20226 W JUBILEE WAY 91326
Certificate Information: 20226 W JUBILEE WAY 91326
- Application / Permit
- 16010-20000-00329
- Plan Check / Job No.
- B16VN01289
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY SFD WITH ATTACH 3 CAR GARAGE_*STANDARD PLAN # 643 _ PLAN 5
- Permit Issued
- Issued on 3/18/2016
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 3/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2016 | APPLICANT |
| Green Plans Picked Up | 2/10/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2016 | HERNAN ARREOLA |
| Corrections Issued | 2/18/2016 | HERNAN ARREOLA |
| Quality Review Completed | 2/19/2016 | STEVEN KIM |
| Building Plans Picked Up | 2/22/2016 | APPLICANT |
| Plan Check Approved | 3/15/2016 | HERNAN ARREOLA |
| Issued | 3/18/2016 | LADBS |
| Permit Expired-Status Void | 4/18/2018 | APPLICANT |
| Re-Activate Permit | 4/25/2018 | DONALD SUNSERI |
| CofO in Progress | 10/18/2018 | DONALD SUNSERI |
| CofO Issued-Status Void | 10/18/2018 | DONALD SUNSERI |
| Permit Finaled-Status Void | 10/18/2018 | DONALD SUNSERI |
| Re-Activate Permit | 11/7/2019 | MICHAEL SMITH |
| Permit Finaled | 3/15/2021 | DONALD SUNSERI |
| CofO Corrected | 3/15/2021 | DONALD SUNSERI |
| Permit Finaled | 3/15/2021 | DONALD SUNSERI |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/26/2016 | AMMAR ELTAWIL |
| Address approval | Cleared | 3/8/2016 | ARMEN DERMENJIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2016 | ARMEN DERMENJIAN |
| Permit | Cleared | 3/8/2016 | ARMEN DERMENJIAN |
| Roof/Waste drainage to street | Cleared | 3/8/2016 | ARMEN DERMENJIAN |
| Sewer availability | Cleared | 3/8/2016 | ARMEN DERMENJIAN |
| Hydrant and Access approval | Cleared | 3/11/2016 | ROBERT DUFF |
| "T" removal | Cleared | 3/14/2016 | ANNA VIDAL |
| CPC | Cleared | 3/14/2016 | ANNA VIDAL |
| Miscellaneous | Cleared | 3/14/2016 | ANNA VIDAL |
| Miscellaneous | Cleared | 3/14/2016 | ANNA VIDAL |
| Miscellaneous | Cleared | 3/14/2016 | ANNA VIDAL |
| Miscellaneous | Cleared | 3/14/2016 | ANNA VIDAL |
| Specific Plan | Cleared | 3/14/2016 | ANNA VIDAL |
| Tract Map conditions | Cleared | 3/14/2016 | ANNA VIDAL |
| Tract Map conditions | Cleared | 3/14/2016 | ANNA VIDAL |
| ZA Case | Cleared | 3/14/2016 | ANNA VIDAL |
| ZA Case | Cleared | 3/14/2016 | ANNA VIDAL |
| GPI Written Notices | Cleared | 3/15/2016 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 3/15/2016 | HERNAN ARREOLA |
| Green Code | Cleared | 3/15/2016 | MICHAEL AYERS |
Contact Information
| Architect | Gorrill, Ernest Bernard; Lic. No.: C13407 | 419 E BAY ST COSTA MESA, CA 92627 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Kim, Kevin Chae; Lic. No.: C53821 | 2349 N CAMPUS AVENUE UPLAND, CA 91784 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Engineer | Wong, Ramon Roman Ii; Lic. No.: S2345 | 1800 E. 16TH STREET SANTA ANA, CA 92701 |
Inspector Information
| HENRY KIM, (818) 774-4334 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/25/2018 | Approved | DONALD SUNSERI |
| Footing/Foundation/Slab | 5/24/2018 | Conditional Approval | BRUCE ROZAK |
| Sewer | 6/1/2018 | Approved | BRUCE ROZAK |
| Underground Mechanical | 6/12/2018 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2018 | Partial Approval | BRUCE ROZAK |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2018 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2018 | Approved | BRUCE ROZAK |
| HVAC-Rough | 8/3/2018 | Approved | BRUCE ROZAK |
| ELECTRICAL-Rough | 8/6/2018 | Approved | BRUCE ROZAK |
| PLUMBING-Rough | 8/6/2018 | Approved | BRUCE ROZAK |
| BUILDING-Rough-Frame | 8/8/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Green Building Rough | 8/8/2018 | Approved | DONALD SUNSERI |
| Verify Sprinkler Sign Off | 8/8/2018 | Not Ready for Inspection | DONALD SUNSERI |
| BUILDING-Rough-Frame | 8/10/2018 | Approved | BRUCE ROZAK |
| Verify Sprinkler Sign Off | 8/10/2018 | Approved | BRUCE ROZAK |
| Interior/Exterior Lathing | 8/15/2018 | Not Ready for Inspection | BRUCE ROZAK |
| Drywall Nailing | 8/17/2018 | Approved | BRUCE ROZAK |
| Interior/Exterior Lathing | 8/17/2018 | Approved | BRUCE ROZAK |
| Gas Test | 8/30/2018 | Approved | DONALD SUNSERI |
| Service/Power Release | 8/30/2018 | Approved | DONALD SUNSERI |
| SGSOV-Seismic Gas S/O Valve | 9/7/2018 | SGSOV Approved | BRUCE ROZAK |
| HVAC-Final | 10/10/2018 | Approved | BRUCE ROZAK |
| PLUMBING-Final | 10/10/2018 | Approved | BRUCE ROZAK |
| ELECTRICAL-Final | 10/12/2018 | Approved | DONALD SUNSERI |
| Final | 10/12/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Footing/Foundation/Slab | 10/12/2018 | Approved | DONALD SUNSERI |
| Green Building Final | 10/12/2018 | Approved | DONALD SUNSERI |
| Smoke Detectors | 10/12/2018 | Approved | DONALD SUNSERI |
| Final | 10/16/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Final | 10/18/2018 | OK to Issue CofO | DONALD SUNSERI |