5901 W SUNSET BLVD 90028

Certificate Information: 5901 W SUNSET BLVD 90028

Application / Permit
16010-10022-04681
Plan Check / Job No.
B19LA03538
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
PROPOSED OPENINGS IN THE POST TENSIONED SLABS AT LEVELS 7-13 OF A HIGHRISE BUILDING. FRAME IN THESE OPENINGS AND INFILL WITH STEEL JOIST FRAMING. PROPOSED ELEVATOR AT FIRST LEVEL. DURING THE TENANT IMPROVEMENT -ALL AREA MUST BE MADE ACCESSIBLE VIA RAMPS -PER DISABLED ACCESS REQUIREMENTNT. ORIG WORK DESCR= HIGHRISE OFFICE BLDG WITH RETAIL ON GROUND FLOOR, PARKING IN BASEMENT LEVELS AND LEVELS 2 THROUGH 5 WITH OFFICE FROM 6TH TO 13. THE PT SLABS were approved under 10010 and 10012 supplementals.
Permit Issued
Issued on 4/5/2019
Issuing Office
Metro
Current Status
Permit Finaled on 3/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2019 APPLICANT
Assigned to Plan Check Engineer 2/22/2019 JOHN VASQUEZ
Corrections Issued 2/25/2019 JOHN VASQUEZ
Quality Review Completed 2/27/2019 CHARLES CHANG
Building Plans Picked Up 2/28/2019 APPLICANT
Applicant returned to address corrections 3/27/2019 JOHN VASQUEZ
Plan Check Approved 4/3/2019 JOHN VASQUEZ
Issued 4/5/2019 LADBS
Permit Finaled 3/31/2020 DAVID BURKHEAD

Permit Application Clearance Information

CPC Cleared 3/1/2019 SOPHIE GABEL-SCHEINBAU
Project located in CRA area Cleared 3/1/2019 JIM URQUHART
Project located in CRA area Cleared 3/1/2019 JIM URQUHART
Project located in CRA area Cleared 3/1/2019 JIM URQUHART
Fire Marshall Fire Life Safety Cleared 3/15/2019 DOMINIQUE MEDINA
Green Code Cleared 3/22/2019 DONALD CRICHLOW
DAS Clearance Cleared 3/26/2019 JOHN VASQUEZ

Contact Information

Architect Sommerhalder, Olivier R; Lic. No.: C32170 844 GRANT #C      SANTA MONICA, CA 90405
Contractor Hathaway Dinwiddie Construction Company; Lic. No.: 729664-A 275 BATTERY STREET SUITE 300      SAN FRANCISCO, CA 941113330
Engineer Powers, Brian Frederick; Lic. No.: C75902 2090 WEST 31ST STREET      LOS ANGELES, CA 90018
Engineer Wilkerson, Ryan Lee; Lic. No.: S4728 20734 SARDINIA WAY      PORTER RANCH, CA 91326

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2019 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/16/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/16/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/16/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/16/2019 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/16/2019 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/17/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/17/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/17/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/17/2019 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/17/2019 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/18/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/18/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/18/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/18/2019 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/18/2019 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/19/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/19/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/19/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/19/2019 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/22/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/22/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/22/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/22/2019 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/23/2019 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/24/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/24/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/24/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/24/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 4/24/2019 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/25/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/25/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/25/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/25/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 4/25/2019 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/25/2019 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/26/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/26/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/26/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/26/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 4/26/2019 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/29/2019 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 4/29/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/29/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 4/29/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 4/29/2019 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/30/2019 Approved JEFF BYTHEWAY
Light Gage Steel Frame 5/7/2019 Partial Approval JEFF BYTHEWAY
Drywall Nailing 5/24/2019 Approved JEFF BYTHEWAY
Drywall Nailing 6/3/2019 Approved JEFF BYTHEWAY
Final 7/22/2019 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 7/22/2019 Approved JEFF BYTHEWAY
Smoke Detectors 7/22/2019 Approved JEFF BYTHEWAY