927 N EVERETT ST 90026

Certificate Information: 927 N EVERETT ST 90026

Application / Permit
16010-10000-06193
Plan Check / Job No.
B16LA20522
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
NEW 2 STORY, TYPE VB, CORE & SHELL COMMERCIAL BUILDING WITH RESTAURANT AT 1ST FLOOR & OFFICE AT 2ND FLOOR FOR A SINGLE TENANT USE ONLY. (SEE COMMENTS)
Permit Issued
Issued on 5/24/2018
Issuing Office
San Pedro
Current Status
CofO Issued on 5/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2016 APPLICANT
Green Plans Picked Up 2/13/2017 APPLICANT
Assigned to Plan Check Engineer 2/23/2017 PRANITA SHAH
Corrections Issued 3/22/2017 PRANITA SHAH
Quality Review Completed 3/24/2017 LARRY LEE
Building Plans Picked Up 3/28/2017 APPLICANT
Disabled Access Plans Picked Up 3/28/2017 APPLICANT
Applicant returned to address corrections 5/16/2017 PRANITA SHAH
Applicant returned to address corrections 7/25/2017 PRANITA SHAH
Plan Check Approved 9/22/2017 PRANITA SHAH
Issued 5/24/2018 LADBS
CofO in Progress 4/26/2023 RAFAEL ESPINOZA
CofO Issued 5/4/2023 ERNESTO CORRAL
Permit Finaled 5/4/2023 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/21/2017 ALFREDO JARA
Hydrant and Access approval Cleared 4/21/2017 JOHN CONNEALLY
Permit Cleared 4/21/2017 ALFREDO JARA
Green Code Cleared 5/18/2017 MICKEY YAMASHITA
Sewer availability Cleared 6/5/2017 CARLA VALLADARES
Highway dedication Cleared 6/28/2017 JAMES MORALEZ
DAS Clearance Cleared 7/14/2017 EDDIE GARIN
Bicycle Parking Cleared 9/19/2017 EILEEN HUNT
Bicycle Parking Cleared 9/20/2017 JAMES KHO
Work Adjacent to Public Way Cleared 9/20/2017 JAMES KHO
Low Impact Development Cleared 9/22/2017 SAM NAVID
Roof/Waste drainage to street Cleared 9/22/2017 STEVE MELGAR

Contact Information

Architect Lu, Alan S; Lic. No.: C34631 1155 S GRAND AVENUE   # 407    LOS ANGELES, CA 90015
Contractor Forte Build & Design Inc; Lic. No.: 1026084-B 1545 N VERDUGO RD   #104    GLENDALE, CA 91208
Engineer Aoanan, Virgilio Cendana; Lic. No.: C36079 3951 MEDFORD ST      LOS ANGELES, CA 90063
Engineer Nam, Young-Keun; Lic. No.: S4029 17 SANTA EUGENIA      IRVINE, CA 92606
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Carnegie, Vincent John; Lic. No.: EG1608 P.O. BOX 5444      GLENDALE, CA 912012036

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/3/2018 Approved ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 8/29/2018 Not Ready for Inspection NICK DANERI
Piling/Pier/Caisson 9/27/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 9/28/2018 Conditional Approval ERNESTO CORRAL
Piling/Pier/Caisson 9/28/2018 No Access for Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/2/2018 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 10/2/2018 Not Ready for Inspection ERNESTO CORRAL
METHANE-Subgrade 10/2/2018 Not Ready for Inspection ERNESTO CORRAL
Piling/Pier/Caisson 10/2/2018 Partial Inspection ERNESTO CORRAL
Deputy Other (see comments) 10/10/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/10/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 4/4/2019 Not Ready for Inspection ERNESTO CORRAL
METHANE-Barrier 4/4/2019 Not Ready for Inspection ERNESTO CORRAL
METHANE-Subgrade 4/4/2019 Not Ready for Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 4/5/2019 Not Ready for Inspection JEFFREY FULTON
Piling/Pier/Caisson 4/22/2019 Not Ready for Inspection JEFFREY FULTON
Wood Frame 4/22/2019 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 4/23/2019 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 4/26/2019 Corrections Issued JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/3/2019 Not Ready for Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 5/6/2019 Partial Inspection ERNESTO CORRAL
Masonry Wall/Backfill 5/21/2019 Corrections Issued JEFFREY FULTON
Masonry Wall/Backfill 5/23/2019 Not Ready for Inspection JEFFREY FULTON
Masonry Wall/Backfill 5/24/2019 Corrections Issued JEFFREY FULTON
Masonry Wall/Backfill 7/11/2019 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/30/2019 No Access for Inspection JEFFREY FULTON
METHANE-Barrier 8/30/2019 No Access for Inspection JEFFREY FULTON
METHANE-Subgrade 8/30/2019 No Access for Inspection JEFFREY FULTON
Reinforced Concrete Frame 9/3/2019 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 9/5/2019 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 9/9/2019 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 9/12/2019 Corrections Issued JEFFREY FULTON
Reinforced Concrete Frame 9/13/2019 No Access for Inspection JEFFREY FULTON
Deputy Wood Construction 10/15/2019 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/15/2019 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 11/6/2019 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/6/2019 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/25/2019 Partial Inspection JEFFREY FULTON
Green Building Rough 2/24/2020 Not Ready for Inspection RONALD PACHECO
METHANE-Rough 2/24/2020 Not Ready for Inspection RONALD PACHECO
Verify Sprinkler Sign Off 2/24/2020 Not Ready for Inspection RONALD PACHECO
Wood Frame 2/24/2020 Not Ready for Inspection RONALD PACHECO
Deputy Wood Construction 2/25/2020 Conditional Approval LANNY MERRICK
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Partial Approval RONALD PACHECO
Interior/Exterior Lathing 3/9/2020 Conditional Approval LEOPOLDO MENDOZA
Green Building Rough 3/24/2020 Not Ready for Inspection RONALD PACHECO
METHANE-Rough 3/24/2020 Not Ready for Inspection RONALD PACHECO
Verify Sprinkler Sign Off 3/24/2020 Not Ready for Inspection RONALD PACHECO
Wood Frame 3/24/2020 Not Ready for Inspection RONALD PACHECO
Green Building Rough 6/22/2020 Approved RONALD PACHECO
METHANE-Rough 6/22/2020 Not Ready for Inspection RONALD PACHECO
Verify Sprinkler Sign Off 6/22/2020 Partial Approval RONALD PACHECO
Wood Frame 6/22/2020 Partial Approval RONALD PACHECO
Insulation 6/25/2020 Approved LANNY MERRICK
METHANE-Rough 6/26/2020 Not Ready for Inspection LANNY MERRICK
Verify Sprinkler Sign Off 6/26/2020 Not Ready for Inspection LANNY MERRICK
Wood Frame 6/26/2020 Conditional Approval LANNY MERRICK
Drywall Nailing 7/6/2020 Partial Approval LANNY MERRICK
Pre-Inspection 7/15/2020 Not Ready for Inspection LANNY MERRICK
Excavation/Setback/Form/Re-Bar 8/24/2020 Not Ready for Inspection LANNY MERRICK
Excavation/Setback/Form/Re-Bar 8/25/2020 Approved LANNY MERRICK
Interior/Exterior Lathing 10/19/2020 Partial Approval RONALD PACHECO
Pre-Inspection 7/14/2022 No Access for Inspection RAFAEL ESPINOZA
Pre-Inspection 7/15/2022 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 2/27/2023 Approved RAFAEL ESPINOZA
Final 2/27/2023 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Final 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 2/27/2023 Approved RAFAEL ESPINOZA
Structural Steel Frame 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/27/2023 Approved RAFAEL ESPINOZA
Wood Frame 2/27/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 4/7/2023 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/7/2023 Approved RAFAEL ESPINOZA
Green Building Final 4/7/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 4/7/2023 Approved RAFAEL ESPINOZA
METHANE-Final 4/7/2023 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 4/7/2023 Approved RAFAEL ESPINOZA
METHANE-Subgrade 4/7/2023 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 4/7/2023 Conditional Approval RAFAEL ESPINOZA
Structural Steel Frame 4/7/2023 Conditional Approval RAFAEL ESPINOZA
Wood Frame 4/7/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 4/19/2023 No Access for Inspection RAFAEL ESPINOZA
Green Building Final 4/19/2023 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Final 4/19/2023 Approved RAFAEL ESPINOZA
METHANE-Rough 4/19/2023 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 4/19/2023 Approved RAFAEL ESPINOZA
Structural Steel Frame 4/19/2023 Approved RAFAEL ESPINOZA
Wood Frame 4/19/2023 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 4/20/2023 Partial Inspection RAFAEL ESPINOZA
Final 4/25/2023 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 4/25/2023 Approved RAFAEL ESPINOZA
Wood Frame 4/25/2023 Approved RAFAEL ESPINOZA