15012 W MOORPARK ST 2 91403
Certificate Information: 15012 W MOORPARK ST 2 91403
- Application / Permit
- 16010-20000-00046
- Plan Check / Job No.
- B16VN00276
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SFD/GARAGE AND ROOF DECK WITH ARCHITECTURAL OVERHANGS. SMALL LOT SUBDIVISION PURSUANT TO VESTING TENENATIVE TRACT MAP NO. 73725. A CERTIFICATE OF OCCUPANCY (TEMP. OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
- Permit Issued
- Issued on 7/3/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2016 | RODNEY SAMIIAN |
| Green Plans Picked Up | 2/11/2016 | APPLICANT |
| Corrections Issued | 2/25/2016 | RODNEY SAMIIAN |
| Quality Review Completed | 3/1/2016 | STEVEN KIM |
| Building Plans Picked Up | 3/1/2016 | APPLICANT |
| Applicant returned to address corrections | 3/17/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 5/6/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 5/11/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 5/18/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 5/31/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/3/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/8/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/13/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/27/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 7/27/2016 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 3/21/2017 | RODNEY SAMIIAN |
| Plan Check Approved | 3/21/2017 | RODNEY SAMIIAN |
| Issued | 7/3/2017 | LADBS |
| Permit Closed-Status Void | 10/1/2018 | DONALD SUNSERI |
| Re-Activate Permit | 10/4/2018 | DONALD SUNSERI |
| CofO in Progress | 5/22/2020 | JOSEPH SAGEN |
| Permit Finaled | 6/2/2020 | DONALD SUNSERI |
| CofO Issued | 6/2/2020 | DONALD SUNSERI |
| Permit Finaled | 6/2/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/20/2016 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2016 | ROBERT SAMONTE |
| Sewer availability | Cleared | 5/23/2016 | ROBERT SAMONTE |
| Green Code | Cleared | 6/3/2016 | MICHAEL AYERS |
| Address approval | Cleared | 6/27/2016 | HOWARD COOPER |
| Highway dedication | Cleared | 7/11/2016 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 7/11/2016 | LEE GUILBEAUX |
| Permit | Cleared | 7/11/2016 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/11/2016 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 9/8/2016 | TRACY WILLIAMS |
| Construction within easement | Cleared | 12/18/2016 | LUCIO FERRER |
| Low Impact Development | Cleared | 3/2/2017 | MICHAEL SCADUTO |
Contact Information
| Architect | Zeitlian, Hraztan S; Lic. No.: C28719 | 3324 GRAND VIEW BLVD LOS ANGELES, CA 90066 |
| Contractor | B M R Enterprises; Lic. No.: 901546-B | 5405 WILSHIRE BLVD SUITE 300 LOS ANGELES, CA 90036 |
| Engineer | Erdelyi, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2017 | Not Ready for Inspection | MICHAEL YOUNG |
| Excavation/Setback/Form/Re-Bar | 9/19/2017 | Partial Approval | DONALD SUNSERI |
| Deputy Reinf. Concrete | 11/2/2017 | Approved | DONALD SUNSERI |
| PLUMBING-Rough | 11/15/2017 | Not Ready for Inspection | BRUCE ROZAK |
| Underground Mechanical | 11/15/2017 | Approved | BRUCE ROZAK |
| Footing/Foundation/Slab | 12/26/2017 | Not Ready for Inspection | BRUCE ROZAK |
| Footing/Foundation/Slab | 1/2/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Footing/Foundation/Slab | 1/4/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 1/5/2018 | Approved | BRUCE ROZAK |
| Wood Frame | 1/22/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/26/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Wood Frame | 1/26/2018 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 1/29/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Wood Construction | 1/30/2018 | Conditional Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/31/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/6/2018 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 2/15/2018 | Approved | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2018 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 2/26/2018 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/1/2018 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/4/2018 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 4/4/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 4/4/2018 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/10/2018 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 4/10/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 4/10/2018 | Not Ready for Inspection | JOHN KIDWELL |
| Wood Frame | 4/10/2018 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/13/2018 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2018 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2018 | Partial Approval | DONALD SUNSERI |
| Interior/Exterior Lathing | 5/22/2018 | Partial Approval | DONALD SUNSERI |
| Deputy Wood Construction | 7/19/2018 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2018 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 8/1/2018 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 8/1/2018 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 8/22/2018 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/10/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2018 | Partial Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2018 | Not Ready for Inspection | DONALD SUNSERI |
| PLUMBING-Rough | 10/1/2018 | Partial Approval | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2018 | Partial Approval | DONALD SUNSERI |
| ELECTRICAL-Rough | 10/17/2018 | Corrections Issued | DONALD SUNSERI |
| Interior/Exterior Lathing | 10/17/2018 | Not Ready for Inspection | DONALD SUNSERI |
| ELECTRICAL-Rough | 11/29/2018 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 11/29/2018 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/29/2018 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/4/2018 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/4/2018 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/4/2018 | Approved | JOHN KIDWELL |
| HVAC-Rough | 12/4/2018 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 12/4/2018 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/4/2018 | Approved | JOHN KIDWELL |
| Drywall Nailing | 12/31/2018 | Approved | BRUCE ROZAK |
| Interior/Exterior Lathing | 12/31/2018 | Approved | BRUCE ROZAK |
| ELECTRICAL-Rough | 5/7/2019 | Not Ready for Inspection | DONALD SUNSERI |
| Underground Mechanical | 6/4/2019 | Not Ready for Inspection | DONALD SUNSERI |
| Underground Mechanical | 7/9/2019 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Final | 10/24/2019 | Partial Inspection | JOSEPH SAGEN |
| ELECTRICAL-Final | 12/24/2019 | Approved | JOSEPH SAGEN |
| Gas Test | 12/24/2019 | Approved | JOSEPH SAGEN |
| HVAC-Final | 12/24/2019 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 12/24/2019 | Approved | JOSEPH SAGEN |
| Footing/Foundation/Slab | 2/10/2020 | Approved | JOSEPH SAGEN |
| Green Building Final | 2/10/2020 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 2/10/2020 | SGSOV Approved | JOSEPH SAGEN |
| Service/Power Release | 2/10/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 2/10/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Structural Steel Frame | 2/10/2020 | Approved | JOSEPH SAGEN |
| Final | 2/24/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Service/Power Release | 2/24/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 2/24/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Service/Power Release | 4/20/2020 | Approved | JOSEPH SAGEN |
| Smoke Detectors | 5/5/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Final | 5/8/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 5/8/2020 | Approved | JOSEPH SAGEN |
| Final | 5/21/2020 | OK to Issue CofO | JOSEPH SAGEN |