Pre-Inspection
|
12/8/2020
|
Approved
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
12/11/2020
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
1/19/2021
|
Conditional Approval
|
THOMAS LOGRASSO
|
|
Piling/Pier/Caisson
|
3/8/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
3/12/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
3/17/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
3/17/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
3/19/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
3/23/2021
|
Approved
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
4/9/2021
|
Partial Inspection
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
4/14/2021
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
4/20/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
4/23/2021
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
4/23/2021
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Deputy Drilled-In Anchors
|
4/27/2021
|
Conditional Approval
|
CHRISTOPHER DELLEFIELD
|
|
Excavation/Setback/Form/Re-Bar
|
4/29/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
5/10/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
5/10/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
5/28/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
5/28/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
6/4/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
6/7/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Underground Mechanical
|
8/5/2021
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2021
|
Partial Approval
|
CRAIG DAVIS
|
|
Footing/Foundation/Slab
|
10/12/2021
|
Partial Approval
|
KATHRYN BUTTERWORTH
|
|
Underground Mechanical
|
10/14/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
10/18/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Underground Mechanical
|
10/18/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
12/16/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
12/16/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
1/13/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/3/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
3/3/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
HVAC-Rough
|
3/11/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
HVAC-Rough
|
3/18/2022
|
Approved
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
3/18/2022
|
Approved
|
OSVALDO PARAMO
|
|
Deputy Wood Construction
|
3/23/2022
|
Conditional Approval
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
3/30/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/30/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
Shower Pan
|
3/30/2022
|
Approved
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
4/5/2022
|
Approved
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/5/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
4/5/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Sewer
|
4/22/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/26/2022
|
Approved
|
OSVALDO PARAMO
|
|
Sewer
|
4/26/2022
|
Approved
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/5/2022
|
Approved
|
OSVALDO PARAMO
|
|
Sewer
|
5/5/2022
|
Approved
|
OSVALDO PARAMO
|
|
BUILDING-Rough-Frame
|
6/10/2022
|
Approved
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/10/2022
|
Approved
|
OSVALDO PARAMO
|
|
Green Building Rough
|
6/10/2022
|
Approved
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
6/10/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
Verify Sprinkler Sign Off
|
6/10/2022
|
Approved
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
6/16/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
6/23/2022
|
Approved
|
OSVALDO PARAMO
|
|
Insulation
|
7/11/2022
|
Approved
|
OSVALDO PARAMO
|
|
Drywall Nailing
|
7/18/2022
|
Approved
|
AMY COLIN
|
|
HVAC-Final
|
11/4/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
ELECTRICAL-Final
|
11/9/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
HVAC-Final
|
11/9/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Gas Test
|
11/10/2022
|
Approved
|
OSVALDO PARAMO
|
|
PLUMBING-Final
|
11/10/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
ELECTRICAL-Final
|
11/30/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
HVAC-Final
|
11/30/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
ELECTRICAL-Final
|
12/5/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
HVAC-Final
|
12/5/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
ELECTRICAL-Final
|
12/9/2022
|
Approved
|
OSVALDO PARAMO
|
|
HVAC-Final
|
12/9/2022
|
Approved
|
OSVALDO PARAMO
|
|
Special/Order Compliance
|
12/19/2022
|
Approved
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
6/2/2023
|
Approved
|
OSVALDO PARAMO
|
|
PLUMBING-Final
|
6/2/2023
|
Approved
|
OSVALDO PARAMO
|
|
Reinforced Concrete Frame
|
6/2/2023
|
Approved
|
OSVALDO PARAMO
|
|
Final
|
8/11/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
Green Building Final
|
8/11/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
SGSOV-Seismic Gas S/O Valve
|
8/11/2023
|
SGSOV Not Required
|
ALIZAH MAYAGOITIA
|
|
Service/Power Release
|
8/11/2023
|
Not Ready for Inspection
|
ALIZAH MAYAGOITIA
|
|
Smoke Detectors
|
8/11/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Final
|
8/15/2023
|
OK to Issue CofO
|
OSVALDO PARAMO
|
|
Service/Power Release
|
8/15/2023
|
Approved
|
OSVALDO PARAMO
|