1429 S BEDFORD ST 90035

Certificate Information: 1429 S BEDFORD ST 90035

Application / Permit
16010-10000-06358
Plan Check / Job No.
B16LA20718
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 8 UNIT, TYPE VA, 4-STORY APARTMENT BUILDING OVER TYPE 1A, 1-STORY SUBTERRANEAN GARAGE
Permit Issued
Issued on 4/30/2021
Issuing Office
Metro
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2016 APPLICANT
Disabled Access Plans Picked Up 2/2/2017 APPLICANT
Assigned to Plan Check Engineer 2/23/2017 PRANITA SHAH
Green Plans Picked Up 3/14/2017 APPLICANT
Corrections Issued 3/16/2017 PRANITA SHAH
Quality Review Completed 3/24/2017 LARRY LEE
Applicant returned to address corrections 5/1/2017 PRANITA SHAH
Applicant returned to address corrections 6/16/2017 PRANITA SHAH
Applicant returned to address corrections 6/28/2017 PRANITA SHAH
Applicant returned to address corrections 12/20/2017 PRANITA SHAH
Applicant returned to address corrections 12/28/2017 PRANITA SHAH
Applicant returned to address corrections 1/8/2018 PRANITA SHAH
Applicant returned to address corrections 1/18/2018 PRANITA SHAH
Applicant returned to address corrections 1/30/2018 PRANITA SHAH
Applicant returned to address corrections 3/7/2018 PRANITA SHAH
Applicant returned to address corrections 9/6/2018 PRANITA SHAH
Plan Check Approved 9/20/2018 PRANITA SHAH
Issued 4/30/2021 APPLICANT
Building Plans Picked Up 5/5/2021 APPLICANT
TCO Issued (Expire Date: 07-15-2025) 1/16/2025 DAVID TSAU
CofO Issued 6/23/2025 HENRY BAGHDASSARIAN
Permit Finaled 6/23/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 6/16/2017 SEVAK ISAKHAYAN
ZI Cleared 7/28/2017 JOHN DACEY
Eng Process Fee Ord 176,300 Cleared 7/31/2017 ANDREW SLUSSER
"Q" conditions Cleared 8/18/2017 DANALYNN DOMINGUEZ
Frnt yard landscape/Water mgmt Cleared 8/18/2017 DANALYNN DOMINGUEZ
Permit Cleared 8/18/2017 LINDA MARGARET
Sewer availability Cleared 8/18/2017 NAZILA NOORIFAR
Green Code Cleared 8/25/2017 RICHARD DOCKUS
Internal circulation Cleared 8/25/2017 TAIMOUR TANAVOLI
Miscellaneous Cleared 8/25/2017 LINDA MARGARET
Miscellaneous Cleared 8/25/2017 TAIMOUR TANAVOLI
Highway dedication Cleared 9/7/2017 JAMES MORALEZ
Opn space landscape/Water mgmt Cleared 9/12/2017 DANALYNN DOMINGUEZ
Hydrant and Access approval Cleared 10/30/2017 ROBERT DUFF
DAS Clearance Cleared 11/2/2017 SOMKIAT SUPANYACHOTSKUL
Low Impact Development Cleared 12/19/2017 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 12/19/2017 ADRIAN SANCHEZ
Building over 3-story or 36-ft Cleared 12/20/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/20/2017 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 5/1/2018 PEJMAN NOORI
Work Adjacent to Public Way Cleared 9/20/2018 BOK GOH

Contact Information

Architect Goodarzi,, Morteza; Lic. No.: C23941       ,
Contractor Chase Construction Inc; Lic. No.: 700816-B 1825 PANDORA AVE      LOS ANGELES, CA 90025
Engineer Eftekhari, Hossein; Lic. No.: C50121 5945 SETTLER COURT      ANAHEIM, CA 92807
Engineer Gorbin, James D; Lic. No.: S5859 210 S JUANITA AVE A      REDONDO BEACH, CA 90277

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2021 Approved JEFF BYTHEWAY
Pre-Inspection 2/8/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 2/17/2022 Partial Approval JEFF BYTHEWAY
METHANE-Barrier 2/17/2022 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 2/17/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Concrete 2/24/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/24/2022 Partial Approval GRANT WOODS
METHANE-Barrier 2/24/2022 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 2/24/2022 Not Ready for Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 3/11/2022 Partial Approval GRANT WOODS
METHANE-Barrier 3/11/2022 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 3/11/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Concrete 3/14/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 3/17/2022 Partial Inspection GRANT WOODS
METHANE-Barrier 3/17/2022 Not Ready for Inspection GRANT WOODS
METHANE-Subgrade 3/17/2022 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 3/23/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 3/23/2022 Partial Approval JEFF BYTHEWAY
METHANE-Barrier 3/23/2022 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 3/23/2022 Not Ready for Inspection JEFF BYTHEWAY
Deputy Shotcrete 3/24/2022 Approved JEFF BYTHEWAY
Deputy Shotcrete 3/25/2022 Approved JEFF BYTHEWAY
METHANE-Barrier 3/29/2022 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Subgrade 3/29/2022 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 3/29/2022 Not Ready for Inspection JEFF BYTHEWAY
Green Building Rough 3/30/2022 Not Ready for Inspection JEFF BYTHEWAY
METHANE-Rough 3/30/2022 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 3/30/2022 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 3/30/2022 Approved JEFF BYTHEWAY
Deputy Shotcrete 3/31/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 4/13/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/14/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 4/15/2022 Partial Approval GRANT WOODS
METHANE-Barrier 4/15/2022 Not Ready for Inspection GRANT WOODS
METHANE-Subgrade 4/15/2022 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 4/19/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/9/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/12/2022 Approved JEFF BYTHEWAY
METHANE-Barrier 5/12/2022 Approved JEFF BYTHEWAY
METHANE-Subgrade 5/12/2022 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 5/12/2022 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 5/17/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/24/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/25/2022 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 6/1/2022 Partial Approval NICK LAROCCA
Green Building Rough 6/1/2022 Approved NICK LAROCCA
METHANE-Rough 6/1/2022 Not Ready for Inspection NICK LAROCCA
Reinforced Concrete Frame 6/1/2022 Partial Inspection NICK LAROCCA
Deputy Reinf. Concrete 6/2/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 6/7/2022 Approved JEFF BYTHEWAY
Masonry Wall/Backfill 6/8/2022 Approved JEFF BYTHEWAY
METHANE-Rough 6/27/2022 Partial Inspection SORIN CIRSTOIU
Wood Frame 6/27/2022 Conditional Approval SORIN CIRSTOIU
METHANE-Rough 7/7/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 7/7/2022 Partial Approval GRANT WOODS
METHANE-Rough 7/20/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 7/20/2022 Partial Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 8/8/2022 Partial Approval GRANT WOODS
METHANE-Rough 8/23/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 8/23/2022 Not Ready for Inspection GRANT WOODS
METHANE-Rough 8/25/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 8/25/2022 Partial Approval GRANT WOODS
Insulation 9/8/2022 Partial Approval GRANT WOODS
Insulation 9/14/2022 Partial Approval GRANT WOODS
METHANE-Rough 9/20/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 9/20/2022 Partial Approval GRANT WOODS
Insulation 10/25/2022 Corrections Issued SORIN CIRSTOIU
Insulation 10/27/2022 Partial Approval GRANT WOODS
Insulation 11/1/2022 Partial Approval GRANT WOODS
Drywall Nailing 11/2/2022 Partial Approval JOEY BUCHANAN
Drywall Nailing 11/14/2022 Partial Approval GRANT WOODS
METHANE-Rough 12/16/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 12/16/2022 Not Ready for Inspection GRANT WOODS
Deputy Methane Barrier 1/6/2023 Conditional Approval GRANT WOODS
Interior/Exterior Lathing 1/24/2023 Not Ready for Inspection GRANT WOODS
Drywall Nailing 1/27/2023 Partial Approval GRANT WOODS
Drywall Nailing 1/31/2023 Partial Approval AMANUEL BERHE
Drywall Nailing 2/6/2023 Approved AMANUEL BERHE
Interior/Exterior Lathing 2/22/2023 Conditional Approval SHAVONNE ESPINOZA
Footing/Foundation/Slab 3/2/2023 Partial Approval GRANT WOODS
METHANE-Rough 3/9/2023 Not Ready for Inspection GRANT WOODS
Wood Frame 3/9/2023 Partial Inspection GRANT WOODS
METHANE-Rough 5/16/2023 Not Ready for Inspection GRANT WOODS
Deputy Methane Barrier 6/13/2023 Conditional Approval GRANT WOODS
METHANE-Final 6/13/2023 Partial Approval GRANT WOODS
Footing/Foundation/Slab 6/26/2023 Partial Approval GRANT WOODS
METHANE-Rough 5/1/2024 Partial Approval RICARDO ROBLES
Special/Order Compliance 5/1/2024 Partial Approval RICARDO ROBLES
Final 1/13/2025 Partial Approval RICARDO ROBLES
Footing/Foundation/Slab 1/13/2025 Approved RICARDO ROBLES
Green Building Final 1/13/2025 Approved RICARDO ROBLES
METHANE-Final 1/13/2025 Approved RICARDO ROBLES
METHANE-Rough 1/13/2025 Approved RICARDO ROBLES
Reinforced Concrete Frame 1/13/2025 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Approved RICARDO ROBLES
Smoke Detectors 1/13/2025 Approved RICARDO ROBLES
Wood Frame 1/13/2025 Approved RICARDO ROBLES
Final 1/16/2025 OK for TCO RICARDO ROBLES
Final 2/24/2025 Conditional Approval GRANT WOODS
Final 4/10/2025 Corrections Issued RICARDO ROBLES
Special/Order Compliance 6/17/2025 Partial Inspection PAUL DAVIDSON