Approval CHRISTOPHER WILSON
Insulation 9/30/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/11/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 10/12/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/12/2022 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 11/3/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/4/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/4/2022 Corrections Issued CHRISTOPHER WILSON
Insulation 11/16/2022 Partial Approval CHRISTOPHER WILSON
Shower Pan 11/16/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 12/12/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/12/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 12/12/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/15/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 12/15/2022 Approved CHRISTOPHER WILSON
Insulation 1/3/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 1/10/2023 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 1/18/2023 Partial Approval CARLOS MATAMOROS
Drywall Nailing 2/24/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/22/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/22/2023 Approved CHRISTOPHER WILSON
Shower Pan 3/22/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 3/22/2023 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 4/11/2023 Partial Approval CHRISTOPHER WILSON
Shower Pan 4/11/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 4/24/2023 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 10/24/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/24/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/8/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 11/8/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 11/27/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 11/29/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 11/30/2023 Partial Approval CHRISTOPHER WILSON
Sewer 2/16/2024 Partial Approval CHRISTOPHER WILSON
Gas Test 3/27/2024 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 3/28/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 4/22/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 8/14/2024 Corrections Issued MICHAEL PELHAM
PLUMBING-Final 8/20/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 8/26/2024 Partial Approval SEAN HAUPT
ELECTRICAL-Final 9/3/2024 Approved MICHAEL PELHAM
Service/Power Release 9/3/2024 Approved MICHAEL PELHAM
HVAC-Final 11/27/2024 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 12/10/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 12/18/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 12/18/2024 Partial Approval CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Approved CHRISTOPHER WILSON
PLUMBING-Final 2/4/2025 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/6/2026 Approved CHRISTOPHER WILSON
Final 1/6/2026 OK to Issue CofO CHRISTOPHER WILSON
Footing/Foundation/Slab 1/6/2026 Approved CHRISTOPHER WILSON
Green Building Final 1/6/2026 Approved CHRISTOPHER WILSON
Green Building Rough 1/6/2026 Approved CHRISTOPHER WILSON
Smoke Detectors 1/6/2026 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/6/2026 Approved CHRISTOPHER WILSON