1541 N WILCOX AVE 90028
Certificate Information: 1541 N WILCOX AVE 90028
- Application / Permit
- 16010-10002-01151
- Plan Check / Job No.
- B18LA04302
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- SUPPLEMENTAL TO PERMIT #16010-10000-01151 FOR MAJOR ARCHITECTURAL AND STRUCTURAL REVISIONS; ADD A PARTIAL LEVEL 2 BUT REMOVE ENTIRE LEVEL 3, REDUCE THE NUMBER OF UNITS FROM 200 TO 190, ADDITIONAL 10' SETBACK ALONG PROPERTY LINE, REMOVE MECHANICAL PARKING, REVISE LAYOUT ALL LEVELS INCLUDING ROOFTOP PENTHOUSE. NO FEE, PROJECT VALUATION IS LESS THAN ORIGINAL PERMIT. ORIGINALLY A 10 STORY TYPE IA HIGHRISE HOTEL W/GROUND LEVEL RESTAURANT OVER 3 LEVELS OF TYPE IA SUBTERRANEAN PARKING. RESTAURANT PORTION IS CORE AND SHELL ONLY.
- Permit Issued
- Issued on 8/31/2018
- Issuing Office
- Metro
- Current Status
- Issued on 8/31/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/13/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 3/22/2018 | APPLICANT |
| Green Plans Picked Up | 4/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2018 | MINYE PAK |
| Corrections Issued | 4/30/2018 | MINYE PAK |
| Quality Review Completed | 5/2/2018 | BILL STUTSMAN |
| Applicant returned to address corrections | 6/1/2018 | MINYE PAK |
| Applicant returned to address corrections | 6/7/2018 | MINYE PAK |
| Applicant returned to address corrections | 6/20/2018 | MINYE PAK |
| Applicant returned to address corrections | 8/14/2018 | MINYE PAK |
| Plan Check Approved | 8/31/2018 | MINYE PAK |
| Issued | 8/31/2018 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2018 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/2/2018 | STEVE MELGAR |
| Green Code | Cleared | 7/9/2018 | COLIN LOREDO |
| Bicycle Parking | Cleared | 7/17/2018 | FATIMA GUERRA |
| Encroachment in public way | Cleared | 7/17/2018 | FATIMA GUERRA |
| Sewer availability | Cleared | 7/26/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 7/30/2018 | MARTIN FRAGOSO |
| DAS Clearance | Cleared | 8/2/2018 | MINYE PAK |
| ZI | Cleared | 8/3/2018 | EDBER MACEDO |
| Project located in CRA area | Cleared | 8/6/2018 | JIM URQUHART |
| "D" conditions | Cleared | 8/7/2018 | EDBER MACEDO |
| "Q" conditions | Cleared | 8/7/2018 | EDBER MACEDO |
| "T" removal | Cleared | 8/7/2018 | EDBER MACEDO |
| CPC | Cleared | 8/7/2018 | EDBER MACEDO |
| Frnt yard landscape/Water mgmt | Cleared | 8/7/2018 | EDBER MACEDO |
| Site Plan review | Cleared | 8/7/2018 | EDBER MACEDO |
| Fire Marshall Fire Life Safety | Cleared | 8/30/2018 | ANDREW KO |
Contact Information
| Architect | Ha, Simon Y; Lic. No.: C31188 | 7902 LOUISE LANE LA PALMA, CA 90623 |
| Contractor | Suffolk Construction Company Inc; Lic. No.: 751099-B | 390 FREMONT STREET SAN FRANCISCO, CA 94105 |
| Engineer | Hoda, Erzen Galip; Lic. No.: S5577 | 3621 HARBOR BLVD 125 SANTA ANA, CA 92704 |
| Engineer | Petroni, Matthew Brian; Lic. No.: C69473 | 1809 GOODMAN AVE REDONDO BEACH, CA 90278 |
| Engineer | Walter, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/25/2018 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 7/29/2021 | Approved | DAVID BURKHEAD |
| Final | 7/29/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Reinforced Concrete Frame | 7/29/2021 | Approved | DAVID BURKHEAD |
| Structural Steel Frame | 7/29/2021 | Approved | DAVID BURKHEAD |