Grading Pre-Inspection
|
8/3/2018
|
Approved
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
8/29/2018
|
Not Ready for Inspection
|
NICK DANERI
|
|
Piling/Pier/Caisson
|
9/27/2018
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
9/28/2018
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Piling/Pier/Caisson
|
9/28/2018
|
No Access for Inspection
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
10/2/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
METHANE-Barrier
|
10/2/2018
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
METHANE-Subgrade
|
10/2/2018
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Piling/Pier/Caisson
|
10/2/2018
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Other (see comments)
|
10/10/2018
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/10/2018
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
4/4/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
METHANE-Barrier
|
4/4/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
METHANE-Subgrade
|
4/4/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
4/5/2019
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Piling/Pier/Caisson
|
4/22/2019
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
4/22/2019
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
4/23/2019
|
Partial Inspection
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
4/26/2019
|
Corrections Issued
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
5/3/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
5/6/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Masonry Wall/Backfill
|
5/21/2019
|
Corrections Issued
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
5/23/2019
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
5/24/2019
|
Corrections Issued
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
7/11/2019
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
8/30/2019
|
No Access for Inspection
|
JEFFREY FULTON
|
|
METHANE-Barrier
|
8/30/2019
|
No Access for Inspection
|
JEFFREY FULTON
|
|
METHANE-Subgrade
|
8/30/2019
|
No Access for Inspection
|
JEFFREY FULTON
|
|
Reinforced Concrete Frame
|
9/3/2019
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Reinforced Concrete Frame
|
9/5/2019
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Reinforced Concrete Frame
|
9/9/2019
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Reinforced Concrete Frame
|
9/12/2019
|
Corrections Issued
|
JEFFREY FULTON
|
|
Reinforced Concrete Frame
|
9/13/2019
|
No Access for Inspection
|
JEFFREY FULTON
|
|
Deputy Wood Construction
|
10/15/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/15/2019
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Wood Construction
|
11/6/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2019
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/25/2019
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
2/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
METHANE-Rough
|
2/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Verify Sprinkler Sign Off
|
2/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Wood Frame
|
2/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Deputy Wood Construction
|
2/25/2020
|
Conditional Approval
|
LANNY MERRICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/26/2020
|
Partial Approval
|
RONALD PACHECO
|
|
Interior/Exterior Lathing
|
3/9/2020
|
Conditional Approval
|
LEOPOLDO MENDOZA
|
|
Green Building Rough
|
3/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
METHANE-Rough
|
3/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Verify Sprinkler Sign Off
|
3/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Wood Frame
|
3/24/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Green Building Rough
|
6/22/2020
|
Approved
|
RONALD PACHECO
|
|
METHANE-Rough
|
6/22/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Verify Sprinkler Sign Off
|
6/22/2020
|
Partial Approval
|
RONALD PACHECO
|
|
Wood Frame
|
6/22/2020
|
Partial Approval
|
RONALD PACHECO
|
|
Insulation
|
6/25/2020
|
Approved
|
LANNY MERRICK
|
|
METHANE-Rough
|
6/26/2020
|
Not Ready for Inspection
|
LANNY MERRICK
|
|
Verify Sprinkler Sign Off
|
6/26/2020
|
Not Ready for Inspection
|
LANNY MERRICK
|
|
Wood Frame
|
6/26/2020
|
Conditional Approval
|
LANNY MERRICK
|
|
Drywall Nailing
|
7/6/2020
|
Partial Approval
|
LANNY MERRICK
|
|
Pre-Inspection
|
7/15/2020
|
Not Ready for Inspection
|
LANNY MERRICK
|
|
Excavation/Setback/Form/Re-Bar
|
8/24/2020
|
Not Ready for Inspection
|
LANNY MERRICK
|
|
Excavation/Setback/Form/Re-Bar
|
8/25/2020
|
Approved
|
LANNY MERRICK
|
|
Interior/Exterior Lathing
|
10/19/2020
|
Partial Approval
|
RONALD PACHECO
|
|
Pre-Inspection
|
7/14/2022
|
No Access for Inspection
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
7/15/2022
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
2/27/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Final
|
2/27/2023
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Barrier
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Final
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Rough
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Subgrade
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
2/27/2023
|
SGSOV Approved
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
2/27/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Structural Steel Frame
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
2/27/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
2/27/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
4/7/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
4/7/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
4/7/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Barrier
|
4/7/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
METHANE-Final
|
4/7/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
METHANE-Rough
|
4/7/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
METHANE-Subgrade
|
4/7/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
4/7/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Structural Steel Frame
|
4/7/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/7/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
4/19/2023
|
No Access for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
4/19/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Final
|
4/19/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
METHANE-Rough
|
4/19/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Reinforced Masonry Frame
|
4/19/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Structural Steel Frame
|
4/19/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/19/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Pre-Inspection
|
4/20/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
4/25/2023
|
OK to Issue CofO
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
4/25/2023
|
Approved
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/25/2023
|
Approved
|
RAFAEL ESPINOZA
|