3101 N BELDEN DR 90068

Certificate Information: 3101 N BELDEN DR 90068

Application / Permit
16010-10000-06192
Plan Check / Job No.
B16LA20514
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED 4-CAR GARAGE W/LIFT
Permit Issued
Issued on 6/19/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2016 APPLICANT
Assigned to Plan Check Engineer 2/23/2017 MANUEL MONTUFAR
Green Plans Picked Up 3/7/2017 APPLICANT
Corrections Issued 3/14/2017 EDMOND HAGOPYAN
Quality Review Completed 3/22/2017 CELESTE MORRIS
Building Plans Picked Up 3/23/2017 APPLICANT
Applicant returned to address corrections 12/29/2017 EDMOND HAGOPYAN
Plan Check Approved 6/19/2019 MANUEL MONTUFAR
Issued 6/19/2019 LADBS
CofO in Progress 2/14/2024 BRIAN SULLIVAN
Permit Finaled 2/19/2024 DEROLD HAUFF
CofO Issued 2/19/2024 DEROLD HAUFF
Permit Finaled 2/19/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/10/2017 CARLA VALLADARES
Eng Process Fee Ord 176,300 Cleared 4/10/2017 CARLA VALLADARES
Roof/Waste drainage to street Cleared 8/23/2018 CELINA MORENO
Work Adjacent to Public Way Cleared 8/23/2018 BOK GOH
Green Code Cleared 6/14/2019 SEAN DANG
Miscellaneous Cleared 6/14/2019 EDUARDO HERMOSO
Miscellaneous Cleared 6/14/2019 GEORGE SUCHAND
Specific Plan Cleared 6/14/2019 DIANA JIMENEZ
GPI Written Notices Cleared 6/17/2019 MANUEL MONTUFAR
Grading Pre-Inspection Cleared 6/17/2019 CELESTE NGUYEN
Miscellaneous Cleared 6/17/2019 RICHARD REASER

Contact Information

Contractor Owner-Builder       ,
Engineer Abrahamian,, Zaven; Lic. No.: C41672 237 S LAMER ST      BURBANK, CA 91506
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 2/9/2022 Approved BRIAN SULLIVAN
Deputy Reinf. Concrete 3/9/2022 Conditional Approval RUBEN SALAS
Excavation/Setback/Form/Re-Bar 4/4/2022 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/5/2022 Partial Approval BRIAN SULLIVAN
Special/Order Compliance 8/2/2022 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 12/6/2022 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 12/9/2022 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/9/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Reinf. Concrete 3/9/2023 Conditional Approval STUART CHAPMAN
Deputy Drilled-In Anchors 3/31/2023 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/6/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 7/6/2023 Approved BRIAN SULLIVAN
Sewer 7/6/2023 Approved BRIAN SULLIVAN
Final 12/18/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 12/18/2023 Approved BRIAN SULLIVAN
Green Building Final 12/18/2023 Approved BRIAN SULLIVAN
Green Building Rough 12/18/2023 Approved BRIAN SULLIVAN
Reinforced Masonry Frame 12/18/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 12/18/2023 Approved BRIAN SULLIVAN
Smoke Detectors 12/18/2023 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 12/18/2023 Approved BRIAN SULLIVAN
Final 2/14/2024 OK to Issue CofO BRIAN SULLIVAN