9873-9875 W RIMMELE DR 90210
Certificate Information: 9873-9875 W RIMMELE DR 90210
- Application / Permit
- 16010-10002-02408
- Plan Check / Job No.
- B24LA37270
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Construction shall not commence without CALOSHA permit SUPPLEMENTAL TO PERMIT 16010-10000-02408 TO RECHECK FOR 2023 LA CITY CODE AND REDESIGN. CHANGE THE WORK DESCRIPTION TO "(N) 1-LEVEL BASEMENT AND 3-STORY SINGLE FAMILY DWELLING WITH ATTAHCED STORAGE, RECREATION ROOM, GARAGE AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e). FIRE SPRINKLER 13D THROUG OUT."
- Permit Issued
- Issued on 6/10/2025
- Issuing Office
- Current Status
- Issued on 6/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | DANIEL YIP |
| Corrections Issued | 12/31/2024 | DANIEL YIP |
| Quality Review Completed | 1/3/2025 | KEN GILL |
| Building Plans Picked Up | 1/7/2025 | APPLICANT |
| Applicant returned to address corrections | 3/6/2025 | DANIEL YIP |
| Applicant returned to address corrections | 4/9/2025 | DANIEL YIP |
| Applicant returned to address corrections | 4/23/2025 | DANIEL YIP |
| Plan Check Approved | 6/4/2025 | DANIEL YIP |
| Issued | 6/10/2025 | APPLICANT |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 1/23/2025 | ALEX VELA |
| Private street | Cleared | 1/23/2025 | ALEX VELA |
| Hydrant and Access approval | Cleared | 1/30/2025 | JOHN CONNEALLY |
| Address approval | Cleared | 2/22/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/22/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/22/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/22/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/22/2025 | KIMBERLY HERNANDEZ |
| Work Adjacent to Public Way | Cleared | 3/5/2025 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2025 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 3/12/2025 | KIMBERLY HERNANDEZ |
| GPI Written Notices | Cleared | 4/17/2025 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 4/17/2025 | DANIEL YIP |
| Low Impact Development | Cleared | 5/15/2025 | DANIEL LEON-MENDOZA |
| Roof/Waste drainage to street | Cleared | 5/23/2025 | CINDY QI |
Contact Information
| Architect | Elmanovich,, Vladimir; Lic. No.: C25822 | 134 N WESTGATE AVE LOS ANGELES, CA 90049 |
| Contractor | Newform Construction Company; Lic. No.: 833302-B | 7405 DEL ZURO DRIVE LOS ANGELES, CA 90046 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 6/12/2025 | Not Ready for Inspection | SEAN HAUPT |
| Piling/Pier/Caisson | 6/12/2025 | Not Ready for Inspection | SEAN HAUPT |
| Reinforced Concrete Frame | 6/12/2025 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 6/12/2025 | Not Ready for Inspection | SEAN HAUPT |
| Piling/Pier/Caisson | 6/13/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 6/17/2025 | Approved | SEAN HAUPT |
| Piling/Pier/Caisson | 6/17/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 6/18/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 6/23/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Shotcrete | 6/24/2025 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 6/30/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/2/2025 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 7/10/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/11/2025 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 7/23/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/28/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 8/14/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 8/22/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 8/22/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 9/3/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 9/15/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/17/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 10/1/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 10/1/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 10/6/2025 | Partial Approval | DANIEL VERA |
| Deputy Shotcrete | 10/7/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 10/20/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 10/21/2025 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/30/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 10/31/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 11/3/2025 | Partial Approval | DANIEL VERA |
| Deputy Reinf. Concrete | 11/4/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 11/10/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 11/12/2025 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 11/24/2025 | Partial Approval | SEAN HAUPT |
| Special/Order Compliance | 11/24/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 11/25/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 12/1/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 1/9/2026 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/9/2026 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/13/2026 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 1/14/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/22/2026 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 2/10/2026 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Steel/Welding | 2/13/2026 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/24/2026 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Steel/Welding | 2/25/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 3/20/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 3/26/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 3/31/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/7/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/10/2026 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 4/13/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/15/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 4/17/2026 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 5/4/2026 | Conditional Approval | CARLOS MATAMOROS |